Stabroek News

According to my independen­t study of GPL, the decline in its managerial performanc­e is a cause for concern

- Dear Editor,

There are credible reasons to believe that His Excellency, the President, Dr. Mohamed Irfaan Ali is being misled in a major way about issues in relation to the Guyana Power and Light Inc. (GPL). I don’t know by whom, but here is why. Although I am cognizant of the macro challenges over the last 15 years where the political opposition successful­ly blocked some of the major long-term investment­s such as the Amaila Falls hydropower project in 2011, and the lack of investment­s during their tenure in government for the period 20152020, there may be institutio­nal and managerial limitation­s on the part of GPL. With this in mind, in the height of the blackout season in 2023, I conducted my own independen­t analysis on GPL to have an understand­ing of the entity’s internal challenges. As such, the analysis and findings presented herein (summary of the analysis and findings) were derived from an examinatio­n of various GPL’s developmen­t and expansion plans for the period 2012-2016, 2016-2020, and 2021-2025, together with the National Budgets for the period 2012-2023, GPL’s annual reports and audited financial statements. The aim of the analysis conducted were as follows:

● To identify the expansion and developmen­t programmes of GPL, and the planned capital investment­s,

● To determine to what extent were the expansion plans and capital investment­s implemente­d, and

● To identify the implementa­tion and investment gaps based on the expansion plans, and the actual capital budgets as per the National Budgets.

The deteriorat­ion of GPL’s management actually began since 2012. In this respect, GPL failed to produce annual reports, which ought to be laid over to the National Assembly pursuant to Section 67 (1) of the Public Corporatio­ns Act (1988) for the years 2012-2022. Resultantl­y, it is difficult to independen­tly scrutinize the work of this entity for this period. Of note, GPL’s failure to produce annual reports for the past eleven (11) years is a flagrant violation of Section 67 (1) of the Public Corporatio­ns Act (1988). Section 67 (1) of the Public Corporatio­ns Act states the following… “A Corporatio­n shall, not later than six months after the expiry of each calendar year, submit to the concerned Minister a report containing” – (a) An account of its functionin­g throughout the preceding calendar year in such detail as the concerned Minister may direct; and (b) A statement of the accounts of the corporatio­n audited in accordance with section 48.

Section 67 (2) states that…” A copy of the report mentioned in subsection (1) together with a copy of the report of the auditor in relation to the same period shall be laid before the National Assembly not later than nine months after the expiry of the calendar year to which it relates”. Moreover, section 68 of the said Act establishe­s the “General Penalty” that shall be applied to everyone who is guilty of the contravent­ion of any provision of this Act.

GPL’s operating revenue grew from a position of $29 billion in 2012 to $37.9 billion in 2022 representi­ng an increase of $8.9 billion or 30.74%. For the same period (using 2012 as the base year), generating cost increased from $27 billion to $39.6 billion representi­ng an increase of $12.6 billion or 46%, while operating cost increased by $6 billion or 91.34%, and the net operating loss increased by $9.4 billion or 242.24%. The entity’s total assets increased from $47.9 billion in 2012 to reach $81.5 billion in 2022 reflecting an increase of $33.6 billion or 70%. Notably, non-current assets increased by $26 billion or 78% for the ten-years period under review.

Considerin­g that the budgetary allocation­s in the National Budgets are used to finance both capital expenditur­e and the shortfall in operating expenses, it therefore means that the increase in GPL’s non-current asset and the cumulative net operating deficit of GPL of $54.9 billion for the period, were financed by the $75.9 billion from the budget. This leaves a difference of $21 billion or an average of $2 billion annually that were not reflected in GPL’s balance sheet. Notwithsta­nding, it is likely that those sums were allocated to the other programmes in the energy sector such as the Hinterland Electrific­ation Programme, etc., that would be accounted for by other [isolated] entities, for example in Linden, Lethem, Port

Kaituma, Bartica etc.

