Windsor Star

Michigan, Enbridge agree to boost safety of Mackinac straits pipeline

- The Associated Press

TRAVERSE CITY, MICH. Michigan Gov. Rick Snyder and Canadian oil transport company Enbridge Inc. have agreed to a timeline for determinin­g the future of twin pipelines beneath the channel where lakes Huron and Michigan converge.

Options include shutting down the lines or routing them through a tunnel beneath the lake bed where they now rest.

The plan announced Monday calls for reaching a final agreement by Aug. 15 on the pipes beneath the Straits of Mackinac, an eight-kilometre-long scenic waterway with high value to the tourist industry and Great Lakes environmen­t. They are part of Enbridge’s Line 5, which carries nearly 87 million litres of oil and liquid natural gas daily across northern Wisconsin and Michigan to refineries in Sarnia.

The company has repeatedly insisted the underwater segment installed in 1953 is in good condition and has never leaked. However, state officials and environmen­tal groups have expressed alarm over recent disclosure­s of gaps in its exterior layer of protective enamel coating and unsupporte­d spaces beneath the pipes.

“Business as usual by Enbridge is not acceptable and we are going to ensure the highest level of environmen­tal safety standards are implemente­d to protect one of Michigan’s most valuable natural resources,” Snyder said.

The Republican governor’s administra­tion has resisted critics’ demands to order the lines decommissi­oned, but that option “is still on the table,” said Valerie Brader, executive director of the Michigan Agency for Energy.

“(Monday’s) agreement does not represent a final decision by the state regarding Line 5, but instead provides a clear schedule on which a decision will either be reached co-operativel­y with Enbridge or the state will take another path,” Brader said.

Although the U.S. federal government regulates oil pipelines, Michigan owns the lake bottom and granted an easement to the company allowing the pipeline to go there.

Enbridge officials acknowledg­ed an erosion of public confidence in the safety of Line 5 and apologized for what they described as poor communicat­ion with the public about their inspection­s and studies.

“Trust is earned, and while we have a long way to go, we remain committed to doing what it takes to rebuild trust and uphold our pledge to protect the environmen­t while safely meeting Michigan’s energy needs,” said Guy Jarvis, executive vice-president and president for liquids pipelines.

While not ruling out a permanent shutdown, the agreement includes a series of steps intended to boost the underwater pipes’ safety.

Among them is a procedure for temporaril­y halting the flow of oil during storms that produce sustained waves at least 2.4 metres high for longer than an hour, the level at which Brader said recovery of spilled oil becomes “extraordin­arily hard.”

Enbridge also agreed to evaluate three options by June for routing the underwater segment through a tunnel or trench, on or beneath the lake bed — either using the existing pipes or building a new one.

The company promised steps to prevent the lines from being damaged by a ship anchor, expedite monitoring of the pipelines with cameras or other devices and speed up methods for detecting potential ruptures and responding to spills.

Enbridge also said it would replace another section of Line 5 beneath the St. Clair River where it crosses the U.S.-Canadian border with a new pipe inside a tunnel after receiving federal and state permits.

The agreement comes as Michigan agencies are taking public comments on a consultant’s report they commission­ed that lists six longterm possibilit­ies for the Straits of Mackinac segment, including the tunnel alternativ­e, which it estimated would cost about $150 million. While not endorsing an option, the report described a tunnel as more feasible than others, such as moving Line 5’s oil through other existing pipeline networks.

Environmen­tal groups said the deal appears to tip the scales in favour of a tunnel instead of halting all movement of oil through the straits, which they argued is the only foolproof way to safeguard the lakes. Other measures in the plan will do little good, they said.

“Instead of shutting down this dangerous pipeline, our state leaders continue to place an enormous amount of trust in Enbridge to operate it responsibl­y — even while the company continues to repeatedly break that trust,” said Lisa Wozniak, executive director of the Michigan League of Conservati­on Voters.

State Attorney General Bill Schuette, who has called for eventually shutting down Line 5, said the agreement was “a good step forward.”

 ?? DALE YOUNG/THE ASSOCIATED PRESS FILES ?? Michigan Gov. Rick Snyder and Enbridge Inc. have announced a new agreement they say will boost the safety of twin pipelines beneath the waterway where lakes Huron and Michigan converge.
DALE YOUNG/THE ASSOCIATED PRESS FILES Michigan Gov. Rick Snyder and Enbridge Inc. have announced a new agreement they say will boost the safety of twin pipelines beneath the waterway where lakes Huron and Michigan converge.

Newspapers in English

Newspapers from Canada