Vancouver Sun

No shift in B.C.’s tailing pond strategy

All 10 active mine proposals call for traditiona­l dams.

- GORDON HOEKSTRA

After the catastroph­ic failure of the Mount Polley mine tailings dam last summer, an expert engineerin­g panel appointed by the B.C. government called for a major shift in how to deal with mine waste.

The panel recommende­d a move away from the convention­al method of storing waste behind dams. But companies in British Columbia with proposals for large, open-pit metal mines have no plans, at least for now, to follow the panel’s recommenda­tion, a review by The Vancouver Sun has found.

Among the convention­al proposals is Seabridge Gold’s $5.4-billion KSM copper-gold project that includes a 239metre-high earth dam, which would be among the highest in the world. It would store more than two billion tonnes of tailings under water, 27 times more than the amount of tailings stored at Mount Polley northeast of Williams Lake in the Interior.

The KSM mine has already been approved by the B.C. and Canadian government­s, and the company is seeking a partner to finance the massive project.

Like Seabridge’s planned mine, all large mines in British Columbia have stored tailings — the finely ground rock remaining after metals are extracted — under water, behind earth-and-rock dams. The purpose is usually two-fold: it keeps potentiall­y acid- generating mine waste from exposure to air and leaching into the environmen­t, and it provides a supply of water to run the plant that grinds and extracts metal from the rocks. The panel said, however, that to reduce dam failures, the number of dams must be reduced.

So, it recommende­d an alternativ­e method of filtering the water out of the tailings and then stacking them in a big pile, a method commonly called dry stacking.

The result is there is no dam to fail, and if a dry stack shifted or moved, including as a result of an earthquake, it would not go as far as water-saturated tailings. The Mount Polley dam failure released millions of cubic metres of water and tailings into the Quesnel watershed, destroying a nine-kilometre creek and raising concerns about the long-term effects on millions of salmon.

The panel pointed to the Greens Creek silver-gold undergroun­d mine in Alaska, which has used filtered tailings and dry stacking for decades.

However, all 10 of the active open-pit metal mine proposals either approved or on the province’s assessment list have plans to build convention­al storage facilities with dams to store tailings.

Mining companies say filtering and dry stacking won’t work in B.C. — there’s too much rain and it is too costly.

There are several proposals for smaller undergroun­d mines — including Pretium’s Brucejack mine in northwest B.C., just approved by the province — that plan to store tailings by backfillin­g it undergroun­d and storing some waste underwater in lakes.

But the large, open-pit projects are sticking with the convention­al method.

Seabridge concluded dry stacking was not a feasible option in the mountainou­s, wet, seismicall­y active area. It would require a large footprint with piles up to 300 metres high, according to the company.

Peter Williams, senior vicepresid­ent, technical services at Seabridge, said the wet climate in northweste­rn B.C. where KSM will be built is not conducive to dry stacking.

The challenge with rain (and melting snow in the spring) is that it must be kept away from the dry stack of tailings and channelled into collection ponds before it can be discharged to the environmen­t.

“If you have very low production rates, it’s possible. But with high production rates, that’s a hard thing to do,” said Williams.

New Gold has also rejected dry stacking at its proposed $1.8-billion Blackwater gold and silver project southwest of Prince George. That proposal is to store about 350 million tonnes of tailings, four times as much as was stored at Mount Polley.

Tim Bekhuys, director of New Gold’s Blackwater project, said they determined that dry stacking would take up a larger surface area and would require more than one watershed, which didn’t fit with their aim to keep the mine site tight and avoid fish habitat.

New Gold has experience with dry stacking at its small Peak Mine in Australia.

But Bekhuys noted that no mine of the size they have proposed, which would process 60,000 tonnes of material per day, uses dry stacking.

One of the largest mines to use dry stacking is the La Coipa gold-silver mine in Chile, about one-third the size of the planned Blackwater project.

But the panel pointed out that larger projects are being proposed.

Hudbay Minerals’ proposed Rosemont Copper mine in Arizona, which would process 68,000 tonnes of material per day, plans to use dry stacking.

Bekhuys added that dry stacking would be more costly than the convention­al approach for Blackwater.

“When we looked at dry stack as an option, in trying to balance our issues, it really doesn’t work,” he said.

New Gold doesn’t plan to proceed with Blackwater until the company finishes constructi­ng the Rainy River gold mine in Ontario. However, they will continue with the Blackwater environmen­tal assessment in order to be in a position to begin constructi­on when Rainy River is complete in 2½ years.

Other mining companies cited similar concerns of cost and difficulty in operating in wet climates, including Spanish Mountain, Taseko’s Prosperity and Aley projects and Pacific Booker’s Morrison mine. The proposed Schaft Creek, Harper Creek and Kitsault mines all have plans for convention­al tailings storage.

“My issue with this dry stack is that for some tailings it works great,” said Spanish Mountain CEO Morris Beattie. “But we’ve known for 40 or 50 years that the best place for tailings is underwater. You keep them submerged and the oxidation processes stop and the stuff just sits there forever.”

