Kinder Morgan shares drop 2.6% over possible Trans Mountain delay

- ETHAN LOU

Kinder Morgan Canada Ltd shares fell 2.6 per cent on Tuesday after the company said there could be more delays in the expansion of its $7.4-billion Trans Mountain pipeline expansion, raising concerns about cost blowout.

Kinder Morgan’s Trans Mountain expansion to the west coast has already been delayed by nine months.

The company said late on Monday that the lack of clarity around municipal permit processes and related judicial process could push it back further. It did not provide a time frame.

The project, an expansion of the Trans Mountain pipeline from Alberta’s energy heartland to Burnaby, B.C., would nearly triple capacity to 890,000 barrels per day and significan­tly increase crude tanker traffic.

The company, a unit of Houston-based Kinder Morgan Inc., did not immediatel­y respond to a request for comment.

Kinder Morgan has not updated its cost estimate for the project since March, a move that would not sit well with the market, analysts said.

“We believe that the market will likely anticipate increased capital costs for the project,” said Royal Bank of Canada analyst Robert Kwan.

“I find it a very odd and sad situation that we have this sort of conflict going on once you’ve got federal approval and previous provincial approval,” said Chris King, vice-president and portfolio manager at Morgan Meighen & Associates, who holds shares in Kinder Morgan Inc.

He said he expects the company to provide an update in a week or two and give a more detailed timeline for the project next year.

While the expansion is not considered critical to the Houston parent, it is the main project for Kinder Morgan Canada, whose current Trans Mountain network forms most of its business.

On Monday, Kinder Morgan separately argued before the National Energy Board that the project had been delayed due to what it said was the city of Burnaby’s vagueness in providing timelines.

The city had disputed that view, saying officials treated Kinder Morgan impartiall­y, and that any delay was caused by what it characteri­zed as the company’s poorly prepared applicatio­ns.

 ?? JONATHAN HAYWARD/THE CANADIAN PRESS ?? Kinder Morgan’s Trans Mountain facility in Edmonton. Kinder Morgan says the lack of clarity on municipal permit and related processes could further push back the project.
JONATHAN HAYWARD/THE CANADIAN PRESS Kinder Morgan’s Trans Mountain facility in Edmonton. Kinder Morgan says the lack of clarity on municipal permit and related processes could further push back the project.