Stabroek News

GPL contingenc­y plans yield success as company awaits sub

-

Although the Guyana Power and Light Inc. (GPL) is still awaiting the repair of its 69kV submarine cable, it says its contingenc­y plans have resulted in power being fully restored around the country.

On June 2nd, one of GPL’s submarine cables was damaged by what was suspected to be an anchor from a vessel. The damage resulted in sporadic blackouts as the utility’s distributi­on system was crippled.

According to Ryan Ross, GPL’s Divisional Director of Projects, while power has been restored and there is currently no load shedding schedule being employed, the main submarine cable that was damaged last month has not yet been fixed.

Ross said GPL is currently waiting on the manufactur­er to build and send the repair kit, which they have already ordered.

Ross also dispelled reports about a second cable being damaged earlier this month and explained that while it was suspected, it was not true and that there was an incident that involved a ship anchoring in the area of the cable, there was no damage.

As a result of the damage to the cable last month and previous incidents, questions have been raised about the reason why GPL does not work along with the Maritime Administra­tion Department (MARAD) to prevent ships from anchoring in the area where the cables are located.

However, Ross noted that there is a system in place where the cable’s location is always identified on the mariners chart but the power company cannot enforce the regulation­s. He added that they have had consistent positive discussion­s on working together to prevent such incidents from occurring.

As part of its emergency response to the damage to the cable, the company decided to run a smaller 13.8 kV submarine cable from Vreed-en-Hoop to Kingston to supply additional power and carried out maintenanc­e on Kingston generating units.

Ross explained that while linking the substation­s with the smaller cable was not enough, it assisted significan­tly in restoring full power.

While the current capacity is enough to serve the country, Ross said that the company still needs to ensure that the submarine cable is fixed so that it can have more flexibilit­y, especially during peak hours, when there is a higher demand for electricit­y.

“GPL is working hard towards restoring it completely. Even though we have full power now, we would like to have the flexibilit­y so that if one area goes down, we can put together a contingenc­y plan quickly. While we are having full power, we are not very convinced we can operate the power system in an efficient manner. We require the link back to Vreed-en-Hoop,” he said, while stating that the submarine cable should be repaired within another two months.

Divisional Director of Operations Bharat Harjohn had said that the cable developed a fault on June 2nd, around 7.21 pm, which they suspect to have been caused by the anchor of a vessel. He said their distance relay detected that the faul metres from the Kin

An examinatio­n o power company had armor and insulation cable bore damage w the conductors withi

As a result of t power company had 14mW of power fed en-Hoop Power sta resulted in the eas Demerara-Berbice System (DBIS) havi approximat­ely 90mW able to satisfy a dem across the grid.

The company’s compounded after t third largest generat contribute 7.8 and 6. ly to the Kingston 2 p

 ??  ?? Head of the Co-operative Department Perlina
Head of the Co-operative Department Perlina

Newspapers in English

Newspapers from Guyana