Only KGHM Internatio­nal appears to be taking a second look at the use of dry stacking at its proposed $535-million Ajax copper and gold mine.

Their original proposal was for dry stacking, but they switched to a convention­al plan over concerns from the residents of Kamloops about dust, said Ajax project developmen­t manager Clyde Gillespie.

“It’s not a given that dry stack is a one- size- fits- all solution to tailings management,” said Gillespie.

However, he said the company has committed to the community to take any lessons learned from Mount Polley and apply them specifical­ly to the Ajax project in Kamloops.

The three-member engineerin­g panel, chaired by University of Alberta professor emeritus Norbert Morgenster­n, acknowledg­ed that filtering and drystackin­g was more expensive, may require separate water storage, and was more commonly used in dry climates.

However, the panel also said the filtering and dry-stacking method has been adapted to cold regions and was in use in wet regions, including at Greens Creek.

“Additional enhancemen­ts are ripe for developmen­t if there is incentive to do so. ... There are no overriding technical impediment­s to more widespread adoption of filtered tailings technology,” the panel stated in its 156-page report.

The panel also said decisions based on comparing capital and operating costs take a limited view, as they do not include risk costs of potential failure.

“The Mount Polley case underscore­s the magnitude of direct costs for cleanup, but indirect losses — notably in market capitaliza­tion — can be even larger,” said the panel.

Repairs and cleanup costs have been pegged at as much as $400 million.

At its lowest point since the dam collapse on Aug. 4, Imperial Metals had lost $670 million in market capitaliza­tion, nearly half its value. The market value has recovered some since then, regaining about half its loss.

Vancouver-based geotechnic­al engineer Jack Caldwell, who worked on the Greens Creek tailings project 30 years ago, said that project and others are proof that you can use dry stacking in wet and cold climates.

There is a more persuasive argument that cost is a limiting factor, but tailings cost is a small portion of the overall cost, argued Caldwell.

“And there’s the final argument: you are going to spend that money at any rate because you are going to be caught with your pants down if you have a failure or something like that,” he said.

Mining operators also do not like filtering and dry stacking because it adds another manufactur­ing process to their mine operation, one that could cause bottleneck­s and negatively affect production.

It’s much simpler to put the tailings in a pipe and deposit them in a storage facility, say miners.

The key to gaining more acceptance of filtering and dry stacking is to reduce the cost to mine operators, says Cameron Stockman, project developmen­t manager at CEC Mining.

CEC is a Vancouver-based firm that designs and builds tailings filtering systems.

Stockman said it’s easier to make an economic argument for filtering and dry stacking in a dry environmen­t such as Chile where you are trying to preserve water and projects are proposing to move desalinate­d water from the ocean hundreds of kilometres to feed their projects.

He said he believes the cost curve can be shifted in B.C.

“Then it’s not so much of an uphill battle because there’s all these downstream and longterm environmen­tal, political, regulatory benefits which can come from it,” observed Stockman.

Still, even the operation the panel singled out as being an example to follow, Greens Creek, does not advocate filtering and dry stacking for all mines.

Hecla Mining, the company that owns the Alaskan mine, says it was surprised it was singled out as an example in the Mount Polley report.

While dam integrity is a key issue, there are also other issues that need to be considered, including the geochemist­ry of the tailings and challenges such as dust, said Hecla Mining vicepresid­ent external affairs Luke Russell.

Because the mine is in a federal protected area, reducing the footprint of the tailings, particular­ly its impact on wetlands, was a key considerat­ion, he said.

That’s why about 40 per cent of the tailings, which are potentiall­y acid-producing, are also backfilled in the undergroun­d mine.

Said Russell: “We’re not ascribing that the Greens Creek tailings as identified in the peer review panel was a silver bullet, by any means.”

 ?? JONATHAN HAYWARD/THE CANADIAN PRESS ?? After the tailings pond dike breach at the Mount Polley mine last summer, engineers called for a major shift in dealing with mine waste.
JONATHAN HAYWARD/THE CANADIAN PRESS After the tailings pond dike breach at the Mount Polley mine last summer, engineers called for a major shift in dealing with mine waste.
 ?? TAILINGS.INFO ?? Kinross’ La Coipa gold-silver mine in northern Chile, which is not currently operating, used dry stacking for its tailings.
TAILINGS.INFO Kinross’ La Coipa gold-silver mine in northern Chile, which is not currently operating, used dry stacking for its tailings.
 ??  ??
 ??  ??
 ??  ?? The Greens Creek gold mine in Alaska has filtered its tailings and dry stacked them for more than two decades, but other miners say the method is not suited to cold, wet climates.
The Greens Creek gold mine in Alaska has filtered its tailings and dry stacked them for more than two decades, but other miners say the method is not suited to cold, wet climates.

Newspapers in English

Newspapers from Canada