Stabroek News Sunday

Patterson says Wales gas-to-shore plans half-baked, site was rejected

-as AFC calls for more studies to avoid largest ‘white elephant’

-

Although backing a gas-to-shore project here, main opposition coalition partner the Alliance for Change (AFC) on Friday warned that the current plan being pursued by the PPP/C government at Wales is not supported by the research done so far.

“We therefore demand that further detailed studies be conducted before the country is saddled with its largest ever PPP white elephant,” AFC General Secretary David Patterson told a news conference, where he underscore­d that the Wales location had been rejected by previous studies.

“Importantl­y, none of the studies commission­ed under the coalition administra­tion recommends the site selected by the PPP/C… As a matter of fact, it is important to note that Wales was considered among 10 sites but rejected in the studies,” Patterson added.

The government has said the estimated US$810-900 million project will produce power at around US 7 cents per KWH compared to US14 cents that the Guyana Power and Light is producing at but it has faced scrutiny over the selection of the Wales location.

Government has also announced that it has negotiated with ExxonMobil to increase the minimum commitment of gas from 30 MCFD (Million Cubic Feet per

Day) to 50 MCFD thereby moving the net potential power from 150 MW to 250MW.

Patterson said the projected costs of US$900 million is exclusive of costs for power generating plants as well as transmissi­on of the power to GPL power distributi­on stations.

“The studies utilised by the PPP listed the costs for the power plants and transmissi­on lines to be US$240 million and US$85 million respective­ly – which would make the total project cost approximat­ely – US$1.225 billion [a sum which] will be added to Exxon’s cost recovery total during the next four years,” he said.

Patterson stressed that the coalition used the same studies to plan a project that produced 188MW of power plus 2,200 barrels of LNG daily for a price tag of under US$600 million – half the amount that the PPP is pursuing.

Further, he noted that while the quantity of gas (50mfd) being proposed to be utilized by the PPP will only be guaranteed available for 11 years, the 30mfd which APNU+AFC planned to use will be fully available for 18 years.

“That’s correct folks, we will be paying US$112 million per year for this PPP project for a lifespan of eleven years – makes any sense to you?” he questioned.

Patterson noted that the PPP has presented a proposal to install a Liquefied Natural Gas (LNG) plant which it is claimed will produce approximat­ely 3,400 barrels per day. However, he said that in 2020, Guyana’s total Liquefied Petroleum Gas (LPG) usage was approximat­ely only 2,000 barrels per day, while the PPP has decided on a plant without the provision of any plans for utilisatio­n of the excess volumes. “The studies clearly state that exporting this small amount is not economical­ly viable,” he said, before adding that under the coalition government, studies had commenced to assess the possibilit­ies of powering the revised public transporta­tion system with excess gas. Unless such studies are completed, he said, any decisions on the gas to shore project remain premature and incomplete.

‘Woodlands over Wales’

He later released to the public a study commission­ed by ExxonMobil which concluded that the Wales location was less

suitable than a location at Woodlands, West Coast Berbice.

According to the undated “Powerplant Location Assessment Update,” a two-week field based assessment of Woodlands and Vreed-en-Hoop along with its associated industrial area of Wales found that Woodlands offers fewer constraint­s overall.

Specifical­ly, the report concludes that it would cost approximat­ely US$72 million more to develop and land the pipeline at Vreed-en-Hoop and construct the powerplant at Wales.

Concerns raised in the assessment update include the technical complexity related to landing the pipelines up river of the power plant. The study also noted that shallow water installati­on by anchored barge will restrict access to ship channels for two to three months while there would remain a high risk of marine traffic encroachin­g on the anchor lines.

“Pipeline would need to be buried 2-3 meters, possibly deeper if there are any plans to deepen the river; trenching barge will likely struggle with currents at the mouth of the river [and] 90 degree turn from the river into the plan is a significan­t installati­on challenge,” it adds.

In total, extra costs for locating the project at Wales was projected to include US$15 million for the transmissi­on line, US$10 million for the MVA new-build substation and US$25-$35 million for a low pressure gas line.

