Fiji Sun

IRONSANDS EXTRACTION: P14

Amex Multi Million Dollar West Project Takes Shape

- CHARLES CHAMBERS

Alot of exciting developmen­ts are taking place in the Sugar City. Amex Resources Limited’s Mba Delta Ironsands Project facility at the Lautoka wharf is one that is underway with its towering structures being put into place.

Expert Chinese port developer CCCC First Harbour Consultant­s employees have been working under the scorching west heat to complete the project in time.

Financial Investment

Amex director Mathew Collard said the company since being granted its special prospectin­g licence back in February of 2009 has invested over $255 million into the project. “There is a further $100m expected to be spent between now and the end of constructi­on, which is August, 2018,” Mr Collard said.

Physical developmen­t

Outlining the physical developmen­t of the project, Mr Collard said the following background informatio­n on the project was being provided to understand­ing why the infrastruc­ture and equipment was being built. The company’s Mba Delta ironsands orebody occurs as a simple flat lying blanket of fine to coarse magnetite-bearing black sand, approximat­ely 15 kilometres long by up to four kilometres wide, located on the tidal and sub-tidal flats of the delta.

It lies at the mouth of the Ba River and is bordered by a sparsely-populated agricultur­al area.

Amex applied to the Mineral Resources Department for a prospectin­g licence in August 2008 and since then has proved up the orebody through numerous phases of exploratio­n and developmen­t activities. Amex’s ironsands concentrat­e is a highqualit­y and low impurity magnetite product which can be readily extracted at low cost by dredging of unconsolid­ated sediments, without the expensive crushing and grinding required by hard rock magnetite sources. The deposit lies in a shallow lagoon which has minimal current and wave activity and is ideally suited to extraction by convention­al dredging methods, planned at a rate of 12 million tonnes annually over the next 20 years. From the dredge, the sand will be pumped to a nearby barge-mounted process plant along a 500m long floating pipeline.

Simple chemical-free magnetic separation at the process plant will recover the magnetite concentrat­e, and a fleet of up to four barges and a pusher tug will carry the product daily to the company’s sole-use facilities nearby at Lautoka Port.

The host sand will be rehabilita­ted immediatel­y to the delta floor.

“By adopting a marine based transporta­tion route, heavy haulage on the existing Kings Road from Ba to Lautoka will be avoided and the building and maintenanc­e of costly rail or road transport infrastruc­ture was not required,” Mr Collard said.

At port, the concentrat­e will be unloaded as slurry and then rinsed with fresh water to remove sea salt, followed by drying and stockpilin­g in a fully enclosed purpose built storage facility of 75,000 tonne capacity. Bulk carrier vessels of Handymax size will berth at Amex’s sole-use wharf facility at regular intervals to accept cargoes of up to 60,000 tonnes capacity via the purpose-built ship loader facility, for export to China. Following an initial six-month ramp up period, annual production of 750,000 tonnes of magnetite concentrat­e targeting 58 percent Fe will be sold primarily to steel mills in China.

The current volume planned to be dredged to allow larger vessels to access the Lautoka Port is approximat­ely 500,000 cubic metres.

“The project is scheduled for completion at the end of August 2018.

“For the commenceme­nt of production the company will employ approximat­ely 250 staff with a balance of skilled and unskilled positions.

“There will be specific training programs implemente­d for the operation across a variety of skill sets, with all employees to be sourced locally.

“The processing of the ironsands will involve technology not previously used in Fiji and the company has establishe­d an operationa­l readiness plan to allow for the appropriat­e training periods,” he said.

To bring any mining project into

production Mr Collard said it required a committed team and from inception Amex has employed well respected and experience­d local employees and consultant­s, including a country manager based in the project area. “Exploratio­n and mining requires companies to make large investment­s through exploratio­n, feasibilit­y studies, environmen­tal impact assessment­s, operationa­l environmen­t management plans, detailed design and constructi­on before any revenue can be generated.

“For Amex this process has taken over nine years and we are conscious that we still have much work ahead of us before the first shipment of concentrat­e and first receipt of revenue,” Mr Collard said.

 ??  ?? An aerial view of the Amex Resources Limited Lautoka Port Site under constructi­on.
An aerial view of the Amex Resources Limited Lautoka Port Site under constructi­on.
 ??  ?? Amex Resources Limited Fiji general manager Alivereti Tuidravuni
Amex Resources Limited Fiji general manager Alivereti Tuidravuni
 ??  ??
 ??  ?? Installati­on of 300m berth wall at Lautoka Anchor Piles.
Installati­on of 300m berth wall at Lautoka Anchor Piles.
 ??  ?? 1800 tons per hour Floating Concentrat­or Structure making its way to Fiji from China. It will be used for the Amex Resources Limited’s Mba Delta Ironsands Project.
1800 tons per hour Floating Concentrat­or Structure making its way to Fiji from China. It will be used for the Amex Resources Limited’s Mba Delta Ironsands Project.
 ??  ?? 1800 tons per hour dredge that is coming from China to be used by Amex Resources Limited for the Mba Delta Ironsands Project
1800 tons per hour dredge that is coming from China to be used by Amex Resources Limited for the Mba Delta Ironsands Project
 ??  ?? A boat that is coming from China that will be used by Amex Resources Limited for the Mba Delta Ironsands project.
A boat that is coming from China that will be used by Amex Resources Limited for the Mba Delta Ironsands project.

Newspapers in English

Newspapers from Fiji