Stabroek News

Court allows gov’t to proceed with $4.6B GPL network rehab contract

-

The government can now proceed with the $4.6 billion contract awarded to a Chinese contractor for the rehabilita­tion of low and medium voltage distributi­on network for the Guyana Power and Light Inc (GPL) after acting Chief Justice Yonette Cummings-Edwards last Friday discharged an order she had previously made for them to defend the selection.

The order had been granted based on an applicatio­n by a rejected bidder, Fix-It Depot, which had argued that the contract was awarded to China National Machinery Import and Export/China Sinogy Electric Engineerin­g Co Ltd “in flagrant breach” of the Procuremen­t Act and the bid invitation as it did not meet the tender evaluation criteria.

In arriving at its decision, the court considered the government’s argument that the contract was one aimed at benefiting citizens through the renewal and upgrade of the electricit­y distributi­on network, which would include upgrading transforme­rs and meters, which are causing blackouts, line losses, inconvenie­nce and hardship to citizens.

The respondent­s, listed collective­ly as the Ministry of Public Infrastruc­ture, Senior Minister David Patterson, Permanent Secretary Balraj Balram, GPL, and the National Procuremen­t and Tender Administra­tion Board (NPTAB) and their representa­tives, had noted that the government was ready to release the funds to the Chinese group, but for the court proceeding­s.

The state had contended that the applicant stood to gain nothing from asking the court to quash the award of the contract to the Chinese conglomera­te, as this would only result in the contract having to be retendered.

This process, the respondent­s advanced, would last a minimum of six months, and could have resulted in the country losing access to the InterAmeri­can Developmen­t Bank (IDB) funded multimilli­on-dollar loan and grant.

The respondent­s had also defended the award of the $4.6 billion contract, citing, among other things, that Fix-It Depot, failed to meet the requiremen­ts of the bid.

In an affidavit in answer, they argued also that the applicants were aware that the contract was not governed by the Procuremen­t Act, but rather, by procuremen­t policies of the IDB. This, they said, was communicat­ed to the applicant by way of a correspond­ence, dated January 18, 2017. According to the government, the alleged breaches of the Procuremen­t Act, raised by the applicant, “are nonexisten­t.”

In a Notice of Motion filed by his attorney Devindra Kissoon, Paul James, of Fix-It Depot, was contending that his company’s bid, which was the lowest, was unfairly rejected and that GPL set out vague criteria for the award of the contract and even then did not apply it.

James also cited reports to the ministry that criticised the past performanc­e of the Chinese contractor and he charged that it was clear that it did not satisfy the evaluation criteria set out in the bid invitation, “it not having the experience to satisfy the bid requiremen­ts.” As a result, he argued that the decision to award the contract was “irrational, unlawful and a manifest error.”

In response, however, the government had said that the contract was awarded to the applicant who would have met all requiremen­ts “and not just the applicant with the lowest bid who may have failed to meet all the identified qualificat­ions.”

The engineer’s estimate for the project was $3.8 billion, while Fix-It-Depot’s bid was $3.5 billion. According to James, based on the criteria in the Procuremen­t Act and in the IDB Procuremen­t Policy, not only did his firm, in a joint venture with Colombian civil engineer Enrique Lourido Caicedo, submit the lowest evaluated tender but it had also submitted the lowest evaluated cost.

“The decision to award the contract to [the Chinese group] in no way benefits the public since the tendered sum is $1,093,737,993 higher than the Applicant’s tender, that amount resulting in a waste of taxpayers’ funds, being approximat­ely 25% higher than the Engineer’s estimate…,” James had said.

Among other things, the respondent­s had countered the applicant’s contention of the contract being “improperly” done, unfair, and in breach of natural justice, by advancing that there has in fact been no such breaches, as the applicant has no right to be heard prior to the awarding of the contract.

In its affidavit in answer, the state was contending that the applicant had failed to establish that the respondent­s have “made a decision in relation to the award of the contract” and that there was therefore nothing before the court “in relation to those Respondent­s to be quashed.”

James himself had noted that up to January 18, 2017, no money had been advanced to the group and no contract was yet in force.

He had resultantl­y asked the court to prohibit the respondent­s from concluding, entering into, or bringing into force, any contract with the Chinese group, to order that they reissue the bid invitation with clear criteria or to reconsider his bid on the basis that the award to the Chinese group was unlawful.

For its part, the government had said that the monies were ready to be disbursed to the company awarded the contract, and that the court proceeding­s were causing a delay in the country’s ability to utilise internatio­nal donor funding from the IDB and the European Union.

The government was adamant, that the applicant had failed to show, where, in the execution of its duties, it had acted unreasonab­ly, in bad faith or made decisions that were procedural­ly wrong or bad in law.

It had maintained that there were no averments suggesting any impropriet­y on its part, as it had, at all times, acted pursuant to its powers provided for in the IDB procuremen­t policies.

To James’ applicatio­n to the court for the award made by the government to be set aside, and to be called upon to show cause why this should not be done, the respondent­s had asked the court to discharge those applicatio­ns.

The rehabilita­tion of 328 km of GPL’s low and medium voltage network, including the procuremen­t and installati­on of smart meters throughout the network, is part of the Power Utility Upgrade Programme, which is intended to enhance the company’s operationa­l efficiency.

Newspapers in English

Newspapers from Guyana