AN UPDATE RECEIVED FROM THE FIJI ROADS AUTHORITY ON THE NEW DENARAU ISLAND BRIDGE IS AS FOLLOWS:

-

Demolition of existing (old) bridge – completed All the bridge piling work - completed Constructi­on of bridge headstocks - completed Bridge concrete abutment works - completed Installati­on of bridge main supporting steel beams - completed Constructi­on of bridge concrete decking slab – 90 per cent complete Installati­on of water and sewer main – 80 per cent complete nstallatio­n of electricit­y mains – 80 per cent complete Installati­on of telecommun­ication cabling - about 80 per cent complete.