AN UP­DATE RE­CEIVED FROM THE FIJI ROADS AUTHOR­ITY ON THE NEW DE­NA­RAU IS­LAND BRIDGE IS AS FOL­LOWS:

Fiji Sun - - Business -

De­mo­li­tion of ex­ist­ing (old) bridge – com­pleted All the bridge pil­ing work - com­pleted Con­struc­tion of bridge head­stocks - com­pleted Bridge con­crete abut­ment works - com­pleted In­stal­la­tion of bridge main sup­port­ing steel beams - com­pleted Con­struc­tion of bridge con­crete deck­ing slab – 90 per cent com­plete In­stal­la­tion of wa­ter and sewer main – 80 per cent com­plete nstal­la­tion of elec­tric­ity mains – 80 per cent com­plete In­stal­la­tion of telecom­mu­ni­ca­tion ca­bling - about 80 per cent com­plete.