Stabroek News

Gov’t used APNU+AFC studies to clear gas-to-shore...

-

the first 18 months to complete studies, complete engineerin­g, and conducting a competitiv­e tender for the constructi­on of the pipeline.”

There was also broad agreement on the key financial considerat­ions including: Estimated outer limit on the capital cost of the project, that funding of the pipeline by Exxon be out of Cost Oil (as defined in the 2016 Production Sharing Agreement with Exxon and partners), estimated cost per KWH delivered at the gate of the power plant at approximat­ely 3.5 cents per KWH.

Also, “Definition of the project to cover: i. Constructi­on of the pipeline by Exxon based on a competitiv­e tender ii. Natural Gas Liquids (NGL) that will allow (the Government of Guyana’s) share of the NGL to be sold whereby such revenue (is) expected to exceed the cost paid for the gas; iii. Constructi­on of a gas power plant (in phases) iv. Layout of Wales Developmen­t Authority to cater for a large expansion covering all of the above plus residentia­l developmen­t, mixed use, and industrial demand.”

The power points were expounded on by Jagdeo who stressed that government was using studies done by the former APNU+AFC Government as it presses ahead with other financial, environmen­tal and technical studies for the project.

Stabroek News expressed concern at government’s decision to use pre-existing studies alone to come to major decisions that would utilise billions of taxpayers’ dollars.

“I have never heard of a government anywhere, embarking on a project that might cost US$900M based on pre-existing studies. Particular­ly studies done under the previous government, (when the two government­s) don’t see eye to eye on anything. I don’t know how one can argue that we can embark on a major project like this. This is not purpose built to what the PPP/C might have envisaged in its manifesto or even before it came to office. When you rely on those (studies), it would seem to be opportunis­tic and solely intended to provide a certain result without you having designed a purpose built study that would (address) the PPP/C’s issues,” Stabroek News’ Editor-inChief Anand Persaud stated.

“One of the major concerns is that you are embarking on a project but yet you have come to major decisions on a lot of things. Embarking in that way, raises serious questions on the due diligence that has been done, or if at all and will be one of the lasting concerns that people have” about the project, he emphasised.

Jagdeo in reply stated that exhaustive work was done as a pre-requisite for the project but that his government understand­s that detailed studies are imperative to a final decision on the project and that is why it would soon begin those.

He promised that as those studies are ongoing, the public would be updated on findings and that government would be transparen­t in the execution of the project.

From work done, he informed, a decision on the route of the pipeline has already been made so that it is away from any encumbranc­es that could occur if it were to be run in the busy under shore of the Demerara River.

Instead, it will be routed to land at Crane on the West Coast of Demerara.

“The pipeline would not follow the route of the Demerara River. We are studying two routes and the engineers are working to determine which of the two routes, but both run in that area. Just parallel but a little bit further left,” he explained.

“The power plant is going to be located almost to the southern end of the layout. The residentia­l, commercial, business and other areas of the estate…those would be north. The river was found not suitable,” he added.

While it would only see 50 MCFD of gas brought in daily, the pipelines designed to bring in the gas would be 12 inches in diameter and have the potential to hold at least 120 MFCD of gas.

But he disclosed that although both sides have settled on 50 MCFD per day, it was not without exhaustive negotiatio­ns as ExxonMobil was adamant that it could only afford to give the promised 30 MFCD.

“Had a contention with Exxon too because they did not want to give us more than 30 (MCFD). But 30 would not allow us to generate 250MW … that we hope to get. The 50 (MCFD) would allow us to generate that and still have some additional gas that would remain for other purposes. We are looking at urea, polymers, proteins for the agricultur­e sector…Remember this is not a gas field, it is associated gas,” he said.

“The pipeline, that too was an issue. From the government’s side we insisted that there be a bigger pipeline to bring in additional gas. The 12 inches maximum would be 120 (MFCD)…So if anything happens you have a pipeline with storage. We are pushing for greater capacity to bring in gas there,” he added.

No FLNG

With financial analysis and data from countries that would have looked at Floating Liquid Natural Gas (FLNG) plants overwhelmi­ngly showing the project too costly, Jagdeo said that having an offshore plant was ruled out.

A Japanese study – one of the five used to arrive at decisions - had favoured FLNG and that country had said that it would help to develop that facility and take off the gas derived from it.

Such a facility too, Jagdeo agrees, would not help develop this country’s local content potential as only a few jobs would be created with profits only going to a few.

“We are not creating the conditions for economic rent for individual­s. We are creating the conditions so that Guyanese will have benefits,” he said and underscore­d that for all projects, current jobs such as cleaning, transporta­tion, brokerage, “all have to be Guyanese; not a single one but everyone. We are not creating for one.

Jagdeo said that Guyanese should hold government to the commitment that when the project, estimated to be completed by 2024, is commission­ed, they will have far cheaper energy.

 ??  ?? Vice President Bharrat Jagdeo (sixth from left) and his team.
Vice President Bharrat Jagdeo (sixth from left) and his team.

Newspapers in English

Newspapers from Guyana