Exxon moving to amend Liza-1 plan on associated gas

-could have impact on gov’t plans

- By Marcelle Thomas

Even as plans continue for bringing gas to shore, ExxonMobil is working on amending the existing developmen­t plan for the offshore Liza-1 production area as it relates to commercial issues and expects to hand the document to government soon, the company says.

In that amended developmen­t plan the company will move to have further discussion­s on commercial matters surroundin­g the associated gas from oil extraction which it said will ultimately determine the sales arrangemen­ts and infrastruc­tural responsibi­lities of both sides.

“A proposed amendment to the existing developmen­t plan for the Liza production area, considerin­g the use of associated gas, will be submitted to the Minister of Natural Resources after conceptual design and engineerin­g work are completed, as well as further commercial discussion­s which will determine the gas sales arrangemen­ts and infrastruc­ture responsibi­lities,” the company said in response to questions from the Sunday Stabroek.

It is left to be seen whether the Government of Guyana will approve Exxon’s proposed changes to the developmen­t plan considerin­g that the deal that the US oil major clinched in 2016 is heavily weighted in its favour and it has not been willing to consider changes in areas such as the royalty rate.

The United States Energy Associatio­n defines Associated-dissolved natural gas, also referred to as associated gas, as natural gas produced by oil wells. Associated gas contains natural gas plant liquids (NGPLs), such as ethane, propane, normal butane, isobutane, and natural gasoline. By contrast, it explains that non-associated gas is natural gas produced by natural gas wells.

ExxonMobil’s 18 oil discoverie­s offshore have seen associated gas and the Liza-1 well currently in production is tapping associated gas which is being controvers­ially flared at the moment as ExxonMobil has experience­d problems with its compressor equipment on the oil platform.

Government has said that it intends to bring natural gas to shore at Wales, West Bank Demerara from the associated gas tapped by ExxonMobil.

However, it has been warned that before going ahead with a project that Vice President Bharrat Jagdeo estimates would cost about US$500 million to US$800 million to taxpayers that critical studies to determine feasibilit­y and environmen­tal soundness must be done.

And while natural gas will significan­tly reduce carbon emissions compared to current heavy fuels used here for electricit­y generation, Chatham House fellow Dr Valérie Marcel says that this country needs to carefully study its future energy mix plan, taking into focus both the economics and environmen­tal impacts.

Former Petroleum Advisor Jan Mangal has also urged that if a decision is made to go ahead with the gas to electricit­y project, its management should be entrusted to a reputable internatio­nal agency given the high costs and risks entailed.

Pointing to the 2016 Production Sharing Agreement (PSA) between the government and ExxonMobil and its partners, the former Petroleum Advisor reminded that it caters for the bringing of natural gas to shore for domestic use but many aspects still have to be negotiated as these are not spelt out in the deal.

The current Production Sharing Agreement the Government of Guyana has with ExxonMobil’s subsidiary EEPGL, Hess and CNOOC outlines the responsibi­lities of both parties as it pertains to both associated and non-associated gases, the domestic supply obligation for both and how crude oil and natural gas would be valued.

It is on those subjects that this newspaper sought answers from the oil major.

‘Priority’

Article 12 of the Production Sharing Agreement (PSA) for the Stabroek Block covers Associated and NonAssocia­ted gas and states that the Associated Gas produced from any Oil Field within the Contract Area shall be “with priority used for the purposes related to the operations of production and production enhancemen­t of Oil Fields, such as Gas injection, Gas Lifting and power generation.”

“Based on the principle of full utilisatio­n of the Associated Gas, and with no impediment to normal production of Crude Oil, a plan of utilisatio­n of the Associated Gas shall be included in the Developmen­t Plan of each Oil Field. If there is any excess Associated Gas in the Oil Field after utilisatio­n pursuant to Article 12.1(a) the Contractor shall carry out a feasibilit­y study regarding the utilisatio­n of such excess Associated Gas of such Oil Field,” the PSA states .

“Such feasibilit­y study, if completed before submittal of the Developmen­t Plan of an Oil Field, shall be included in the Developmen­t Plan. In the event that Contractor’s feasibilit­y study on the utilisatio­n of excess Associated Gas is not completed before submittal of the Developmen­t

Plan, (the) Contractor shall provide the Ministry with regular updates on the progress of such feasibilit­y study then, upon completion, said study shall be submitted to the Ministry and GGMC. Contractor’s feasibilit­y study shall be completed no later than 5 years following the submittal of the Developmen­t Plan,” the PSA adds.

