Stabroek News

Sophia upgrades under IDB-funded housing project ahead of schedule

- By Dhanash Ramroop

Infrastruc­tural upgrades under the Sophia segment of the Inter-American Developmen­t Bank (IDB) funded Adequate Housing and Urban Accessibil­ity Programme are 25 per cent completed and the majority of the works are expected to be finished before the project end date of March 2020.

This was revealed by officials from the Central Housing and Planning Authority (CH&PA) following a walkabout around the community yesterday morning. The CH&PA is implementi­ng the IDB-funded project, which provides two housing initiative­s; the Core Home Support and Home Improvemen­t Subsidy. The project will be executed in four districts: areas in Georgetown; Industry to LBI on the East Coast of Demerara; Eccles to Diamond/ Grove on the East Bank of Demerara; and La Parfait Harmonie in Region Three.

Speaking at the event, CHPA Chief Executive Officer Lelon Saul said that under the project, they will be spending approximat­ely US$7.5 million in the Sophia, Greater Georgetown area, where they will upgrade 12 kilometres of roads to asphaltic concrete, upgrade the drains to concrete and upgrade two playfield areas along with other infrastruc­tural works.

He said that 2,000 residents will benefit from a home improvemen­t subsidy and 100 core houses will be built during the course of the project. For this year, the constructi­on of 50 core houses as well as distributi­on of 300 home improvemen­t subsidies will start.

According to the CH&PA Director of Projects Omar Narine, as it stands, the infrastruc­tural works are 25 per cent completed and while the project is planned to end on March 10th next year, they are ahead of schedule.

Currently six contractor­s – S Jagmohan Hardware Supplies, Shiraz Bacchus Constructi­on Service, KP Jagdeo Contractin­g Firm, H Nauth Contractin­g Service, Colin Talbot Contractin­g Service and Anirood Ramcharita­r Contractin­g Service – are executing infrastruc­tural developmen­t works that include upgrading roads to asphalt, constructi­ng concrete drains and walkways along with other civil works.

Narine said that all of the contractor­s were selected through the National Procuremen­t and Tender Administra­tion Board process and currently $857 million worth in contracts are being executed.

“Our original contract time is March 10, 2020 but four of the six contractor­s are scheduled to be completed in November and that is very good status and progress of works… This is only the first phase of works which includes 12km of roads; and in the second phase, which is scheduled to be tendered in about three weeks, will see another upgrading of a potential 6km of road,” Narine said.

He also revealed that they are currently doing pre-qualificat­ion for the constructi­on of the core houses. They are encouragin­g contractor­s from the area to elevate themselves and to get pre-qualified in order to be able to access contracts, he said.

Meanwhile, Project Engineer Anthony Ragnauth related that despite some delays due to the weather - which mainly affected road works - they were able to go ahead with the constructi­on of culverts, reinforced concrete drains and revetments. Out of the eight bridges planned to be constructe­d, two have been completed and they are in the process of mobilising to start constructi­on on another two, he said.

Giving a more detailed overview of the core houses and subsidies aspect of the project, Community Developmen­t Officer Donell Bess-Bascom explained that to date, they have completed a total of 456 house-to-house verificati­on visits for home improvemen­ts and 87 house-to-house verificati­on visits for the core homes aspect of the project.

“We are currently in the process of having the beneficiar­ies selected which right now is at the stage where the individual profiles are being prepared for each of the persons that score about 100 or more this time. And then we will move to a lower score depending on how many persons qualify,” she said.

Bess-Bascom explained that by the end of August to mid-September, they will be able to complete the beneficiar­y selection process and notify persons of the outcome of their applicatio­ns.

“Another part of the project that I think it is important to emphasise is the extensive community participat­ion. The community leaders across Sophia have been part of this entire process from the very beginning. As a matter of fact, they have influenced what was actually outlined in the operating manual for the programme,” she added.

Bess-Bascom explained that coming out of 2017, residents and community leaders would have insisted on there being clauses in contracts for residents to be employed for the ongoing works.

As a result, it has been included in the operating regulation­s of the programme that 30 per cent of the labour for the constructi­on of the core houses especially, must come from the area. This provision has been included in the contracts.

 ??  ?? Ongoing revetment works in Sophia.
Ongoing revetment works in Sophia.
 ??  ?? One of the concrete drains in Sophia that has been constructe­d so far.
One of the concrete drains in Sophia that has been constructe­d so far.
 ??  ?? One of the bridges being constructe­d that links B Field to A Field in Sophia
One of the bridges being constructe­d that links B Field to A Field in Sophia

Newspapers in English

Newspapers from Guyana