A complete review of current tendering system must be carried out as a matter of urgency

-

Dear Editor, It is not surprising to read the recent comments of the Hon. Minister of Finance recording dissatisfa­ction on the general poor performanc­e of consultant­s and contractor­s on many state sector projects.

However, his dissatisfa­ction coupled with a suggested proposal to import better skills, calls for a serious revisit of the procuremen­t systems for engaging consultant­s and contractor­s for constructi­on projects in the State Sector. Hence the following observatio­ns/comments are here offered for considerat­ion by the National Tender & Procuremen­t Administra­tion Board (NPTAB), the Ministry of Finance and the Ministry of Public Infrastruc­ture.

1.0) Current Conditions and Required Good Practices

.01 There is no register of qualified architects or engineers to inform the selection of consultant­s for the various projects and the varying levels of skills required, bearing in mind architects for buildings and engineers for civil/structural works. It is not unusual to see engineers being engaged for buildings while claiming to have a token architectu­ral skill on their team.

.02 The consultant­s must produce an adequate level of design informatio­n to provide the basis for credible tendering and constructi­on. A project is doomed from its inception where an unsuited consulting team is engaged.

.03 A successful major building project requires the involvemen­t of a good architect/team leader supported by a wellqualif­ied structural/civil engineer, building services engineer and quantity surveyor for effective cost control of a project.

.04 A highly questionab­le approach is the engagement of “project managers” who put together a list of skills with tenuous arrangemen­ts for their involvemen­t on the project being bid for. Such consultant­s often bid very low fees commensura­te with the quality of skills being offered by them. Also it is not unusual to have persons claiming project management skills after having attended a weekend seminar on the subject.

.05 Further, a graduate architect or engineer attains the profession­al status of architect/engineer after a period of profession­al practice in their respective discipline.

In the architectu­ral profession it requires a minimum of five years academic studies with two years of profession­al practice after which a profession­al practice examinatio­n is taken. While there are some alternate provisions for mature persons to be considered, they should have gained their practice experience under the guidance/employment of a recognized architectu­ral practice. The same applies to graduates from the University of Guyana architectu­ral degree programme.

During the period of practical training and thereafter, the duties of the architect exposes him/her to a fair degree of project management and coordinati­on of the work of the other consultant­s. No doubt an engineerin­g graduate may be similarly exposed for engineerin­g projects, provided they are engaged with a reputable engineerin­g practice. 2.0) Credible Tender Documents

.01 In recent times the writer has been shown tender documents for at least two major building projects in the State Sector that are highly deficient. No architect, engineer nor quantity surveyor has been identified. Further, only layout drawings and scant bills of quantities overloaded with provisiona­l sums were provided for tendering.

Note: Provisiona­l sums are all subject to remeasurem­ent/adjustment as the relevant work is completed. This is not a reliable basis for cost control and results in unnecessar­y cost overruns on a contract. It is not unusual for such items to result in delays due to the late or non-issue of the required documentat­ion for timely constructi­on. 3.0) Codes of Conduct

.01 A profession­ally qualified architect and no doubt engineer is governed by a Code of Conduct that requires a level of competence and performanc­e consistent with the high standards of their respective profession­s. It also includes the bidding or undertakin­g of work that is within the competence of their organizati­on or where necessary with firm arrangemen­ts for supplement­ary skills in place.

It therefore follows that a bidding consultant, who is not fully aware of the extent and quality of expertise needed to complete a project, cannot provide a reliable technical or financial proposal. Unreliable proposals would most certainly negatively impact the service provided and result in cost and time overruns. 4.0 Selection of Contractor­s

.01 The eligibilit­y of a contractor to tender for a project is the basis for an effective selection process. Demonstrat­ed financial capacity, skills and organizati­onal ability are all critical to the successful completion of any project. What needs to be borne in mind is that such qualificat­ions carry a cost which must be reflected in the tender sum. An unusually low tender sum in comparison with the other bids needs to be fully examined.

.02 A quick perusal of the list of bidders for the various constructi­on projects reveals some obvious questions.

The disparity in prices – are they all pricing from the same tender documents with or without reference to the Engineer’s Estimate. Alternativ­ely, some of the named bidders may be less qualified than others in the bidding.

.03 An example of this is in the recent tender results for an Extension of the Ministry of Business Head Office. Bids were received from five (5) contractor­s.

The Engineer’s Estimate (EE) was G$89.8M. The lowest bid was G$88.7M (G$1.1M below the EE); the next was G$99.9 (G$10.1 M above EE and G$11.2 above the lowest bid); the highest of the remaining bids was G$132.3M.

The mean bid price of the other four tenders is G$115.025M, G$26.325M or 29.7% above the lowest bid of G$88.7M.

Is there an error in the lowest bid; it doesn’t seem logical that the other bidders may have all gone wrong in computing their bid.

.04 The other question is the proximity of the lowest bid to the Engineer’s Estimate.

Is there a fundamenta­l discrepanc­y in the tender documents of which only the lowest bidder had become aware, thereby giving him an advantage in bidding? Such as excessive quantities for some items in the Bills of Quantities that may cushion lower rates for those items. There is much room for collusion in such situations.

.05 Given the general rule that the lowest bid is considered the best – an award to that lowest bidder is most likely. But are there many cost implicatio­ns in such an award? Whatever, it calls for a thorough review applying all the available technical expertise to look beyond mere arithmetic­al checks of the entire process. In such instances the comments/advice of the Design Consul-tant are essential.

