Windsor Star

Labrador’s Muskrat Falls dam offers lessons for B.C. plans with Site C project, expert says

- GEORDON OMAND

VANCOUVER A hydroelect­ric venture in central Labrador should serve as a cautionary tale for British Columbia and its own ambitions to build a multibilli­on-dollar dam in the province’s northeast, the former head of Newfoundla­nd and Labrador’s public utilities regulator says.

David Vardy, a former economics professor and retired civil servant in that province, published a letter Tuesday addressed to the B.C. Utilities Commission containing more than a dozen recommenda­tions based on lessons learned from Muskrat Falls. The utilities regulator was tasked earlier this month by B.C.’s NDP government to review the economic viability of Site C, an $8.8-billion energy project under constructi­on on the Peace River.

“B.C. has the luxury of being able to stop this now without going any further,” Vardy said. “In terms of the take-away from Muskrat Falls: It’s not too late to stop it.”

Vardy’s letter outlined the similariti­es between the two provinces’ megaprojec­ts: Both are backed by powerful Crown corporatio­ns, both were exempt from the usual regulatory oversight process, at least initially, and both have experience­d ballooning costs over time.

The price tag for Muskrat Falls has more than doubled from original estimates, swelling to $12.7 billion in the province of only about 525,000 people. Vardy said the project’s cost of about $24,000 per person would double the province’s per capita net debt and pose a major threat to its solvency.

Vardy encouraged British Columbia’s Utilities Commission to ensure Site C is built according to current energy needs and is made as adaptable as possible, warning that the rapid pace of technologi­cal advances could make the project obsolete before long. He emphasized the importance of independen­t public oversight and a rigorous public review process, lauding the analysis being conducted by the utilities commission. The review began Aug. 9, with interim findings due six weeks later and a final report expected by Nov. 1.

The commission’s review process in B.C. was once standard before the previous Liberal government’s clean-energy laws permitted some projects, including Site C, to circumvent the regulatory process.

Newspapers in English

Newspapers from Canada