Vancouver Sun

Commission’s report plays down benefits: B.C. Hydro

Utilities Commission underestim­ated by $800 million, Crown corporatio­n argues

- ROB SHAW rshaw@postmedia.com Twitter.com/robshaw_vansun

B.C. Hydro says the recent report into the Site C project by the B.C. Utilities Commission underestim­ated the hydroelect­ric dam’s benefits by $800 million.

In a letter to the commission released Thursday, Hydro argued the independen­t regulator made mistakes in two models that compared Site C to a portfolio of alternativ­e energy options.

“B.C. Hydro performed a preliminar­y analysis of these two models and has identified what appear to be calculatio­n and input errors,” Hydro wrote in the letter. “The cumulative effect of these errors is to understate the benefits of completing Site C, as compared to the commission’s ‘illustrati­ve alternativ­e portfolio,’ by approximat­ely $800 million.”

Hydro’s six-page letter detailed what it argued was an incorrect discount rate on Site C’s surplus, inconsiste­nt inflation rates, and inaccurate treatment of some of the project’s costs, among other technical issues.

One of the errors has already been admitted by the utilities commission, which said last week it had incorrectl­y calculated $336 million in discount rates for Site C’s surplus.

The commission report said that alternativ­e energy sources like wind and geothermal, combined with an aggressive plan to reduce residentia­l and industrial power consumptio­n, could provide similar energy for “equal or lower unit energy cost” than the $8.3-billion dam.

However, Hydro’s argument, as well as the utilities commission’s error, could tilt the financial advantage back to Site C.

“The informatio­n that we need and our decision-making process has to be clear,” Energy Minister Michelle Mungall said on whether the reported errors undermine her government’s confidence in the utilities commission. “There can’t be any vagueness at all. This is a major decision that will be impacting British Columbians today and into the future.”

The utility commission report on Site C, completed within 12 weeks at the government’s request, concluded the project was not on time nor on budget. The

The informatio­n that we need and our decision-making process has to be clear. There can’t be any vagueness at all.

final decision on whether to cancel the mega-project will be made by the NDP cabinet by the end of the year.

Mungall said she thinks the utility commission “did a very good job in the time frame that they had.”

Two government ministers also raised concerns and questions about the commission calculatio­ns in a letter last week. The commission responded Thursday, confirming the increase to Hydro rates if Site C was terminated would be at least 10 per cent, assuming the corporatio­n had to pay off almost $4 billion if the dam project was stopped.

The commission’s letter to government confirmed it did not use the $2.1 billion already spent on the dam and the estimated $1.8 billion to remediate the land when comparing the cost of cancelling the project and obtaining energy from alternativ­e sources for almost the same cost.

Also Thursday, Premier John Horgan’s office announced six outside energy consultant­s have been chosen to present informatio­n to cabinet before the decision about the dam.

They are David Austin of the Clean Energy Associatio­n of B.C.; David Craig of Consolidat­ed Management Consultant­s; Colleen Giroux-Schmidt of Innergex Renewable Energy; Mark Jaccard of Simon Fraser University; Robert McCullough, a researcher who has produced reports for the Peace Valley Landowner Associatio­n; and Karen Tam Wu of the Pembina Institute. The six consultant­s will present to cabinet as a group on Nov. 30.

 ?? B.C. HYDRO ?? Dredging on the north bank of the Peace River in October at the Site C hydroelect­ric project.
B.C. HYDRO Dredging on the north bank of the Peace River in October at the Site C hydroelect­ric project.

Newspapers in English

Newspapers from Canada