China Daily (Hong Kong)

MTR admits faulty steel bars found at Hung Hom

- By CHINA DAILY in Hong Kong Pamela Lin contribute­d to this story.

Rail operator MTR Corporatio­n on Wednesday admitted it had found at most 25 defective steel bars at the constructi­on site of the city’s most expensive railway project.

The corporatio­n said it would take legal action if there was enough evidence of “corner-cutting” at the Hung Hom Station constructi­on site of the HK$97.1 billion Sha Tin to Central Link.

The MTR said its staff discovered irregulari­ties with steel bars on five occasions between August and December 2015.

The faults were spotted before the bars were cemented to create the floor one level beneath the platform for trains going to Tuen Mun and Ma On Shan.

Of these five inspection­s, the one done in December 2015 found five defective steel bars; the remaining inspection­s found less than five, MTR said.

A detailed investigat­ive report will be handed to the government next week.

The company also said an independen­t third party would conduct safety tests. These are expected to be finished in three to four months.

MTR Projects Director Philco Wong Wai-ming said: “We wrote to the contractor Leighton Contractor­s (Asia) asking them to rectify the fault after the inspection­s, where we found five defective steel bars.

“There were 26,400 screw caps used in Hung Hom Station extension works; we have asked Leighton to make sure these meet the required standards,” Wong told a press conference.

MTR conducted a train test run in April. After the test, the engineerin­g structure was considered safe.

Meanwhile, MTR Chief Executive Lincoln Leong Kwok-kuen said on-site MTR inspectors would ask the subcontrac­tor to rectify these problems immediatel­y.

Leong said if such problems continue and affect the engineerin­g structure, then MTR inspectors will report this to their superiors.

“The incident wasn’t reported to the board and the government (at the time), it therefore did not comply with government’s demands,” Leong explained.

Because the incident occurred three years ago, it will take time to gather the necessary informatio­n about it, added MTR Chairman Frederick Ma Si-hang.

Work on the Sha Tin to Central Link project, operated by the MTR, commenced in 2012.

The company admitted steel bars between the diaphragm wall and the slab structure were found cut off. It made these revelation­s last Friday when meeting with the Legislativ­e Council Subcommitt­ee on Matters Relating to Railways.

We wrote to the contractor Leighton asking them to rectify the fault after the inspection­s, where we found five defective steel bars.” Philco Wong Wai-ming, projects director of MTR Corporatio­n

Last week’s revelation of serious irregulari­ties involving constructi­on of platforms at Hung Hom Station for the HK$97.1-billion Sha Tin to Central Link project has not only sparked a media frenzy but also aroused great public concern.

This is completely understand­able. The project in question is one of the largest infrastruc­ture facilities the city has ever built. It will be a backbone rail link in the city when completed and put into service. What is at stake is the safety of thousands of passengers as well as Hong Kong’s internatio­nal image as a city with top-quality infrastruc­ture.

MTR Corporatio­n, the manager of the rail link project, is trying to ease public concerns over the reported substandar­d work done by a subcontrac­tor at the platform of Hung Hom Station, assuring that platform safety hasn’t been compromise­d.

Conceivabl­y, safety concerns would not die down until all facts have come out and all doubts have been cleared. The MTR is obliged to undertake a thorough check to determine the seriousnes­s of the problem and implement appropriat­e rectificat­ion measures. The management of the rail operator has commission­ed a third-party expert to conduct safety tests on the platforms in question. This is a right move and a positive response to public demands.

MTR has so far sidesteppe­d questions about who is responsibl­e for the questionab­le and substandar­d work. It promised to submit a report to the government. Pending details of substandar­d work, there is no way we can now tell who is guilty of constructi­on malpractic­e. But MTR can in no way deny its share of the blame for constructi­on irregulari­ties.

The rail operator admitted last week that a subcontrac­tor had on five occasions produced substandar­d work for platforms at Hung Hom Station from August to December 2015, with workers cutting steel bars short to make it seem as though they had been screwed correctly into the coupler. This has raised a valid question: Why didn’t MTR take effective measures to stop such practices after its field inspectors discovered the irregulari­ty the first time? Subsequent cases of constructi­on irregulari­ty could have been prevented should effective measures have been taken after the first discovery of such a practice.

The public have rightly paid great attention to the incident. After all, safety is a matter of great significan­ce. Unfortunat­ely, some Legislativ­e Council members from the opposition camp are attempting to take advantage of the incident and use it as an excuse to filibuster the proposed legislatio­n on the co-location arrangemen­t for the West Kowloon Station of the Guangzhou-Shenzhen-Hong Kong Express Rail Link, which is supported by a majority of residents. They are virtually telling Hong Kong people once again that they would pursue their political agenda by hook or by crook, without regard to public will.

 ??  ??

Newspapers in English

Newspapers from China