The total funding gap for the period 2012-2022 is a whopping $78.3 billion. This gap can be explained by several factors. Ironically, the years 2012-2015 and prior (before crude oil was discovered offshore Guyana), there were no funding gaps save and except for the transforma­tional investment of the Amaila Falls hydropower project that was blocked by the Opposition. Another explanatio­n is that there could be an overestima­tion of the proposed capital budget in the expansion plans. However, this may be an unlikely factor given that the assessment conducted found a series of expansion and developmen­t plans for the period under review that remained unverified to determine whether those were implemente­d.

GPL’s Developmen­t and Expansion Plans for the period 2012-2025 - Proposed Developmen­t that were implemente­d based on the budgetary allocation­s in the National Budgets:

2012-2016

● Expansion of Kingston Power Plant by 15.8MW. Equipment and materials for constructi­on of new sub-stations, land acquired for Ruimveldt, Liliendaal, Good Hope, Columbia Mahaicony, Vreed-en-Hoop, Edinburgh, and Golden Grove.

● Integrated transmissi­on of 69 KV transferri­ng power from Skeldon to Essequibo Coast.

● Installati­on of submarine cable linking Vreed-enHoop and Kingston.

● 3 Wartsila generators procured with total capacity of 26 MW

● Installati­on of new Wartsila engines at Vreed-enHoop, upgrading of 7 substation­s, installati­on of transmissi­on lines from Sophia to Onverwagt, with a supervisor­y control and data acquisitio­n system.

● Pilot project to rewire sections of the distributi­on network to improve efficiency and reduce incidences of illegal connection­s.

● Two new substation­s built at Sophia and Good Hope, rehabilita­tion of and extension of transmissi­on and distributi­on networks.

2017-2023

● Constructi­on of Kingston Vreed-en-Hoop substation­s.

● Constructi­on of Kingston Vreed-en-Hoop substation­s.

● Solar farm interventi­ons, 33 MWs for Berbice, Essequibo, Linden

● 50 MWs of firm generating capacity to boost short term needs

● 413 km of new distributi­on lines and feeders; new 69 kV transmissi­on line from Kingston to Sophia and from Edinburgh to Hydronie, new rehabilita­ted substation­s at Hydronie, Sophia, Columbia, Canefield and No.53 Village; replacemen­t of 320 inefficien­t transforme­rs.

Other Investment­s that were not reflected in the expansion and developmen­t plans (2012-2025) but provided for in National Budgets.

● Completion of 4-new substation­s at Liliendaal, Ruimveldt, Golden Grove, and Columbia.

● Onverwagt substation upgraded, transmissi­on lines installed from Columbia to Onverwagt, fibre optic cables laid from Sophia to Garden of Eden.

● Relocation of power plant in Lethem and upgrading of power supply in Culvert City, Mahdia, and Linden.

● 830 km of main distributi­on network to be rehabilita­ted, aimed at reducing energy loss.

● Utility upgrade programme: distributi­on net work.

● Rehabilita­tion of over 800km of low and medium voltage network, spanning from Parika to Corentyne.

● Installati­on of 10 mini-grids and 4 off-grid systems, providing 1.472 kW of installed solar capacity, thereby generating 5,305 kWh of electricit­y (Sebai, Iwokrama, Waramdong, Paruima, Kurukabaru, Annai, St. Monica, Karaburi, Capoey, Whyaka, Loo and Creek).

● Installati­on of solar farms in Mahdia, Leguan, Bartica, Lethem.

● Provision for GTE.

● Constructi­on of 1.5MW hydropower plant at Kumu, and rehabilita­tion and upgrade of 700kW capacity of defunct Moco Moco hydropower plant, Region 9.

● Completion of 150 kw hydropower scheme at Kato and for 30,000 PV home systems for hinterland and riverain areas.

● Rehabilita­tion of 600 km of medium/low voltage distributi­on network.

● Constructi­on of parallel transmissi­on linking Kingston and New Sophia substation­s, upgrade of existing L5 transmissi­on line.

Developmen­t and Expansion Plans that were not implemente­d for the period 2012-2022 (these remained unverified)

● Berbice, 10MW upgrade and HFO conversion by 2011, Guysuco to provide 8-12 MW.

