Cabinet approves $809M for drainage projects
Over $809M has been approved for the National Drainage and Irrigation Authority (NDIA) to execute critical drainage works, a Ministry of Agriculture press release said yesterday.
Over $329M has been approved for the procurement of a Suction Cutter Head Dredge for the NDIA. This contract was awarded to the Guyana National Industrial Company Incorporated.
“The dredge will be used to execute major works to de-silt outfall channels which is critical during the rainy season .... ” Minister of Agriculture, Noel Holder said in the release.
Farmers and residents of Region Two will also benefit from the installation of a pump to assist in their drainage and irrigation challenges.
The contract which was awarded to Samaroo’s Investment at a cost of approximately $103M will see the installation of the drainage pump and the rehabilitation of the existing building at Three Friends, Essequibo, Region Two.
In addition, residents of Buxton, Region 4 will benefit from a new and improved pump station. The $376M contract which was awarded to General Engineering Supplies and Services Inc. will allow for efficient drainage in the Buxton/Friendship area.
The release added that government has been working with the regional bodies to ensure that critical works are executed and in a timely manner. To this end, $234M has been awarded to the NDIA to cover capital and current expenditure.