Stabroek News

PPC report is a whitewash of the complaint by Akamai

- Dear Editor,

The Public Procuremen­t Commission (PPC) has finally issued a report based on a complaint from a contractor. Predictabl­y, the report is a whitewash of the administra­tive review process and falls short of the standards expected from a constituti­onal agency.

By way of background – the Office of the Prime Minister issued an invitation to bid for line hardware in March 2023 with the bid opening slated for April 2023. Five bids were returned, and unsurprisi­ngly the lowest bid by Akamai Inc. was the only bid deemed non-responsive. Akamai Inc. by the way is the sole distributo­r of the requested line hardware; hence it was expected that the company would submit the lowest bid.

The evaluation committee deemed Akamai Inc. non-responsive because it was claimed that:

a) the bidder failed to submit documentar­y evidence to demonstrat­e supply of similar goods in at least 1 contract in the last two (2) years to a minimum value of G$5M and

b) the bidder failed to provide a letter stating that the company had no terminated projects.

This is where it becomes interestin­g. There was no prescribed format for the submission of evidence of previous projects, and hence Akamai Inc. submitted a spreadshee­t detailing all their previous contracts, detailing the procuremen­t agencies as well the contract sums. However, not surprising­ly, in an effort to deem the bidder non-responsive, the procuremen­t agency found this detailed listing unacceptab­le.

Additional­ly, a simple conversati­on with the bidder revealed that he did in fact fulfill the second requiremen­t which the evaluation committee deemed non-responsive - which was a letter addressed to the procuring entity stating specifical­ly that none of their projects was ever terminated – clear evidence that this informatio­n was fraudulent­ly omitted by the evaluation committee or ignored.

In arriving at its report to support the award, the PPC never contacted the bidder, seeking clarificat­ions on the claims for debarment made in the evaluation report, as is standard when reviewing complaints, whereby all parties to the complaint should be given an opportunit­y to defend their position. The PPC simply adopted a defective report, performed no investigat­ive analysis and rubberstam­ped the award.

When contacted, the AFC-nominated commission­er within the PPC highlighte­d that a) both opposition commission­ers found the submission of the list of projects comprehens­ive and acceptable and b) that they were unware that the bidder had actually submitted the claimed missing letter regarding terminated projects. The AFC-nominated commission­er also informed that she recommende­d that natural justice procedures be adopted, whereby all parties should be given an opportunit­y to respond before a final decision is made by the commission, however this was overruled by the majority vote of the Commission.

Strangely, but not unsurprisi­ngly, the PPC failed to highlight that section 5 (5) (a) of the Procuremen­t Act specifical­ly states “a procuring entity may not disqualify a supplier or contractor on the ground that informatio­n submitted concerning the qualificat­ions of the supplier or contractor­s was inaccurate or incomplete in a non-material respect.” The claimed incomplete informatio­n as supplied by this contractor are all non-material in every respect, and in accordance with the Act, such non material deficienci­es can be remedied.

The PPC, a constituti­onal agency with an annual budget of almost $300M has taken eight months to respond to the bidder’s complaint, and in the end simply rubberstam­ped a defective and possibly fraudulent evaluation report, without even giving the complainan­t the opportunit­y to prove otherwise.

The public would have been mistaken if they assumed that any investigat­ion by PPC, would have been in-depth, whereby a review of the entire bidding process would have been conducted, including a full review of all documents submitted by all bidders, review of the responsive­ness of the bidders and then a final determinat­ion of who is deemed successful.

I anticipate a similar rubberstam­ping of NPTAB’s award of the Belle Vue pump station, when or if, the PPC ever responds to a complaint lodged since October 2023. I also expect a similar undemocrat­ic rubber stamping to the complaint on the award of the Bamia Secondary school lodged since February 2023 as democratic structures and institutio­ns in our nation continue to falter and become unrecogniz­able.

Newspapers in English

Newspapers from Guyana