Vision (Canada)

St. Joseph work overdue and over budget but just about done

- ALEXIA MARSILLO alexia.marsillo@eap.on.ca

Final project costs for the reconstruc­tion and extension work done on St-Joseph Street in Rockland exceed the expected budget by $ 75 000, and took double the amount of estimated time. The project, however, is now 99 per cent completed.

The initial budgeted cost of the work at the intersecti­on of St-Joseph Street and Laurier Street was $2,470,000. The City has now calculated, however, that $2,544,990 is needed to cover all the final project expenditur­es. Instead of the projected eight-week plan, the work at the intersecti­on ran over the course of 16 weeks. To compensate for going over budget, the City will be re-allocating the needed $75,000 from the 2017 Capital Program for Clark Road Easements, which had an initial budget of $100,000.

The St-Joseph Street project was awarded to STP Constructi­on on December 13, 2016. Constructi­on on the street began in the spring of 2017 and was substantia­lly completed by the end of August. The road is now 99 per cent complete, with only two small items left to finish: minor landscapin­g and the installati­on of a water fountain and park bench that was donated by the Lavictoire family. These remaining works will be done in the spring of 2018.

A delay in constructi­on that occurred in July led to extra costs. Administra­tion had gone ahead with a constructi­on plan that had not been approved by council. Constructi­on was halted at that point and delayed for a month while the entire design was reassessed. The final decision was to maintain the three lanes (two northbound and one southbound) on St-Joseph, eliminatin­g the idea of a bike path on both sides of the road.

As for the Clark Road Easement Project in the amount of $100,000, the project saw a sharp decline in costs after the City ran an assessment. The point of the project was to identify low points along the roadside ditch line and to seek out alternativ­e drainage easements with affected property owners. As a solution to several drainage problems on certain properties, the City will be redirectin­g storm water to a city-owned unopened road allowance. This will significan­tly reduce the amount of money needed for the project and allow for the surplus to bail out the additional costs of the St-Joseph work.

 ?? photo d’archives ?? Les coûts finaux du projet de reconstruc­tion et d’extension, à l’intersecti­on des rues StJoseph et Laurier à Rockland, dépassent le budget prévu de 75 000 $ et le temps estimé de huit semaines a doublé à 16 semaines. Le projet est cependant 99% terminé...
photo d’archives Les coûts finaux du projet de reconstruc­tion et d’extension, à l’intersecti­on des rues StJoseph et Laurier à Rockland, dépassent le budget prévu de 75 000 $ et le temps estimé de huit semaines a doublé à 16 semaines. Le projet est cependant 99% terminé...

Newspapers in English

Newspapers from Canada