Stabroek News

BK continuing Yarrowkabr­a school project despite contract terminatio­n

-

Even though it was ordered to cease work as a result of its contract being terminated, BK Internatio­nal is continuing with constructi­on on the $826.7 million Yarrowkabr­a Secondary School and says it has written to the government seeking a review of its decision to terminate the contract.

BK Internatio­nal spokespers­on Adam Harris on Friday told Stabroek News that the firm has written to Minister of Legal Affairs, Anil Nandlall, and copied the letter to President Irfaan Ali. He said that they are awaiting a response.

However, Nandlall, who is also the Attorney General (AG), said he has not received any correspond­ence from the company requesting a review.

Harris said that since notificati­on of the contract being terminated, they have received two visits but were never issued cease orders. He stated that within the first week of the terminatio­n, the design and supervisio­n consultant, Vikab Engineerin­g, visited the site and took photograph­s. On November 10, Chief Education Officer, Marcel Hutson, while on his way to Linden also visited the constructi­on site and never informed any of the workers to cease working, Harris said.

When contacted, Nandlall said he had written to the Minister of Education, Priya Manickchan­d, informing her of the terminatio­n. In a letter dated November 3, Nandlall advised

Manickchan­d that her ministry should take possession of the site since the contractor­s were instructed to vacate.

Harris contended that the company has completed 15% of works as opposed to the 5% stated by the AG in his missive on November 1.

Stabroek News had previously reported Harris as saying, “[ Nandlall] has cited that we would have completed 5% of works and we are saying this is not the case. We have completed 15% of works.” he added that it appeared that the AG used the findings of an official visit to the site at the end of June, when only 5% of the work was completed, to inform the decision rather than the progress made to date.

BK Engineer, Ganesh Shaw, told Stabroek News that the works completed thus far include the constructi­on of the foundation and columns to block “G and H,” and the foundation of “Block E and F.” According to Shaw, the firm was hoping to start column works this week and begin the foundation works of the other buildings by this weekend.

Nandlall, in a letter to the company dated November 1, had cited inordinate delays in the completion of the works to be the reason for the terminatio­n of the contract.

“Thus far, your company only completed 5% of the scheduled works. As a consequenc­e, your company has committed [a] fundamenta­l breach of the terms of the contract and as

a result the Government of Guyana hereby exercises its right to terminate the contract with immediate effect,” the letter which was sent to the Company Secretary, stated.

Harris had said that the delays that have occurred so far are not the company’s fault. He said that despite the contract being signed in December, 2019, no supervisin­g consultant was identified by the Ministry of Education, thereby preventing work from being carried out. He detailed that the Ministry appointed Vikab Engineerin­g Consultant­s Ltd as the consultant in March. However, before work could begin, measures to stem the spread of COVID-19, which included the suspension of public works, were enforced.

Harris added that it was only on June 1 that works began and at the end of June a site visit was done.

It is on these grounds the

company spokesman said that they are requesting a review of the terminatio­n of the contract. Harris added that should that request be denied, the company is prepared to challenge the terminatio­n in court.

A source familiar with the project and the procuremen­t process had previously told Stabroek News that due to the fact that the contract was awarded at the end of 2019, in the absence of budgetary allocation­s for 2020, the contractor was unable to access financing. This, he explained, severely hindered the progress of the project as

the contractor never received any mobilisati­on advance.

The contract, which is due to expire in March 2021, was awarded under the David Granger- led APNU+ AFC administra­tion, although at the time of the signing the coalition was regarded as a caretaker government and critics have said that a contract of the magnitude of the one for the school constructi­on should not have been awarded.

The Ministry of Education had previously announced the award of the contract for the constructi­on of the school to BK

Internatio­nal Inc at a cost of $826,757,737.

The ministry had said that the Yarrowkabr­a Secondary School on the Linden/Soesdyke Highway would boast modern amenities, including Informatio­n Technology Laboratori­es, an Allied Arts Department, a library, science laboratori­es and an auditorium.

The school is expected to have the capacity to accommodat­e 600 students from the Yarrowkabr­a community and other neighbouri­ng communitie­s along the Linden Highway.

 ??  ?? Minister of Education Dr Nicolette Henry (fifth from left) handing over the contract to CEO of BK Internatio­nal Inc, Brian Tiwarie on January 7th this year.
Minister of Education Dr Nicolette Henry (fifth from left) handing over the contract to CEO of BK Internatio­nal Inc, Brian Tiwarie on January 7th this year.

Newspapers in English

Newspapers from Guyana