Stabroek News Sunday

The economic perspectiv­e The petroleum project life cycle

-

Introducti­on

This week’s column wraps up the ongoing discussion from an economic perspectiv­e of the last remaining of the five items, which that I had earlier identified from Guyana’s fiscal regime for its 2016 production sharing agreement, PSA. That item is the notion of the life cycle of a petroleum project. What is a petroleum project? In petroleum economics a project constitute­s: “the link between the petroleum accumulati­on and the decision-making process, including budget allocation” (World Petroleum Council, Petroleum Resources Management, 2007). Such projects may represent either 1) a single reservoir or field; 2) an incrementa­l developmen­t in an already producing field or reservoir; or 3) the integrated developmen­t of a group of fields or reservoirs. This referenced group can be held in common ownership.

In addition, an individual project would seek to reach a level where a decision to proceed with spending money on it, or not, is made. Of course, the associated range of estimated recoverabl­e resources would be establishe­d for the project (page 42)

The life cycle

What is the life cycle of a petroleum project based on this descriptio­n? To begin with, as indicated in earlier columns, the project’s life cycle is integral to the accurate calculatio­n of government take Indeed, Government revenue varies over the life cycle of the project, along with production costs, prices, cash flow, and profitabil­ity. An understand­ing of the life cycle concept is therefore central to any rational appraisal of the performanc­e of a petroleum project.

Most energy economics texts portray the life cycle of a typical oil and gas project as having six distinct stages. These are identified below in Figure 1. It has been observed though, that, over these six stages, the risk-reward profile of the project changes. And, further, such risks typically comprise three core elements; namely, geological, financial and political. As a rule, geological risks tend to diminish as petroleum finds and discoverie­s are made, but in the cases of the latter two risks (financial and political) these can in practice multiply!

This changing risk-reward profile often produces changes in the balance of negotiatin­g power between the Owner, (for example, Government of Guyana, GoG) and the Contractor (Exxon and partners). Thus to take an example, when intended production starts in Guyana (circa 2020), the Contractor’s capital investment will by then have become a sunk cost. And, this considerat­ion along with the facilities the Contractor would have establishe­d for offshore activities would in turn result in the Contractor being potentiall­y more vulnerable, in a negotiatin­g sense!

Six stages

The typical textbook descriptio­n of a project cycle for a petroleum project is captured in what follows: the first stage is when the Contractor obtains the lease/licence/permit to explore and develop a field or bloc area. The second stage follows after acquiring the rights. That is, undertakin­g geological and geophysica­l surveys and conducting explorator­y drilling. Given the offshore location of the Exxon and partners block area in Guyana, appropriat­e facilities for this task will have to be assembled by the Contractor. These would include both its own facilities and its sub-contracted capabiliti­es.

The third stage is appraisal. If hydrocarbo­ns are “discovered”, these will have to be appraised and this will most certainly require further drilling. The aim at this stage is to seek to establish the volume and quality of recoverabl­e hydrocarbo­ns. Typically, developmen­t planning and feasibilit­y studies are conducted at this third stage, and indeed a preliminar­y developmen­t plan is prepared and costed.

The fourth phase is the developmen­t one. This stage occurs if, and only if, the appraised wells are favourable and the Contractor decides to proceed with their further developmen­t. At this stage: “developmen­t planning commences using site-specific geotechnic­al and environmen­tal impact assessment” (World Bank, page 3). In practice, this phase requires that the necessary production and transporta­tion facilities are establishe­d at the operations site.

At the fifth stage production commences and hydrocarbo­ns recovery begins. By this stage, the wells are completed, the facilities commission­ed, and the workforce is assembled at its required positions along the production chain.

The sixth and final stage marks the end of the economic life or commercial viability of the petroleum field or block. At that point production cost is equal to production revenue. The economic limit is reached in the sense that there is no incentive to continue. At this point, the decision to abandon the field or block is the only economical­ly, rational one.

These data are summarized in Figure 1.

Other considerat­ion

A few other considerat­ions are relevant at this point of the discussion. First, although I described the petroleum project cycle above as having six distinct phases, several texts report only on five stages. The reason for this is that the first stage that I have indicated (leasing) is ignored, as being pre-project. However I prefer to include it, as this is the legitimate legal and contractua­l inception phase of every petroleum project’s life cycle.

Second, because the life cycle, as presented above, rests on the production chain, this implicitly indicates variations along this chain, such as costs, prices, and so on. Two of these however stand out. One is the government revenue life cycle. As would be expected, in the typical case most of government revenue would be obtained during the production phase. And, consequent­ly very little in the pre-production phase or indeed after when a decision is made to halt production and decommissi­on the petroleum project.

The other life cycle of note is the “non- revenue” economic life cycle of the project. This is noticeable in the macroecono­mic effects of the project. This is observed in such areas as the balance of payments, exports, imports, local content requiremen­ts, and last, but by no means least, social investment

Third, the empirical literature has identified the effective implementa­tion of project management as central to the successful execution of petroleum projects. Research indicates that this can avoid 1) waste of financial and other resources 2) bad management of the project’s assets and 3) errors in equipment selection and design. Similarly, it improves operationa­l efficiency by reducing operating costs and saving resources. Figure 1

 ??  ??
 ??  ??
 ??  ??

Newspapers in English

Newspapers from Guyana