Hasmukh Patel, Energy Fiji Limited, CEO

We had some technical issues with our Diesel Generators at the Savusavu Power Station towards the end of December, 2018 which affected power supply to our customers in Savusavu. EFL engineers were able to resolve these issues to get the power station fully operationa­l. With the heavy rains due to the inclement weather conditions experience­d around the country towards the end of December 2018, a landslide had brought down a Power Pole at Bagaraki Settlement. This caused an unplanned power outage affecting some of our customers from Naqelekula to Uluvalili Settlement. Our teams worked around the clock to straighten the affected power pole and repair the damaged hardware (cross arms) before power supply was restored.

In the month of February, 2019 there were 5 unplanned outages in different parts of Savusavu. Most of these outages were due to transient faults caused by the inclement weather conditions (heavy afternoon downpours) in the surroundin­g areas. In one incident, power supply was temporaril­y affected to remove a dead pigeon from the power line in front of Hot Bread Kitchen in Main Street, Savusavu. These works were undertaken from 11:00pm to minimise the impact of the outage on our valued customers. EFL has some 220km of power lines providing power supply to our valued customers in Savusavu. To ensure safety, reliabilit­y and security of power supply, we need to carry out regular repairs and maintenanc­e of the power line hardware and clearing of vegetation from around the power lines. In order to ensure the safety of EFL teams and the general public, power supply to the various areas need to be deenergise­d for the advertised duration of these planned maintenanc­e works.

Due to the adverse weather conditions, we were only able to partially complete maintenanc­e works in the Vakativa to Uluivalili areas around Savusavu in the month of December, 2018. The remaining maintenanc­e works had to be deferred to January and February, 2019 and we have had 8 planned outages for repair and maintenanc­e in the month of January, 2019 to ensure reliabilit­y and security of power supply.

Newspapers in English

Newspapers from Fiji