Vancouver Sun

Suncor reports ‘excellent progress’ as it pushes to finish $17B Fort Hills facility

- GEOFFREY MORGAN

Suncor Energy Inc. is pushing to complete constructi­on of its $17-billion Fort Hills oilsands project as the company looks to produce the facility’s first barrel of oil by the end of December.

“We continue to have excellent progress at Fort Hills,” Suncor spokespers­on Sneh Seetal said, adding that constructi­on crews on the site north of Fort McMurray, Alta., are “largely supporting commission­ing activities.”

The last part of the plant to be commission­ed is the “secondary extraction” facility, which processes bitumen froth into bitumen. All other parts of the oilsands mine and processing facility — a massive joint venture between Suncor, Paris-based Total SA and Vancouverb­ased Teck Ltd. — are complete and ready to begin producing oil.

Seetal could not say whether Fort Hills would be able to produce its first barrel of oil by the end the month as planned, but it is still the company’s goal.

During investor presentati­ons at the beginning of December, Suncor communicat­ed three key messages to analysts, one of which was that the Fort Hills project was on track to produce first oil by the end of the year, BMO Capital Markets analyst Randy Ollenberge­r said in a note.

Seetal said Suncor has conducted five test runs at the oilsands project and produced 1.4 million barrels of bitumen froth so far. She said the froth has been loaded onto trucks and sent to the company’s existing oilsands base plant closer to Fort McMurray for processing.

Progress on the last portion of the extraction plant at Fort Hills is being closely watched and analysts expect the facility, which will be able to process 194,000 barrels per day, to cost about $17 billion when finished. Suncor has said it expects Fort Hills to operate at 50 to 60 per cent capacity over the course of 2018.

Suncor has been paying Total’s share of constructi­on costs since the French oil major in July announced it would not provide any more funding as costs rose.

“We expect that Suncor will eventually recoup these costs from Total either in the form of cash or an increased working interest in the project,” GMP FirstEnerg­y analyst Michael Dunn said in a research note. “Given that we suspect Suncor has a standing bid for Total’s working interest that is well below cost, this standoff may be a way for Total to effectivel­y sell a small portion of its working interest at cost.”

 ?? FORT HILLS ENERGY L.P. ?? Constructi­on continues on Fort Hills oilsands mine and processing project in the spring of 2015. The secondary extraction facility is the last part of the plant to be commission­ed.
FORT HILLS ENERGY L.P. Constructi­on continues on Fort Hills oilsands mine and processing project in the spring of 2015. The secondary extraction facility is the last part of the plant to be commission­ed.

Newspapers in English

Newspapers from Canada