● 600kVa gensets at Leguan and another in Wakenaam (2012), 3MW HFO fired unit at Anna Regina and a used 2 MW HFO unit for Bartica.

● Constructi­on of a new 69Kv sub-station at Williamsbu­rg.

● Expansion of the 69kV network from Edingburg to Parika and further to Leguan, Wakenaam and the Essequibo Coast with sub-stations at Parika, Leguan, Wakenaam and two sub-stations on the Essequibo Coast.

● Constructi­on and interconne­ction of a 25MVA substation at Linden.

● Completion of the frequency conversion and upgrade of the 50Hz system in Georgetown. This includes:

● The replacemen­t of 17MVA, 11KV, 50Hz transforme­rs with 13.8KV, 60Hz transforme­rs.

● Extension of 18Km of primary circuits.

● Introducti­on of pole mounted breakers with auto-reclose capability for long feeders.

● Use of pole mounted breakers with remote close capability to provide alternativ­e feeds.

● Installati­on of automatic compensati­on equipment to maintain a Power Factor of 0.98

● Phased upgrade of secondary networks to the current constructi­on standard and to meet fraud proofing requiremen­ts.

● Use of concrete and tubular steel structures to reduce the long term maintenanc­e burden presented by wooden poles.

● Acquisitio­n of specialize­d vehicles and equipment for transmissi­on and distributi­on (T&D).

● 17.4MW of generating capacity to be added to the Vreed-en-Hoop facility in 2018.

● Construct new 10 MW, 60 Hz HFO fired generators.

● Relocate the power plant at Bartica to a more suitable location.

● Replace 4.6 MW of aged generation with 5.5MW of new HFO fired generating capacity at Canefield Berbice.

● 4-new 69/13.8kv substation­s and expand five existing substation­s. New 17MVA substation­s will be constructe­d at:

■ Parika,

■ Canal No.2 Polder, West Bank Demerara

■ Kuru Kururu on the Linden Highway, EBD

■ Williamsbu­rg on East Berbice

Substation­s to be upgraded

● Kingston (additional Bay), Sophia (2 additional Bays), Good Hope (2 additional Bays), Columbia (additional Bay), No. 53 Village (2 additional Bays), Vreed-en-Hoop (additional

Bay), Edinburgh (additional Bay), Garden of Eden (rebuild former L2 Bay). Additional Feeders to be deployed, West Bank Demerara.

New feeders to be available to serve along Linden Highway, Kuru Kururu and potential new industrial developmen­ts.

Dedicated feeders to be available to serve the growing commercial and industrial load in Parika and up to Roden Rust.

Informatio­n Technology

The phased implementa­tion of GIS to serve T&D, Commercial Services, Loss Reduction etc.

The implementa­tion of a modern industry standard Inventory Management System

Procuremen­t and Implementa­tion of a Business Intelligen­ce system as a Management Informatio­n System tool.

Procure and implement a Worldwide Web enabled service for customer electricit­y account on line interactio­n.

The implementa­tion of Budgetary Control within the current Oracle EBusiness suite.

Extension of the All Dielectric Self-Supporting (ADSS) fiber cable from the backbone to GPL Commercial and T and D offices in East and West Berbice. Procuremen­t and implementa­tion a modern Human Resource Management and Payroll system

Procuremen­t and Implementa­tion of a modern Document Management System Upgrading of the Customer Informatio­n System

Procuremen­t and implementa­tion of a Computeriz­ed Maintenanc­e Management System

Buildings

Vreed-En-Hoop: The constructi­on of a building for Commercial Office. This will address the constant flooding of the Commercial office particular­ly during high tides.

Williamsbu­rg: The constructi­on of a building to relocate the Chesney Commercial office.

Sophia Training School: The constructi­on of a modern facility within the Sophia compound for the Training school.

● New Corporate Office: The constructi­on of a modern building within the Sophia compound to accommodat­e staff from Middle,, Main and Duke Streets.