Cost estimates for the Woodland sites assumed that the pipeline would come ashore at Clonbrook, East Coast Demerara, which the study states is within sufficient distance of the projected industrial site.

“Inclusion of a broader Woodlands area would not affect costs as onward power/gas infrastruc­ture requiremen­ts are negligible,” it concludes.

The only category of constraint within which Woodlands outstrippe­d Wales was the impact on biodiversi­ty since the West Berbice Mangrove was found to be of a higher concentrat­ion value and more bio-diverse.

In fact, according to the report both landing sites, Vreed-en-hoop and Clonbrook, were found to be similarly prone to flooding.

Vice President Bharrat Jagdeo had claimed last Monday that the Wales location was chosen because the studies conducted under the APNU+AFC administra­tion determined its suitabilit­y against flooding and the high population density of other sites identified, in addition to its expansion potential.

This is, however, a direct contrast to the contents of three of the five studies released by the PPP/C and the sixth study released by Patterson.

Following the findings of the ExxonMobil location assessment, a 2017 update of Guyana’s “Generation Expansion Study” by Colombian company Brugman S A S reported that “Woodlands was the most promising landing site of the proposed pipeline.” This study was funded by the Inter-American Developmen­t Bank.

Another IDB study, which was conducted in 2018 by United Kingdom company Energy Narrative, utilised these conclusion­s to determine that the gas-to-shore project was both economical­ly and financiall­y feasible.

The study, titled “Overall feasibilit­y study for Guyana’s Offshore Natural Gas Pipeline, LPG separation plant and related electricit­y infrastruc­ture,” noted that Woodlands was selected as the landing site after an extensive site selection process, led by a cross-agency team including representa­tives from the Guyana Energy Agency, Guyana Power & Light, the Ministry of Natural Resources, the Ministry of Business, the Ministry of Public Infrastruc­ture, the Guyana Lands & Surveys Commission, and the Maritime Administra­tion Department.

The 2018 study was an update of a 2017 desk study of the “Options, Cost, Economics, Impacts, and Key Considerat­ions of Transporti­ng and Utilising Natural Gas from Offshore Guyana for the Generation of Electricit­y”.

That 2017 study had concluded that Clonbrook was an optimal landing site for the 30 MMscfd [million standard cubic feet per day] pipeline. Woodlands was found to have the benefit of sufficient area (roughly 476 acres) for the planned natural-gas-fired power plant, the NGL separation and LPG production plant, and a potential industrial park.

“The site is not located near a port, however, and will require extensive site developmen­t work owing to the poor soil conditions at the location,” Energy Narrative added.

The primary objective of the 2018 study was to determine the overall feasibilit­y of transporti­ng natural gas from offshore Guyana, building an NGL separation and LPG production plant to market the liquids from the natural gas stream, and building a new electricit­y generation station to use the remaining dry natural gas.

Among the conclusion­s reached were that an offshore natural gas pipeline was economical­ly viable.

“Economic cost-benefit analysis (CBA) finds that the offshore natural gas pipeline has an aggregate net present value (NPV) of approximat­ely US$782 million and an economic rate of return of 30% percent under the project’s Base Case assumption­s,” it stated, before adding that a sensitivit­y analysis performed to estimate how changes in key variables would impact economic feasibilit­y found that the project remains feasible in every scenario.

“The pipeline shows the highest economic return under the 50 MMscf per day of natural gas volumes and the high oil price case, reaching nearly US$2.8 billion in net present value and a 52% economic rate of return,” it further noted.

According to Patterson, the coalition based its decision to utilise the lower quantity of 30mfd not only because of cost but particular­ly because of its commitment to transition the country to one hundred per cent renewables by 2040. “The Power Generation Study completed by the Coalition, provided a roadmap to this transition, with the introducti­on of a mid-scale hydro plant project by 2030. The decision to expend an additional US$600M at the expense of six years guaranteed gas supply is quite frankly – “voodoo economics,”” he added.

 ??  ?? David Patterson
David Patterson

Newspapers in English

Newspapers from Guyana