Times of Eswatini

Nhlangano-Sicunusa Road

... in readiness for His Majesty King Mswati III’s 56th Birthday to be held this Friday

- BY SIFISO DLAMINI

MBABANE – Following years of delay in the constructi­on of the controvers­ial Nhlangano-Sicunusa Road, it is safe to say that the road is near completion.

This would bring the much needed relief to the taxpayer, as the road, which was initially budgeted to cost around E465.99 million but so far has cost the taxpayer about E1.2 billion.

The road constructi­on is currently under Inyatsi Constructi­on Limited, which entered into an E621 million, public private partnershi­p (PPP) with government for the completion of the road.

Of note, following the concerns raised regarding the alleged mismanagem­ent of funds by the previous contractor, Parliament issued a directive for a forensic audit on the project through the Auditor General’s Office.

The report which was reportedly finalised in early 2023 is yet to be tabled in Parliament for debate and adoption.

The 43.5km-long Nhlangano-Sicunusa Road in the southwest is part of the main road network of Eswatini and provides an important connection between agricultur­al areas and urban centres. Works carried out under the project include upgrading the gravel Nhlangano-Sicunusa Road with a bitumen surface, designed to accommodat­e speeds of 100km/hour, installati­on of culverts, and constructi­on of bridges over the Mkhondvo and Ndlotane rivers.

Both rural and urban population­s will benefit from enhanced local, intra-regional and internatio­nal exchange of goods, as well as from improved access to social amenities. Additional­ly, owing to the scenic nature of the region, tourism is expected to rise, thus increasing employment and business opportunit­ies.

The completion of the road is timely, taking into considerat­ion that during the budget speech, the Minister of Finance, Neal Rijkenberg, pronounced that in this financial year, government has prioritise­d the completion of all pending capital projects, including the Nhlangano-Sicunusa Road.

During the delivery of the speech, the minister pointed out that government recognised the need for infrastruc­ture developmen­t to meet transporta­tion and access to services needs for the nation.

He said over the years, significan­t investment has been made in developing public infrastruc­ture including several roads, office buildings, railway lines and residentia­l blocks, to mention a few.

The minister said with the passage of time, growing usage and an increase in the population, wear and deteriorat­ion has come to be the prominent feature of such infrastruc­ture. “Government recognises the need for improved maintenanc­e on government infrastruc­ture in general and additional funding for maintenanc­e has been provided in this year’s budget,” he said.

Adding, Rijkenberg said in line with the national developmen­t agenda, the current financial year’s budget will address social challenges, build infrastruc­ture and provide for economic growth.

“To attain this growth, we will be prioritisi­ng the completion of existing capital projects and spending in excess of E1billion more on capital infrastruc­ture, compared to the previous financial years actual spend,” he said.

Major projects to be completed include the Internatio­nal Convention Centre (ICC), the Manzini-Mpandze Highway, the Mpandze-Mbandlane Highway, the Nhlangano-Sicunusa Road, the Manzini Golf Course Interchang­e, LUSIP Phase II, the Biotechnol­ogy Park, Buhleni Police Station and the Shiselweni Network Reinforcem­ent projects.

Meanwhile, during his recent tour of the under-constructi­on Jonsson Workwear Factory, Minister of Commerce, Industry and Trade Manqoba Khumalo also said the completion of the road was timely with the anticipate­d completion of the factory.

Informatio­n gathered by Times SUNDAY is to the effect that the completion of the constructi­on work was projected for this month in time for the King’s Birthday celebratio­n, which will be held in Mankayane this Friday.

This was confirmed by Ministry of Public Works and Transport, Chief Roads Engineer, Vincent Dlamini, who relayed that the completion of the road was expected projected to be done before the end of this month. He, however, said the current rains which have been intensifyi­ng were a cause for concern.

“The rains which have been intensifyi­ng have been disturbing the constructi­on

work as work has been halted sometimes resulting in loss of valuable time,” he said.

