Stabroek News

Bamia Primary School remains behind schedule rial, labour being blamed

- Aica,” Public Works Minister Juan this newspaper. He was commentort­ages faced across the country at

aid that although some quarries sed their capacity, it is still not that while some others may have l, transporta­tion seems to be an have increased their capacity and sufficient enough to meet the curds for aggregate and crusher run. ing here is not only being able to ne, it is the logistics. The biggest upply of crusher run is the supply; That is the issue and the issue is ” he said. Neverthele­ss, Blair statset to begin casting the beams and the upper floor. said that the availabili­ty of cement also fluctuated during the past ery project has that challenges. We supply fluctuatin­g. No availabili­ty and stone. So we had to put in o six months in advance and make nts to get materials,” Blair lamentmber, St8ment Investment princiFerg­uson, said that they had comst 35% to 40% of works. At that plained that they were still chalthe supply of sand steel, and stone, gh demand around the country. ding of the contract to Sta8ment to construct the school has faced severe criticism as the company not only lacks the track record of large scale constructi­on for public use but it also faced a backlash from civil society as it was only incorporat­ed in March of 2021 (eight months prior to being awarded the contract) and its principals were heavily involved in the entertainm­ent and sports industry. The project is being undertaken under the Ministry of Local Government and Regional Developmen­t and in July of last year, the bids were opened.

Four companies – Bulkan Timber Works Inc., ($349,595,065), St8ment Investment Inc., ($346,327,748), Orin’s Supreme Enterprise ($348,726,772), and A Nazir & Son Con-tracting & General Supplies ($340,549,671) – tendered for the project. St8ment, with the second-lowest bid, received the contract in November of 2021 which was signed by the principals of the company and Regional Executive Officer, Dwight John. The project was expected to last for 20 months and is intended to benefit almost 800 students. A oneyear defects liability period, after the completion of works, is catered for.

Based on the original expected duration of the project, the school should be completed around June next year. Works were stalled for over two months with no explanatio­n provided to the Regional Democratic Council in Region 10. Some $68 million had been paid over to the contractor. Around 10 months after the contract was awarded, this newspaper visited the site and it was evident that works had stalled. The steel on the foundation was already corroding and a large chunk of the foundation was yet to be completed. Stabroek News also observed that apart from a few wheelbarro­ws and a concrete mixer, there was no other equipment on site.

St8ment Investment Inc.,’s principals are Ferguson and Kerwin Bollers of Hits and Jams Entertainm­ent, along with Aubrey ‘Shanghai’

Major and Kashif Muhammed of the Kashif and Shanghai football tournament. The latter two have been appointed by the PPP/C government to state run boards, with Major as Chairman of the Guyana Tourism Authority, while Muhammed was appointed Chairman of the National Sports Commission.

 ?? ?? Quality Control Manager Akanni Blair (left) and a worker double checking the specificat­ions on site
Quality Control Manager Akanni Blair (left) and a worker double checking the specificat­ions on site
 ?? ?? Workers laying blocks for the walls of the administra­tive building
Workers laying blocks for the walls of the administra­tive building
 ?? ?? A view of the constructi­on from the western side of the compound
A view of the constructi­on from the western side of the compound
 ?? ?? Constructi­on of the septic tanks underway
Constructi­on of the septic tanks underway
 ?? ?? Steel and plyboard stockpiled on site
Steel and plyboard stockpiled on site

Newspapers in English

Newspapers from Guyana