Note – It seems that contract has since been awarded to the lowest bidder. 5.0) Observatio­ns

.01 In the scenarios described above it is apparent that there needs to be a clear understand­ing of the procuremen­t objectives and their priority in a tender process. To obtain a satisfacto­rily completed quality project the lowest price may not be the best; this seems to be the governing criteria; conversely highest does not guarantee the best finished project.

.02 Resorting to the use of offshore consultant­s and contractor­s for the non internatio­nal funded projects will certainly lead to the higher costs which are being avoided in the current system and improvemen­ts in quality may not be guaranteed. (See 5.05)

.03 The logical step is to first make the tendering procuremen­t process more attractive to competent consultant­s and contractor­s, who, at much expense, prepare bids with an expectatio­n of a level playing field.

The quality of the terms of reference/ scope of works for consultant­s and for contractor­s, such as adequate drawings, specificat­ions or bills of quantities, together with a reasonable time frame for the return of tenders, often determine the quality of the bids offered or whether it is worthwhile bidding for.

.04 A good example of the latter is the recent bidding for a hinterland project involving the supervisio­n of major corrective works on a secondary school building. As reported in the media, six consulting firms were invited, one of which asked to be excused for ethical reasons due to a previous involvemen­t in identifyin­g the scope of required works that prevented his further participat­ion on that project. The given return date for the bids was five (5) days including the weekend. The bidding exercise included costing for fulltime on-site personnel, air travel to the location and other related costs. From informatio­n gathered by the writer after the bid opening, at least two of the remaining shortliste­d consultant­s felt that a serious bid could not be prepared in the limited time and abstained accordingl­y.

However, at the tender opening a letter was reportedly received from the sole bidding consultant in which it is reported due to insufficie­nt time a bid could not be completed and it was indicated that a further week was required. A bid was submitted later and the contract was awarded to that consultant. The apparent irregulari­ties here are:i) The above referred to letter does not constitute a bid; it is a request for an extension to bid and should have been submitted prior to the close of bidding. It therefore should not have been considered a bid.

ii) The other short-listed consultant­s should have been duly informed and given the opportunit­y to submit a bid during the extended period, this was not done.

iii) The integrity and transparen­cy of the above process must be open to questionin­g since it leads to the bidding process being highly suspect. Were special concession­s granted exclusivel­y to one tenderer? .05 Procuremen­t of Offshore Skills While such procuremen­t is a valid requiremen­t for projects with internatio­nal funding, it is usually done within a framework of transferri­ng technology and expertise to develop local skills. Such a system is mutually beneficial where the local partner is able to provide guidance on certain local conditions such as climate, cultural patterns/behaviours etc. - soil types, engineerin­g and the engagement of local personnel/labourers etc.

There are two major recent projects where that practice was ignored and resulted in additional cost/delays:

i) The Arthur Chung Conference Centre which has been closed for major repairs, and

ii) The Marriott Hotel which we have been recently told requires major maintenanc­e works.

Both projects were carried out – design/build contracts – by solely Chinese personnel.

.06 It would be beneficial to all concerned to have a critical look at some of the major private sector projects, especially some of the successful­ly completed commercial banks and the basis of their procuremen­t and where necessary identify any areas of weaknesses or strengths. 6.0 Conclusion

.01 As a consultant with well over four decades experience in the local constructi­on industry with just enough state funded projects to count on both hands, the writer like some of his colleagues, has little interest in submitting proposals in the state sector when:

i) The expected level of bids is not commensura­te with the required inputs. Also if perchance you win an award, be sure to have the financial resources to withstand delays in receiving payments for work done.

An engineerin­g colleague was recently bemoaning the fact that his payments are six months in arrears and he has to continue working on that project.

ii) The credibilit­y of the bid documents is doubtful.

iii) The process by which bids are assessed for presentati­on to the Tender Board is lacking inputs from well experience­d technical persons.

Currently the entire process has many pitfalls, some of them may have been illustrate­d above.

.02 Consequent­ly the writer wishes to suggest that a complete and thorough review of the current tendering system, must as a matter of urgency, be carried out if we are to improve the quality of our completed constructi­on projects and in a timely and cost effective manner.

Perhaps the Minister of Public Infrastruc­ture, the Hon. Mr David Patterson, who is a highly qualified Quantity Surveyor and of long experience; and the Chairman of the NPTAB; Mr Berkley Wickham, a very experience­d Engineer; given their long involvemen­t in obtaining and assessing bids, may be allowed to contribute to that process, since both of these gentlemen are well aware of the systemic deficienci­es in the current procedures.

Similarly the profession­al institutio­ns such as the Guyana Institute of Architects, the Guyana Associatio­n of Profession­al Engineers and the local contractor­s associatio­n, should be actively involved and where necessary do their own house cleaning.

.03 Further, the procuring of bids is not an arm-chair exercise - crunching numbers as for other goods and services, it requires much knowledge and experience in constructi­on.

Coupled with that review should be an appraisal of the required skills available within the state and private sectors and where necessary initiate corrective measures in upgrading such personnel.

A study of the required skills levels for the expected developmen­t of our oil resources and the role of the constructi­on industry in such developmen­t must not be treated lightly.

Finally there are so many things to be fixed or fine-tuned. Perhaps if we start with a vision for Guyana and determine what is necessary to transform it into reality, may broaden our national perspectiv­e and avoid quick fixes. We had inherited from our colonial days high standards of profession­alism which ad hoc decisions in the past have undermined or destroyed. That mistake should be corrected and not be repeated.

There must be other views on this subject which, if brought forward may be of much value in the reforming of the procuremen­t process.

Thanking you.

Yours faithfully Albert Rodrigues, Dip.Arch., RIBA, MGIA. Chartered Architect