Windsor Star

LaSalle locked in legal disputes years after opening of town hall

Judge orders trial to untangle mess surroundin­g $13.8M project

- SARAH SACHELI

Behind the gleaming glass facade of LaSalle’s new civic centre lies a tangled mess of constructi­on liens and lawsuits still making their way through the courts, 31/2 years after the building opened to the public.

Battling in the civil courts are Piroli Constructi­on, the general contractor on the $13.8-million project, and the Town of LaSalle, as well as several sub-contractor­s who claim they were never paid for work they completed.

Tuesday, a Superior Court judge ordered that seven separate lawsuits be dealt with together when and if they ever go to trial. They include Piroli’s $319,000 claim against the town, the town’s countercla­im of $75,000 against Piroli for breach of contract, and six constructi­on liens totalling $613,604 naming both Piroli and the town.

According to court documents filed Tuesday, both Piroli and the municipali­ty agree all the cases are intertwine­d and should be heard together.

Piroli Constructi­on was awarded the contract to build the civic centre complex on Malden Road in October 2012. Piroli had submitted the lowest of 10 bids.

The new town hall complex opened for business on Aug. 18, 2014, eight months late. The building wasn’t finished and contractor­s were on site, continuing to work, even after the town took occupancy of the building. Piroli blamed fierce winter weather and scheduling problems with sub-trades for the project running behind schedule.

Due to the delay, a clause in the constructi­on contract kicked in, making Piroli responsibl­e for paying lease costs of $15,000-$20,000 a month for temporary offices the town set up at Windsor Crossing outlet mall.

Sub-contractor­s began registerin­g liens against the project in 2014, filing claims against Piroli and the town in Superior Court.

With the number of claims against the general contractor mounting, Piroli filed a lawsuit against the town in March 2016.

Piroli claims the town withheld payment despite the general contractor fulfilling its obligation­s under the contract.

“The plaintiff denies that its work was completed in a deficient manner,” Piroli says in its statement of claim filed with the court.

In its statement of defence, the town says Piroli isn’t entitled to any more money because it never finished work or corrected problems. Those deficienci­es are outlined in the town’s lawsuit as “water feature deficienci­es” and “interior and exterior deficienci­es.”

The town claims it didn’t hold back enough money to cover the cost of completing the project.

“The defendant claims that the funds being held back from the plaintiff under this contract are insufficie­nt to cover the costs of remedying all of the outstandin­g deficienci­es.”

None of the claims contained in either side’s documents have been tested yet in court. A trial date has yet to be set.

Piroli’s lawyer declined to comment on Tuesday. Myron Shulgan said it would be inappropri­ate to talk about the case while it is before the courts.

On Tuesday, LaSalle Mayor Ken Antaya referred questions to chief administra­tive officer Kevin Miller, who did not return phone calls.

This week’s motion to have all the cases tried together is the latest developmen­t in the ongoing legal battle.

Last month, Piroli lost a case before the Ontario Court of Appeal involving Berkley Insurance Company over constructi­on bonds for the LaSalle civic centre.

Berkley agreed to post bonds to cover nearly $973,000 in constructi­on liens claims by eight subcontrac­tors.

Piroli was supposed to direct the Town of LaSalle to pay Piroli’s lawyers $486,000 — $191,000 of which was to be forwarded to Berkley. The balance was to be held in trust should Berkley be called upon to make payment of the constructi­on lien bonds.

Piroli got the money from the town, but instead used it to pay sub-contractor­s.

Last year in Superior Court, Berkley won an injunction ordering Piroli to honour the original agreement. The order gives Berkley priority over unsecured creditors in the case of bankruptcy.

Piroli was also ordered to pay $12,000 for Berkley’s legal bills.

Piroli appealed the decision. The Ontario Court of Appeal last month dismissed the case. The general contractor must pay Berkley’s legal fees of $7,500 for the appeal.

A Superior Court judge ordered that seven separate lawsuits be dealt with together when and if they ever go to trial.

 ?? NICK BRANCACCIO ?? LaSalle’s $13.8 million civic centre opened in August 2014 but it remains at the centre of a tangled web of legal disputes.
NICK BRANCACCIO LaSalle’s $13.8 million civic centre opened in August 2014 but it remains at the centre of a tangled web of legal disputes.

Newspapers in English

Newspapers from Canada