Global Times

PREPA’S PREDICAMEN­T

Puerto Rico’s utility authority suffering same old challenges post- Maria

-

New leadership at Puerto Rico’s beleaguere­d electric utility may not be sufficient enough to compensate for missteps following Hurricane Maria that led to delayed work, recurrent blackouts and more than $500 million in contracts with untested companies now under federal investigat­ion.

A management shakeup on Friday will not by itself cure the chaotic and slow power restoratio­n efforts two months after the hurricane struck the island. So far, authoritie­s say only 54 percent of the power has been restored.

Federal and local leaders have struggled to repair the devastatio­n wrought by the storm, which knocked out power for all 3.4 million residents and killed dozens of people.

Leadership reshuffle

Puerto Rico Electric Power Authority’s (PREPA) chief executive Ricardo Ramos stepped down unexpected­ly last week, days after congressio­nal hearings on the restoratio­n.

New interim head Justo Gonzalez, previously the director of generation for the bankrupt utility, inherits a situation that even before the storm was far more complicate­d than that of any US utility. He faces growing pressure from the US Congress, federal regulators, the board overseeing Puerto Rico’s finances and longtime creditors to whom the territory owes $72 billion in debt.

“There are still challenges preMaria that need to be addressed as well as challenges right now,” said Jose Roman, interim chair of Puerto Rico’s Energy Commission, which regulates PREPA.

On Twitter, Gonzalez said he wants to see a more “modern authority,” with standards “on a par with equivalent bodies in the US and worldwide.”

Gonzalez was not available for additional comment and PREPA’s press office did not respond to questions.

Plight for power

PREPA’s goal is to see 95 percent of power restored by mid-December, but the process was hampered by decisions not to request aid from mainland utilities for nearly six weeks, and to sign contracts with little-known companies like Whitefish Energy Holdings without approval from federal regulators.

PREPA’s Ramos said he went ahead with deals like Whitefish due to worries about having to foot the bill for aid from other utilities.

The utility did not have contracts on hand for poles, response vehicles and other supplies it needed after the hurricane.

The $300 million Whitefish deal was canceled on October 30 – and its crews and subcontrac­tors are now in the process of leaving the island, introducin­g another transition­al period for those who will take up the effort to bring back power.

Florida-based utilities including JEA and Kissimmee Utilities Authority have been on the island for about 40 days, said Kissimmee spokesman Chris Gent.

He said he does not know who will be taking over the projects Kissimmee was working on, and added that recently, crews have said work was starting to stall because needed materials were not always available.

The restoratio­n of power has remained a slog. Last week, an outage on a major 230,000 volt line west of the capital of San Juan disrupted service in an area that included the capital and the populous municipali­ties of Bayamon and Guaynabo. It was the third outage in the last several weeks affecting the capital.

‘No institutio­nal memory’

Meanwhile, the island’s oversight board made a move to review most government contracts. It also announced plans to appoint retired US Air Force Colonel Noel Zamot – already a member of that board – as an outside manager at PREPA.

The utility fought for that decision and won, as the move was blocked in court. However, it puts additional pressure on Gonzalez to right the island’s power situation

without an outside advisor, and could increase the desire for oversight from the island’s energy commission, PREPA’s regulator, which was formed by a legislativ­e act in 2014.

Jose Roman, interim chair of Puerto Rico’s Energy Commission, said it had taken a hands-off approach in the early days after the disaster, only later saying it would get involved in investigat­ing what had happened after controvers­y surroundin­g the contracts popped up.

“It is my sincere desire that PREPA is able to perform to the quality of standards we expect them to,” said Roman. “We have been two months without power. They need to perform. There is no alternativ­e.”

The utility has had a stream of executives appointed by the island’s governor, and the latest, Ramos, lasted only about a year. This frequent changing of the guard has disrupted PREPA’s ability to enact long-term change, according to more than a dozen interviews conducted by Reuters.

Roman said that the utility’s upper management has “no institutio­nal memory” due to frequent turnover. When asked about new management, he said, “the new CEO has been working at PREPA. That will not solve all of PREPA’s issues.

“We will see as time develops how he performs.”

 ?? Photo: AFP ?? A power line tower downed by the passing of Hurricane Maria lies on top of a house in San Juan, Puerto Rico on November 7.
Photo: AFP A power line tower downed by the passing of Hurricane Maria lies on top of a house in San Juan, Puerto Rico on November 7.

Newspapers in English

Newspapers from China