Stabroek News

-says T&D system continues to pose problems

-

The Guyana Power and Light Inc (GPL) has assured its customers that it remains committed to providing reliable electricit­y supply during the holiday season.

According to a press release on Monday, the utility company however went on to acknowledg­e that despite its efforts to ensure adequate generation, the inadequaci­es within its aged Transmissi­on and Distributi­on (T&D) network continues to pose problems. That being said, GPL, despite the circumstan­ces, declared that it would continue to make the most of the existing assets through proactive maintenanc­e and prudent operationa­l practices.

GPL says it would be concluding its pre-planned maintenanc­e activities on the T&D network on December 8 but will continue to ensure that any issues that could cause potential widespread outages during the holidays are addressed. The corporatio­n warns however, that this may mean having localised outages for shorter periods of time. GPL apologised for such situations but stated that they are a necessary inconvenie­nce given the vulnerabil­ities of the T&D network.

GPL has issued the following breakdown of available generation and projected demand for the areas it serves. It should be noted, it says, that in most instances the distributi­on network is radial and failure of any one component may result in service interrupti­on to customers. It however assures that every effort will be made to prevent these failures and to act promptly if they occur.

Demerara-Berbice Interconne­cted System (DBIS)

The current available generation capacity within the DBIS is 137 Megawatt (MW). Efforts are being made to maximise available generation capacity by, among other things, bringing back into operation generating units that were unavailabl­e due to scheduled maintenanc­e. Peak demand for this year has thus far hit 124.6 MW, which is about 7% higher than the peak for last year.

Essequibo & Islands Anna Regina

The three units at the Anna Regina

Power Plant provide a total of 5.4 MW. GPL has also maintained three Caterpilla­r units with total capacity of 3.8 MW to complement the three new sets. Peak demand is currently 5.3 MW and is expected to increase over time. The plan is to add a fourth 1.8 Heavy Fuel Oil (HFO) fired unit, which has been provided for at the current site, and a new 5 MW block by 2021.

Bartica

There will be 5.2 MW of generation available to provide customers in Bartica with an adequate power supply to meet the peak demand of approximat­ely 1.6 MW.

Leguan

Currently available at Leguan are units with an aggregate capacity of 0.8 MW. These units can adequately supply the peak demand of approximat­ely 0.3 MW.

Wakenaam

Wakenaam currently has a peak demand of approximat­ely 0.3 MW and customers can expect adequate power generation with an available capacity of 0.97 MW.

 ??  ?? Kathleen Campbell (left) and her sister, Fidella Peters
Kathleen Campbell (left) and her sister, Fidella Peters
 ??  ?? Kathleen Campbell (left, back) with some of the children
Kathleen Campbell (left, back) with some of the children

Newspapers in English

Newspapers from Guyana