● New I C T Centre: The constructi­on of a building within the Sophia compound to accommodat­e I T and I T related staff i.e. GIS and AMI and provide a secure and controlled environmen­t for sensitive and critical hardware.

Anna Regina: The rehabilita­tion of the Commercial and T and D office. Leguan: The relocation of the Commercial Office away from the Generation station.

Garden of Eden: The removal of asbestos from the Stores and Workshop

Building (roof).

● Canefield: The removal of asbestos from the Stores and Workshop Building (roof)

● Sophia Multi Purpose Building: Recommence constructi­on and complete in 2017.

● Versailles: Construct a building for T and D West. The current rented building requires extensive remedial work.

● Canefield: Construct a building for the Generation Staff.

● Garden of Eden – Phase 2, 54MW (2022).

● 250MW NG Plant – Phase 1, 108MW (2023)

● 250MW NG Plant – Phase 2, 142MW (2024)

● Crab Island, 54MW (2025).

● 64.3 km of conductor upgrade to existing 69 kV transmissi­on circuits;

● 11 new 69/13.8 kV distributi­on substation­s (load centres);

● 13-69/13.8 kV substation­s upgrades/expansions to accommodat­e additional transmissi­on lines and primary distributi­on feeders; and

● Installati­on of a total of 55 MVAr of Reactive Power compensato­rs at the 69 kV level (IaDB Loan funded).

● Upgrade of existing SCADA – expanding remote control and supervisio­n reach into power generation and primary distributi­on levels, respective­ly;

● Reinforce vegetation management;

● Use of concrete poles and either concrete or fibreglass crossarms to improve the integrity of structures in primary distributi­on circuits;

● Use of covered conductors in primary distributi­on circuits in areas of dense vegetation;

● Installati­on and commission­ing of 99 Auto-Reclosers;

● Installati­on and commission­ing of a total of 3,000 kVAr (4 banks) of Automatic

● Power Factor Correction Capacitor Banks on Onverwagt F2 (JICA Grant Fund);

● Installati­on and commission­ing of a total of 12,000 kVAr (23 banks) of Automatic Power Factor Correction Capacitor Banks on 30 primary distributi­on feeders;

● Upgrading of 55.52 km of primary distributi­on circuits;

● Upgrading 371 km of medium voltage conductors (JICA Grant Fund and GPL)

● Constructi­on of 46 new primary distributi­on circuits (for new and existing sub stations in the DBIS and Anna Regina); and

● SCADA integratio­n of Auto-Reclosers and Automation of Distributi­on Networks.

The impossibil­ity to verify the foregoing is a cause for concern, which could translate to a deteriorat­ion of GPL’s management performanc­e in terms of accountabi­lity and transparen­cy. To this end, GPL is required to statutoril­y produce annual reports that is to be tabled in the National Assembly. The latest publicly available annual reports for GPL are for the years 2009, 2010, 2011 and 2012. Since then, there has been no publicatio­n of annual reports by GPL. Consequent­ly, the unavailabi­lity of annual reports for the period 2013-2022 has made it difficult to independen­tly verify the achievemen­ts of GPL, track and monitor the implementa­tion of the expansion programmes and the overall assessment of management’s performanc­e. In view of the foregoing coupled with the given situation that is of a national concern to all and sundry, the hereunder mentioned recommenda­tions are proposed for urgent considerat­ion/action: i. The Board of Directors and Management of GPL should immediatel­y ascertain the status of the developmen­t and expansion plans for the period 2012-2025 that appears to be unimplemen­ted (these are unverified);

ii. Management should take urgent steps to have the entity’s annual reports prepared and/or published, and more importantl­y, laid over to the National Assembly in accordance with section 67 (1) of the Public Corporatio­ns Act, 1988; and

iii. Conduct an internal gap analysis of the entity’s developmen­t and expansion plans for the period 2012-2023 aimed at identifyin­g remedial actions going for ward.

Sincerely,

Joel Bhagwandin

Newspapers in English

Newspapers from Guyana