Stabroek News

Wharves and stellings

-

Not for the first time, citizens who use the Charity Wharf on a daily basis have complained about its visibly dilapidate­d state in the hope that it would finally get the attention it so badly deserves. Two years ago, residents of the area had expressed concerns over the state of the Charity Marketing Centre, which adjoins the wharf, pointing out that the piles holding up the structure were rotted, and it was sinking.

The wharf at Charity has been a danger to life and limb for over 18 years, according to Regional Chairman of Region Two (Pomeroon-Supenaam) Devanand Ramdatt, who was quoted in a report published in this newspaper on Monday last, though it appears that there had been some cosmetic repairs done roughly six years ago. This is according to a speedboat operator who uses the wharf regularly, although he noted that that fix also needed fixing once more.

Unfortunat­ely, the Charity wharf is not an anomaly. With the exception of perhaps the mooring at Moleson Creek, where the Guyana-Suriname ferry operates from, and perhaps the one at Good Hope/Supenaam, which has also had its own set of woes, wharves and stellings around the country have been allowed to fall into staggering disrepair.

In March 2006, constructi­on company BK Internatio­nal had been awarded a contract to the tune of $574.2 million to construct a new stelling at Good Hope/Supenaam as well as to rehabilita­te the marketing centre wharf at Charity. Apart from the Supenaam stelling being in an acute state of disrepair, it needed to be upgraded to facilitate the roll-on/roll-off ferries that the then PPP/C government was acquiring from China.

In April 2010, a section of the not-quite-complete Supenaam stelling sank causing much consternat­ion. Initially, the then minister of Transport and Hydraulics Robeson Benn had put it down to a mistake and nothing to be alarmed about as it was being corrected. However, two weeks later, with the issue still unaddresse­d, Head of BK Internatio­nal Brian Tiwari accused workers in Mr Benn’s ministry of making modificati­ons which compromise­d the structural integrity of the stelling. After a war of words between various members of the Jagdeo administra­tion and Mr Tiwari and the hiring of engineers to review the work done, the government was forced to expend more funds on making the structure usable. Neverthele­ss, it remained defective. On June 20, 2017, the current government announced the award of a contract worth $120.5 million to S Maraj Contractin­g Services for works to be done on the Supenaam Stelling.

At the same time, it also revealed that M Sukhai Contractin­g Services was awarded a contract worth $27.9 million for rehabilita­tion of the Morawhanna Stelling in Region One (Barima/Waini).

The stelling at Parika, which has been a crumbling eyesore for over a decade, will hopefully in the not too distant future see improvemen­ts. Last year, the Caribbean Developmen­t Bank announced that it had approved funding to the tune of US$4.4 million ($900 million) to finance feasibilit­y studies and designs for the constructi­on of a new bridge at Wismar, the upgrade of the Lethem aerodrome and a new transport terminal at Parika. And in February, five companies submitted bids ranging from $164.8 million to $312.2 million to conduct a feasibilit­y study for the design and constructi­on of a new stelling at Parika. In the meantime, in June this year, a $52.01 million contract was awarded to Memorex Enterprise for repairs to the Parika Ferry Stelling.

In 2014, while in opposition, the APNU had called out the then government on its inept approach to infrastruc­ture. In particular, the party had pointed to the neglect and disrepair of the Bartica, New Amsterdam, Parika, Rosignol, Stabroek, Vreed-enHoop and Wakenaam stellings. Further, shortly after it formed the new government with the AFC the next year, the government through its Ministry of Public Infrastruc­ture had announced that the Bartica, Leguan, Parika stellings were to undergo urgent repairs in 2016.

But the contract for the Leguan Stelling, which was so bad that it was likened to a death trap, was not awarded until September 2018. The intention was to build a new one while the residents continued to use the old. But before work could start on the $413.2 million contract, a part of the old stelling collapsed in January this year necessitat­ing urgent repairs.

The Vreed-en-Hoop and Georgetown ferry stellings and the extended Stabroek Wharf where some vendors still ply their trade are in very poor shape and need to be addressed given that they are usually pressed into hard use whenever the Demerara Harbour Bridge is out of operation.

The harbour bridge, which has been in existence since 1978 and provides a crucial link between the city and West Demerara and beyond, has only remained operable because it is stringentl­y maintained. In every other piece of infrastruc­ture referred to in this column, maintenanc­e has been inadequate to non-existent necessitat­ing the expenditur­e of millions of dollars to replace and rehabilita­te them.

It is incomprehe­nsible that in a country where waterways connect major towns, wharves and stellings could be so neglected. One would hope that going forward those in authority see it fit to maintain these structures on which billions of dollars are being spent.

Newspapers in English

Newspapers from Guyana