Stabroek News

Removal of utilities delays Timehri roundabout

-six-month project stalled for over a year

-

The constructi­on of a roundabout at Timehri, East Bank Demerara, which should have been completed in 24 weeks, has been stalled for more than a year due to “complicati­ons” regarding the removal of Guyana Telephone and Telegraph Company (GTT) and Guyana Water Incorporat­ed (GWI) utilities that were present at the site.

This is the explanatio­n provided by the Ministry of Public Infrastruc­ture, according to the 2017 Auditor General’s report, which was tabled last month in the National Assembly.

The $74 million contract for the project was approved by the National Procuremen­t and Tender Administra­tion Board (NPTAB) on August 2nd, 2017, and records show that the contractor, Gaico Constructi­on and General Services, was advanced just over 40% of the contract sum.

According to the report, the contract was awarded to the second lowest of 11 bidders. The engineer’s estimate was $102.920 million. Amounts totalling $30.800 million were paid to the contractor, while the sum of $628,568 was paid to the GRA as 2% withholdin­g tax, the report said. It added that under the contract the works comprised the constructi­on of a single lane rural roundabout and bypass road at the intersecti­on of the existing twolane road coming from the Cheddi Jagan Internatio­nal Airport (CJIA) and the newly constructe­d four lane roadway.

The report states that an audit examinatio­n of the payment vouchers, contract documents and a physical verificati­on on August 28th, 2018, revealed that the works were incomplete and were significan­tly behind schedule. The contractor was mobilised on site but only excavation and general earthworks had commenced on two small sections of the existing roadway; the advance payment bond expired since December 4th, 2017 and only 19.5% of the advanced payment was recovered at the time of reporting in August, 2018. No date was inserted in the signed contract agreement and as a result the Audit Office was only able to determine that the contract was signed sometime in August, 2017 and while according to the contract the duration for the completion of the works was 24 weeks from the letter of commenceme­nt, “at the time of reporting, a total of 12 months had elapsed and the works were still incomplete.”

The ministry, in response to these findings, explained that the contract time had elapsed and the works were not completed due to the complicati­on that arose with regards to the removal of utilities from the work area, namely GTT and GWI.

“These issues arose and required an additional $8.5M to remove GTT utilities and $11.5M for GWI utilities,” the ministry said, before adding that those delays caused works to be stalled until June, 2018.

Further, it was explained that the contractor was awaiting the removal of some light poles that the ministry should have removed by September 24th, 2018, before works could commence on the centre section of the roundabout.

Stabroek News was unable to ascertain if those poles were removed.

The ministry also said that due to the delay, the contract bonds have expired and that the contractor has been instructed to renew his bonds, which he is in the process of doing. The ministry added that based on the value of works, total payments were 19.2% of the contract sum.

As a result, Auditor General Deodat Sharma recommende­d that the Head of Budget Agency ensures that copies of the order to commence/letter of commenceme­nt, performanc­e bond and insurance for the works are submitted for audit examinatio­n and that the advance bond remains valid until the advance payment has been recovered.

He called on the ministry to also clarify whether or not the contractor has been granted any extensions of time and confirm if there is a new scheduled completion date for the works. Any approved extensions of time with justificat­ions should be submitted for audit examinatio­n, he said.

In June this year, subject minister David Patterson had said at the official opening of the Kitty Roundabout, that the circular intersecti­on at Timehri is one of two planned for Region Four. He did not say when it is expected to be completed.

The other roundabout will be constructe­d at the Sheriff Street, East Coast Embankment Road junction and it is being done as part of the Sheriff StreetMand­ela Avenue road upgrade and expansion project.

 ??  ??

Newspapers in English

Newspapers from Guyana