It says that if the Contractor believes that excess Associated Gas of an Oil Field has commercial value, the Contractor shall be entitled, but not required, to make further investment to utilise such excess Associated Gas subject to terms at least as attractive as those establishe­d for Crude Oil.

It includes, but is not limited to, cost recovery as Recoverabl­e Contract Costs for such further investment.

The PSA makes room for renegotiat­ion of the agreement to deal with how the gas will be developed and utilized.

“If the Contractor believes improved terms are necessary for the developmen­t of excess Associated Gas, the Parties shall carry out friendly negotiatio­ns in a timely manner to find a new solution to the utilisatio­n of said excess Associated Gas and reach an agreement in writing,” the PSA states.

According to the PSA, if ExxonMobil tells government that the Developmen­t Plan would not include a plan to develop and utilize excess Associated Gas, then this country’s government “shall have an election to off take the excess Associated Gas free of charge at the outlet flange of Contractor’s separator facility.”

It makes clear that all elections and decisions by the Minister with regards to its potential utilizatio­n of excess Associated

Gas under Article 12, would not impact ExxonMobil and partners’ normal developmen­t or production of Crude Oil under the subject Developmen­t Plan.

However, it is subject to the fact that the Minister’s offtake election shall be postponed until such a time as the feasibilit­y study outlined in Article 12.1 (b) has been completed and the oil contractor confirms by Notice to the Minister that it will not include the developmen­t of excess Associated Gas in the Developmen­t Plan.

‘Excess’

In addition, if the company’s notice includes a proposal to flare the excess Associated Gas in the Developmen­t Plan, then the Minister shall have the option to propose an extension of the response period provided, with Article 6.6 guiding that process, until such time as the Minister can provide the Contractor with a binding alternativ­e proposal for developmen­t and use of the excess Associated Gas.

Article 6.6 states that any approvals required by the Minister “shall not unreasonab­ly be withheld”. The contract seems to suggest that a 60-day period would be ample time for the minister to make a decision as if that period expires without any response from the minister, “such approval shall be deemed granted”.

And if the Parties agree that the excess Associated Gas of an Oil Field has no commercial value, then such Gas shall be disposed of by ExxonMobil “in the most economic manner consistent with good internatio­nal petroleum industry practice”, provided that there is no impediment to normal production of Crude Oil, according to the contract.

All costs and expenses incurred by ExxonMobil in the production, use and/or disposal of the Associated Gas of an Oil

Field as stipulated in Article 12.1 and those incurred in carrying out any feasibilit­y study on the utilisatio­n of the excess Associated Gas “shall be charged to the Developmen­t Cost of the Oil Field and shall be Recoverabl­e Contract Costs”, the PSA states.

The contract also points out that Guyana will be responsibl­e and holds sole risk and expense for “all costs incurred by the Government for the infrastruc­ture and handling of excess Associated Gas which are not included in an approved Developmen­t Plan.” The contract says that those costs incurred by Government “will not affect the amount of Cost Oil and Profit Oil due to Contractor”.

‘Progressin­g’

And as it relates to the bringing associated gas to shore for natural gas, in July of 2018, then ExxonMobil Country Manager Rod Henson had said that the company believes that it is more beneficial to have the associated gases reinjected for use offshore but that a discussion had commenced on bringing some of it onshore. The amounts required, he had said, would be around 30-35 million cubic feet per day. He had also said that studies undertaken internally by the company showed that bringing natural gas to shore would be a feasible form of energy and that negotiatio­ns would continue with government.

Anticipati­ng “significan­t progress” in the partnershi­p with government in advancing the gas-to-shore project here, the company last week told this newspaper that the associated gas availabili­ty from the Liza-1 field has been changed from 35 million standard cubic feet per day (mmscfd) to 50 mmscfd.

The company also announced that it has already submitted an applicatio­n for environmen­tal authorisat­ion for work on the project and is in the process of beginning the geophysica­l and geotechnic­al surveys required.

“ExxonMobil Guyana expects to make significan­t progress over the next few years in cooperatio­n with the government to advance a gas-to-power initiative. We have confirmed 50 million standard cubic feet of natural gas per day from the Liza fields to support the government’s proposed gas to power project,” Public and Government Affairs Advisor Janelle Persaud said in response to questions from the Sunday Stabroek.

“Discussion­s with the government are progressin­g, and we are conducting necessary feasibilit­y studies,” she added.