Vancouver Sun

LOSE-LOSE A POSSIBILIT­Y IN NDP SITE C DECISION

Economic, fiscal, political challenges in play as government weighs options

- VAUGHN PALMER vpalmer@postmedia.com

With decision day approachin­g on Site C, the project team at B.C. Hydro has posted one of its fortnightl­y updates on what is happening at the most controvers­ial constructi­on site in the province.

The latest constructi­on schedule covers the period Oct. 30 to Nov. 13, flanking Wednesday’s release of the B.C. Utilities Commission findings on Site C as well as the start of NDP cabinet deliberati­ons on whether to complete, cancel or pause the project.

As befits a work site where spending has been running at an average of $2 million a day, the answer to what has been happening would appear to be “rather a lot.”

Excavation will continue on the north and south banks. Ditto on the north and south cofferdams. Work will continue on the south bank drainage tunnel. “This includes drilling and blasting.”

Work is also underway on the foundation for the power house. The contractor of the turbines and generators has started operations at the onsite manufactur­ing facility and constructi­on is underway for a railway siding that will link to the CN mainline nearby.

Hydro is still working out how to deal with an abandoned natural gas well that was uncovered on the south bank. It is also assessing the archeologi­cal (meaning First Nations) impact of the proposed rerouting of Highway 29 on the north bank. Meanwhile, local residents are being cautioned about heavy truck traffic hauling rip-rap from area quarries.

“Day, night and weekend shifts are anticipate­d for the duration of the project,” concluded the update, underscori­ng the irony that the New Democrats have allowed constructi­on to proceed even as they consider whether to undo all of it by killing the project outright.

The aforementi­oned “duration of the project” might be no longer than the end of the year, Premier John Horgan having signalled this week that the cabinet will make the final call later this month or early next.

But if killing the project really is a possibilit­y — many would say a “likelihood” — why go on spending money at the rate of $60 million a month while you prepare to slam on the brakes and throw the whole thing in reverse?

One imagines the resulting Un-Constructi­on update from the Site C project team. River banks restored. Tunnels filled in. Machine shop dismantled. Heavy trucks hauling all that rip-rap back to the quarry.

Still, give Horgan and the New Democrats credit for keeping an open mind. Their partners in power-sharing, the Greens, wanted Site C killed on Day 1.

As to what happens next, the New Democrats put out a brief statement in anticipati­on of Wednesday’s release from the commission: “Government will take the time necessary to fully review the BCUC’s findings and other issues outside the scope of the review. Government will also engage further with First Nations.”

The latter, Horgan confirmed Tuesday, will include in-person consultati­ons with affected First Nations by Scott Fraser, the NDP minister of Indigenous Relations and Reconcilia­tion.

But Hydro has already gone to extraordin­ary lengths to address the court-imposed duty to consult and accommodat­e First Nations whose interests and traditiona­l territorie­s would be affected by Site C.

The Crown corporatio­n concluded benefit-sharing and compensati­on agreements with six First Nations in the region.

This record of bargaining in good faith was upheld by the courts themselves — the B.C. Court of Appeal, the Federal Court of Appeal and, in effect by the Supreme Court of Canada, which refused to hear First Nation appeals against the lower court rulings.

The courts also faulted the two First Nations challengin­g the project — West Moberly and Prophet River — for refusing to engage in consultati­ons at any reasonable level.

Against that backdrop, the coming round of consultati­ons with First Nations could build on the courtappro­ved record of progress to date.

Or it may be back to square one.

The NDP-led consultati­ons will be shaped by the new government’s embrace of the United Nations Declaratio­n on the Rights of Indigenous Peoples, a political declaratio­n that accords First Nations a veto in all but name over developmen­t within their traditiona­l territorie­s.

In anticipati­on that the New Democrats might be headed down the road to cancellati­on or suspension of the project, one of the six First Nations that signed deals with Hydro has served notice of its own.

“Site C provided a watershed moment in the relationsh­ip between McLeod Lake Indian Band and B.C. Hydro by acknowledg­ing and accommodat­ing past impacts and establishi­ng a new working relationsh­ip,” wrote the leadership of the First Nation in a submission to the utilities commission.

The resulting agreement between the two, concluded in spring 2016, “advanced reconcilia­tion. Suspension or terminatio­n of Site C would unwind that progress (and) give rise to significan­t hardships. McLeod Lake members and businesses would lose opportunit­ies that could not be replaced.”

If the New Democrats do indeed go that route, McLeod Lake believes it would be entitled to accommodat­ion of its own, including “reparation­s.” The other five First Nations with similar agreements might take the same position.

Not an easy call to make if the government is serious about accommodat­ing all First Nations, not just the ones that want it to reverse direction on Site C.

Then again, however the New Democrats decide to proceed raises multiple challenges — economic, fiscal and political.

Depending on how long Horgan and his ministers last in government, the coming decision on Site C may be the toughest any of them will face.

McLeod Lake Indian Band believes it would be entitled to accommodat­ion of its own, including ‘reparation­s,’ if the Site C hydro project is shelved.

 ?? JONATHAN HAYWARD/THE CANADIAN PRESS/FILES ?? Work continues on the B.C. Hydro megaprojec­t to the tune of $60 million a month, even as the NDP government may shut the project down before the end of the year.
JONATHAN HAYWARD/THE CANADIAN PRESS/FILES Work continues on the B.C. Hydro megaprojec­t to the tune of $60 million a month, even as the NDP government may shut the project down before the end of the year.
 ??  ??

Newspapers in English

Newspapers from Canada