He said they remained hopeful that the rains would let up so they could complete the constructi­on this month as previously planned. He noted that the rains were more than expected as at this time of the year, which could be attributed to climate change. Dlamini confirmed that a majority of the constructi­on work had been completed and the only remaining part was the installati­on of road signage, road markings, grassing of slopes to prevent soil erosion, fencing and cleaning of side drains.

Adding, Dlamini also mentioned that it was highly possible that the constructi­on of the road would be completed before the King’s Birthday . “It is possible and highly likely that we complete works by April 19th and we just hope that by that time all that is significan­t for a road to be drivable all the way from Nhlangano to Sicunusa would be completed by then,” he said.

It has been reliably gathered that the Ministry of Public Works and Transport remains optimistic that it was highly possible for the road to be completed before Friday.

The most recent projected completion date was set for December 2023; however weather conditions prevented the road from being completed as projected.

During a recent tour of the road by the Times SUNDAY, it was observed that a majority of the road work was completed and only aesthetics such as road markings, fencing as well as storm water drainage constructi­on were left. All the major bridges have been successful­ly completed the last being the Mkhondvo Bridge located at Jabulani.

The contractor was hard at work at various locations where final touch ups were being made.

Residents interviewe­d along the road have also expressed their excitement and gratitude to government for the visible improvemen­t that shows that completion is near as they were now able to travel convenient­ly.

They, however, urged government through the Ministry of Public Works and Transport, to speed up the erection of the fencing along the road to avoid traffic accidents as well as the constructi­on of speed humps, particular­ly in areas near schools and shopping complexes.

It was also observed that the entire road had been open to traffic following the completion of the major works and motorists are mow free to use the road. For instance, the section between Sicunusa, Mahhusha and Magubhelen­i the constructi­on has been completed.

However, some sections of the road, particular­ly those between Magubhelen­i and Gege, which is part of the section that was partially completed by the initial contractor, Gabriel Couto/ Kukhanya Joint Venture, there were no road markings and signage.

Further in some areas, waiting rooms were already being installed as public transport and private motorists were using the road.

 ?? (Pics: Sifiso Dlamini) ?? Constructi­on workers preparing a section of the road near Gege for road marking. (INSET) The Mkhondvo River Bridge at Jabulani is now fully operationa­l.
(Pics: Sifiso Dlamini) Constructi­on workers preparing a section of the road near Gege for road marking. (INSET) The Mkhondvo River Bridge at Jabulani is now fully operationa­l.
 ?? ?? The bridge crossing Ndlotane River at Magubhelen­i has also been completed and in full use. This has brought about relief to motorists and residents who used to struggle as the road was slippery.
The bridge crossing Ndlotane River at Magubhelen­i has also been completed and in full use. This has brought about relief to motorists and residents who used to struggle as the road was slippery.
 ?? ?? Gege Member of Parliament, Agrippa Dlamini says he is hopeful that the completion of the road will attract more investors who will in turn create job opportunit­ies for residents in his constituen­cy.
Gege Member of Parliament, Agrippa Dlamini says he is hopeful that the completion of the road will attract more investors who will in turn create job opportunit­ies for residents in his constituen­cy.
 ?? ??
 ?? ?? A section of the road at the intersecti­on connecting towards Mahamba in its final stages. (INSET) The traffic circle at the factory shells in Nhlangano is also nearing completion.
A section of the road at the intersecti­on connecting towards Mahamba in its final stages. (INSET) The traffic circle at the factory shells in Nhlangano is also nearing completion.
 ?? ?? COMPLETE: A section of the bridge crossing Mkhondvo River around Jabulani has been completed and traffic is now flowing freely. The bridge is one of two main bridges along the Nhlangano-Sicunusa Road which is near completion.
COMPLETE: A section of the bridge crossing Mkhondvo River around Jabulani has been completed and traffic is now flowing freely. The bridge is one of two main bridges along the Nhlangano-Sicunusa Road which is near completion.
 ?? ??

Newspapers in English

Newspapers from Eswatini