Stabroek News Sunday

Quantity surveyor calls for more info on terminated BBP pump station contract

- Donald Rodney

Quantity surveyor, Donald Rodney is calling for more informatio­n to be provided to the general public as it relates to the terminated Black Bush Polder (BBP) Pump Station project.

Some of his questions include what are the costs of moving any materials from the site to elsewhere and what is the weekly or monthly cost for these recurrent items? He is also seeking answers to whether the movement of materials from the site is under the surveillan­ce of an auditor.

In a recent letter to the Stabroek News, Rodney said that “a feature of this administra­tion, as well as the previous, is that very little in infrastruc­ture is transparen­t” as he added that those interested need to observe “what is said in relevant government answers and releases as well as carefully note points on which said answers are silent, in order to infer a picture.”

He pointed out, that now that the current opposition, with parts of the media, are productive­ly pressing the National Drainage and Irrigation Authority (NDIA) and the National Procuremen­t and Tender Administra­tion Board (NPTAB) in some way, on the terminatio­n of the almost $1B contract at Black Bush Polder, “answers must be provided.”

Despite several queries from the Sunday Stabroek to the Minister of Agricultur­e (MoA), Zulfikar Mustapha, and NDIA Chairman, Lionel Wordsworth throughout the week, no follow-up statement on the matter was provided.

Rodney in his letter pointed out that after a visit to the location by APNU+AFC MP Ganesh Mahipaul raised questions about corrosion of constructi­on steel languishin­g on site and being wasteful of taxpayers’ money, NDIA responded that this contract was terminated for poor quality and performanc­e of works and that the project will be retendered and that materials are being moved to a safe location.

“We have to assume all pre-conditions for an NDIA terminatio­n but must be mindful of the contractor’s right to challenge and to present its own case. From what NDIA has said the project was terminated on September 23 last. From that date, the informal license of the contractor to possession of the site is revoked and NDIA takes over certain responsibi­lities with their attendant costs, previously that of the terminated contractor: broadly these are, responsibi­lity for safety of the public including for small children who might wander onto the site; security for the project site against theft and vandalism; and protection of the works itself against deteriorat­ion”, he wrote.

According to Rodney, the MP raised his concern on the latter, in regard to the steel. Notwithsta­nding NDIA’s response, he said the MP “must keep up demands for informatio­n of this kind, including the cost of moving any materials elsewhere, since until the new contractor is physically on site, the mentioned items and costs are necessaril­y incurred, and under its governance role, NDIA now ought to assign responsibi­lity for these items, the costs of which will mount over time.”

He said, “Questions could include: what is the weekly or monthly cost for these recurrent items? Is the movement of materials from the site under the surveillan­ce of an auditor? Still on the matter of governance, once terminatio­n is made, there should be no further payment to the terminated contractor, until after a new contractor completes all work. Even valid payment certificat­es not yet disbursed to the terminated contractor must be stopped.”

He pointed out that in this regard, one of the releases stated “…a Project Completion Certificat­e would have been issued by the engineer for works completed and materials on site.”

“Editor, this statement is at best contradict­ory and raises a Red Flag as to if money was paid to the terminated contractor at this juncture. The MoA and NDIA themselves state that the project is not completed, only 14%; would the ‘experience­d engineer’ responsibl­e for the completion certificat­e be asked to give answers now – or must we all await his or her appearance before the Public Accounts Committee, in say five years’ time?”

Furthermor­e, he added, that the same release continues, “therefore, the contractor would only be paid for works that were satisfacto­rily completed and materials on site as is the case when there is a fundamenta­l breach of contract.” This statement compounds his dismay, he added, noting that if there is a ‘fundamenta­l breach’ resulting in terminatio­n “there must be no payment until the works are completed by a new contractor, all extra incurred costs are totaled as consequent­ial losses of NDIA, and the terminated contractor may well owe a debt to taxpayers. Prompt answers are particular­ly due from the Authority in regard to bonds.”

Additional­ly, he noted that the release also states that “at the time of terminatio­n, the advance mobilizati­on and performanc­e bonds were still active. As such, monies can be recouped.”

“Editor, these bonds have useby dates and hence must be demanded immediatel­y after default. Monies must be recouped – now – before the bonds expire. Question: what are the expiry dates of the bonds, and have they been called in? SN has posed the question of what would be the cost of re-tendering, to which some answers can be fielded in due course. In the meantime, NDIA has boldly stated it will provide informatio­n “… as it relates to transparen­cy and accountabi­lity of its projects”; hopefully the above will

help stimulate further questions”, Rodney added.

Following questions raised by Mahipaul, the NDIA on October 9th disclosed that the $978m contract for a pump station at Black Bush Polder, Corentyne was terminated in September for poor work and several others had been granted extensions for a

variety of reasons.

In its statement disclosing the terminatio­n of the BBP pump station contract, the NDIA did not identify the contractor but Mahipaul in a letter to the October 8th edition of Stabroek News had identified the company as Yunas Civil and Building Constructi­on.

“With regards to the constructi­on of the drain-age pump station to irrigate Black Bush Polder Farm-lands, Region No. 6, this project was terminated on September 25, 2023 by the NDIA for poor quality and performanc­e of works being executed. This project will soon be retendered”, the NDIA said.

 ?? ??
 ?? ?? The rusting steel rods (Ganesh Mahipaul photo)
The rusting steel rods (Ganesh Mahipaul photo)

Newspapers in English

Newspapers from Guyana