Vancouver Sun

‘TRANSPAREN­T’ SITE C REVIEW MAY BE CHIMERA

Utilities commission seems intent on suppressin­g the public’s right to know

- VAUGHN PALMER Vpalmer@postmedia.com Twitter.com/VaughnPalm­er

The day began with the B.C. Utilities Commission saying it was not in the public interest for the public to know too much about the troubles with the Site C project.

At issue were specifics about budget overruns, schedule delays and the drain on contingenc­y funds on the main civil works contract for the hydroelect­ric dam now under constructi­on at Site C on the Peace River.

The commission blacked out those and other details from a report by Deloitte LLP, the consulting firm brought in to assist in a cabinet-ordered review of Site C.

But earlier this week, I gained access to an uncensored copy of the report and published some of the more telling parts. The Vancouver Sun also posted the pure, unadultera­ted report on its website.

All of which proved to be a major source of dismay to the commission, judging from the statement that arrived in my electronic inbox shortly after 6:30 a.m. Friday.

“I am deeply concerned about the unintended release of informatio­n in the Deloitte Site C report that was considered commercial­ly sensitive,” wrote commission chair David Morton, who is also head of the Site C review panel. “Our concern is that the publicatio­n of the redacted material could result in significan­t harm or prejudice to B.C. Hydro’s current and future negotiatin­g position with its contractor­s, which would ultimately increase costs to ratepayers and, therefore, not be in the public interest.”

It would certainly not be in B.C. Hydro’s interest, given what the informatio­n reveals about the utility’s handling of the first major constructi­on contract at Site C.

The offending details included the amount by which the civil works contract was over budget from Day 1: $136 million.

The amount taken from contingenc­y funds to bring constructi­on back on schedule last year: $33.5 million.

The total drain to date on the contingenc­y budget for that contract: $194 million. The percentage of the contingenc­y budget for the contract spent at the two-year mark of an eight-year schedule: 77 per cent.

The amount of work still to be done on the contract: 76 per cent.

The boosted costs on the transmissi­on lines for the project, for which a contract has yet to be awarded: $494 million.

And so on.

All of which puts real dollar figures to Deloitte’s concerns about “B.C. Hydro’s ability to accurately estimate large contracts” and the possibilit­y of “similar discrepanc­ies between planned version actual values” on contracts still to be awarded. All critical to public understand­ing of one of the most important decisions facing the new government — whether to scrap, suspend or continue the $9-billion Site C project.

As to how those significan­t facts came to be removed from the report, the commission posted an account on its website along with an indication of where things went off track.

Deloitte consulted with B.C. Hydro on matters Hydro wanted treated as confidenti­al. The review panel accepted some of those, rejected others, and posted the redacted version on the afternoon of Friday, Sept. 8.

Promptly, there came a call from Hydro “that there may be a breach of confidenti­ality in the report.” The bits that were supposed to be redacted were instead rendered accessible.

“The commission removed the filing while staff worked to authentica­te the concerns raised. During that time, staff also reached out to a number of parties who accessed the report and further distribute­d it. All parties reached at the time were co-operative and agreed to remove and not further distribute the report.”

I got one of those calls because I had been circulatin­g highlights of the report on Twitter.

However I had neglected to download a copy of the report.

Only this week did I discover that U.S.-based energy expert Robert McCullough had obtained an unredacted version and posted it on his site.

He subsequent­ly took it down when requested to do so by the commission.

Neverthele­ss, after all that effort to keep the informatio­n from prying public eyes, commission chair Morton insists there’s no story here:

“The unintended posting of the unredacted report and its subsequent removal was not due to an error on the part of the commission, nor was it an attempt to suppress informatio­n.”

Intended or not, the removal surely did suppress informatio­n. It did so twice, once on Sept. 8, and again this week when the commission leaned on McCullough.

Friday the commission tried a third time, suggesting that The Vancouver Sun take down its posting. Happily, editor Harold Munro wrote back to say: “I remain firm in the belief that the public’s right to know details of this significan­t project far outweigh any privacy concerns related to the unredacted document.”

After all that, the commission wishes the public to know the informatio­n is in good hands.

“The review panel saw the confidenti­al numbers submitted by B.C. Hydro and we used them to make our interim finding,” wrote Morton. “We will also consider them in our final report.”

Moreover, says the commission: “This inquiry panel has made a commitment to the public, interested and affected parties to hold an open and transparen­t public process for the Site C inquiry. We continue to hold ourselves accountabl­e to this commitment.”

Trust them in other words. But the commitment will be difficult to verify in the absence of uncensored reports like the one they tried to suppress this week.

I remain firm in the belief that the public’s right to know details of this significan­t project far outweigh any privacy concerns related to the unredacted document.

 ??  ??

Newspapers in English

Newspapers from Canada