Stabroek News

China Railway having difficulty raising $$ for Amaila hydro

-Jagdeo says project may have to be re-tendered

-

Unable to finance the constructi­on of the roughly US$1b Amaila Falls Hydropower Project (AFHP), China Railway Group Limited (CRGL) has written to the government requesting that it consider a different model of financing and this may now require re-tendering for the controvers­y-ridden project.

Speaking on the negotiatio­ns between the company and government, Vice President Bharrat Jagdeo yesterday told a press conference that CRGL had advised that they are “having a hard time doing the BOOT (Build, Own, Operate and Transfer) Contract and they want to shift to an EPC (Engineerin­g, Procuremen­t and Constructi­on) plus financing, where the government finances the project and they will be the contractor­s.”

According to Jagdeo the suggested method of financing is not possible at this time since those are not terms under which the company bid for the project. It is likely the government will have to re-tender the project if company fails to find the financing.

“We are still in negotiatio­ns. We are still trying to get them to meet the commitment that they bid for... if we can’t change that we can’t get it done under the BOOT, we can’t proceed with the company we will have to re-tender. We will not be able to conclude the contract,” Jagdeo said during the press conference at the Office of the President.

Government has been in negotiatio­ns since November last year and has not been able to make headway for an agreement on the project which has been on and off the agenda for over 15 years.

“The last six months we have been struggling to reach an agreement. We will have to give a deadline and cancel if they can’t proceed with the original model… The tender was about Build, Own, Operate, Transfer, not a EPC Plus finance model…so we may have a setback on that,” Jagdeo said.

The Vice President said that while this will delay their plans for the energy sector, the PPP/C government remains committed to ensuring the cost for energy is

reduced by 50%.

Pressed on what difficulti­es the company has been experienci­ng, Jagdeo said “they simply can’t raise financing.”

When asked if there are considerat­ions to engage the second most competitiv­e bidder, he responded in the negative stating that that bidder proposed a higher retail figure per kilowatt hour – US 9.9 cents.

CRGL in their bid proposed to sell electricit­y to the government at US$0.07737 per kWh. With the gas to energy project set to come on stream in several years, Jagdeo said it would not be feasible to lock in an agreement to purchase electricit­y higher than US 6 to 7 cents per kilowatt hour.

He stated that when the project was initially

conceptual­ised and was being undertaken by Sithe Global, a subsidiary of Blackstone, government was prepared to purchase electricit­y at US 10 cents per kilowatt hour since they were generating electricit­y at twice that cost.

Questioned too on whether government is prepared to engage in an EPC financing model should they return to tender, the Vice President said no considerat­ion has been given to that and it will have to be discussed extensivel­y before they make a commitment.

It was contended that the model chosen for the constructi­on of the AFHP was well thought out as government did not want to incur any debt.

Under the BOOT arrangemen­t, CRGL would have operated the project for twenty years before transferri­ng it to government.

Most capable

CRGL was awarded the contract on Cabinet’s no-objection after being deemed the “most capable partner” for the project.

A release from the Ministry of Finance had said the Chinese company will provide the entire equity required and undertake all the risks associated with the project and Guyana will not be investing any finances.

Jagdeo last November had said “Amaila still remains the best option for meeting baseload renewable energy for Guyana. That is the only way you can decarbonis­e, so the only way to achieve renewable energy is through the constructi­on of the hydropower,” while making reference to a Norway study done after the former David Granger-led administra­tion took office.

He explained that despite the delays and shelving of the project by the APNU+AFC coalition-led government in 2015, Guyana stands to benefit from a better deal. In the initial deal, he explained, electricit­y would have been purchased at US 10 cents per kWh but under the new deal GPL will be purchasing electricit­y at US 7 cents per kWh or lower.

Four companies – three Chinese and one Brazilian – responded to government’s Request for Proposals (RFPs) for the resuscitat­ion of the AFHP.

Government wants the project to be completed and commission­ed by the end of 2025.

According to the RFP, the Summary of Scope of Works entails a 165 MW installed hydro dam, plant, and related works; Transmissi­on Line and Structures: 270 KM double-circuit 230 KV from Amaila to Sophia; 230 KV Substation­s in Linden and Sophia; Creation of a 23 square KM storage reservoir; upgrades and completion of roads and bridges to the site (85 KM new; 122 KM existing); and assumption of all geo-technical risks including guarantees relating to the structure of the reservoir, dam and transmissi­on towers.

The hydro project, previously pegged at US$858.1 million, had been the flagship project of the PPP/C government when it was in power pre-2015. However, then opposition A Partnershi­p for National Unity (APNU) and the Alliance For Change (AFC) had used their joint oneseat majority to effectivel­y halt the project.

Once in government in 2015, the APNU+AFC coalition scrapped the project, citing costs and other concerns, while signalling that it was focusing on an energy mix with natural gas as a prime component.

A Norconsult report, which was meant to be a final study of the project and commission­ed under the Guyana-Norway partnershi­p, was generally favourable towards the venture but the APNU+AFC government interprete­d it differentl­y.

In September 2012, the then PPP/C government led by former President Donald Ramotar signed the initial agreement for the constructi­on of the project with Sithe Global and China Railway First Group.

 ?? ?? Vice President Bharrat Jagdeo at the press conference yesterday
Vice President Bharrat Jagdeo at the press conference yesterday

Newspapers in English

Newspapers from Guyana