Windsor Star

Gordie Howe bridge project delayed again

Estimated completion date pushed to 2023 as specificat­ions change

- DAVE BATTAGELLO

Constructi­on of the long-awaited new Windsor-Detroit border crossing bridge has been set back by a year because of the complex bidding process, meaning it likely won’t be completed until 2023.

The three consortium­s vying to build the Gordie Howe Internatio­nal Bridge were informed in the last week by the Windsor-Detroit Bridge Authority that their detailed bids will not be required until next year.

Final bids were to be submitted this fall and a contractor selected by the end of the year, with constructi­on starting in the summer of 2018, according to the previous time table.

But specificat­ions and requiremen­ts for the project have changed, delaying the selection of the contractor and start of constructi­on, according to informatio­n obtained by the Star.

Some of the new requiremen­ts are contained in a US$55-million community benefits agreement reached earlier this year with the City of Detroit that includes job training, health monitoring and neighbourh­ood improvemen­ts for the industrial community of Delray where the bridge will be located.

Separated pedestrian and bike lanes were also recently added to the bridge design.

Incorporat­ing these added elements into the bid documents takes time and means the three consortium­s need until next spring or summer to make their final submission­s. It will likely take the bridge authority until the end of 2018 to select the successful bid.

Several more months in 2019 will be needed for a fairness monitor to verify the process was carried out properly. Then the bridge authority has to negotiate a final contract with the winning bidder and workers will have to be hired before constructi­on can start.

That pushes the anticipate­d completion date back to early 2023, as it is estimated constructi­on will take at least 42 months.

The Howe bridge project includes the crossing, customs plazas and a new two-kilometre feeder road in Detroit to connect with the I-75 freeway.

One of the bidding groups this week informed potential subcontrac­tors that the bridge authority will not be providing “full scope and specificat­ions” for the bridge project until this fall, according to an email obtained by the Star.

That means the three finalists can’t even begin working on final designs and getting price estimates from subcontrac­tors until late this year. It’s unlikely those bids will be submitted until the summer of 2018, and the bridge authority will need at least three to six months to assess them and make a decision.

The bidding process rules prevent any of the primary companies involved from speaking publicly about the project.

“We are somewhat disappoint­ed they won’t meet their milestones on this,” said Jim Lyons, executive director of the Windsor Constructi­on Associatio­n, which represents local constructi­on and supply companies likely to be retained as subcontrac­tors. “There is likely a good reason. Hopefully the general public does not panic over this. We are in way too deep on this project for anyone in the federal government to pull the plug.”

Bridge authority chairman Dwight Duncan declined to comment Tuesday.

Despite the delay, constructi­on could start in late 2018, said bridge authority spokesman Mark Butler.

“We are in constant conversati­on with the proponents who collective­ly have over 2,000 people working on their proposals to ensure that the procuremen­t process will yield the best possible proposals,” he said. “The procuremen­t process is ongoing and we will advise if there are any changes to the establishe­d timeline.”

There has been “significan­t progress on preparator­y activities” that include $200 million invested in the Canadian port of entry and the acquisitio­n of 70 per cent of the properties required on the U.S. side, Butler said.

“Activities at the U.S. port of entry are also underway with demolition and utility relocation,” he said. “These preparator­y activities will make the sites ready for our private sector partner to begin constructi­on as soon as possible after financial close.”

Under plans launched by former prime minister Stephen Harper’s

Conservati­ve government, the Howe bridge was to be completed by 2020. But the final bidding stage of the project was delayed significan­tly by Prime Minister Justin Trudeau’s Liberals.

The request for proposals from the shortliste­d groups was pushed back nearly a full year until late 2016. The latest delay means a contractor will be selected nearly two years later than originally scheduled.

The Howe bridge may again be “off the rails,” said MP Brian Masse (NDP — Windsor West). He believes the decision to undertake a public-private partnershi­p (P-3) to build the bridge was a mistake and that it should have been a simpler design-build process.

Under design-build, the government issues a tender and pays the contractor for the project. All cost overruns are paid for by government. A P-3 requires the privatesec­tor contractor to pay for the majority of the project and collect operating revenues after it is completed — in this case tolls.

“Under a P-3 there are so many legal obligation­s that have to be done to ensure one group does not come back and sue if something is missed along the way,” Masse said. “It means any time you have a departure from the original plan it is almost a restart. This is extremely disappoint­ing news. With designbuil­d you have some flexibilit­y and this could have been built by now. I think there will be more continual challenges like this. It’s become a bit of a nightmare.”

Bill Anderson, director of the University of Windsor’s CrossBorde­r Institute, said the latest Howe project delay is not entirely unexpected. Delays are common during the bidding phase of a P-3 project, but once constructi­on begins there are few holdups since the added cost has to be covered by the private-sector builder, he said.

“Certainly there will not be a positive reaction to this — nobody will be happy — but this is not unusual for big projects like this,” Anderson said. “Given the complexity and how long this has been going on you have to keep this (delay) in perspectiv­e and (look at the) long-term nature of the economic benefits.”

Newspapers in English

Newspapers from Canada