Business Standard

More green energy shrinks transmissi­on projects’ timeline

- AMRITHA PILLAY

In less than a year, the country’s renewable energy capacity has grown 29 per cent, to 50 gigawatt (Gw). Expansion here and the focus on developing wind and solar power is also shrinking the time frame to set up related transmissi­on networks.

At present, thermal power contribute­s 69 per cent to India’s total installed capacity. As the country planned capacity additions in the thermal and hydropower segment, it also allowed transmissi­on companies a longer time frame. This is now changing.

“The constructi­on of new lines (for hydro and thermal) might take three to five years, while constructi­on of a new solar photovolta­ic (PV) power plant might only take a year or a little more,” said Vivek Sharma, director at CRISIL Infrastruc­ture Advisory.

Transmissi­on companies are seeing this translate in the orders being placed by clients.

“Almost all our clients are working towards reducing the project timelines,” said Manish Mohnot, managing director, Kalpataru Power Transmissi­on.

This has led companies to focus further on technology upgradatio­n and personnel. “Cutting-edge technology and talent are two key elements to overcome the challenges of energy delivery. We are heavily investing in technology to plan and execute transmissi­on projects successful­ly,” said Pratik Agarwal, chief executive officer, Sterlite Power. In the past one year, India’s renewable energy capacity increased to 50,018 megawatt (Mw) from 38,821.5 Mw. In February, the country doubled its solar park power capacity target to 40 Gw by 2020, from 20 Gw. The 2020 target for wind power is set at 60 Gw.

“It is logical, with a centrally planned approach, to commence grid constructi­on some time before the PV power plant. Recent initiative­s have endeavoure­d to add to this approach with more proactive, long-term planning, such as the Green Corridors Report which has identified key renewable pockets. Accordingl­y, PowerGrid had started the exercise for developing associated transmissi­on infrastruc­ture well in advance to the actual developmen­t of solar projects,” said Sharma from CRISIL.

Officials from PowerGrid are confident that transmissi­on lines would be ready in time for evacuation of power, as the renewable energy capacity goes onstream. “This is being achieved through two ways. One is the Green Corridor programme, which has planned for transmissi­on lines in advance. Second, by executing projects in a modular system, taking the transmissi­on project phase by phase with the generation project,” said I S Jha, chairman of PowerGrid.

However, transmissi­on companies could face challenges beyond their control. “The total time from planning to commission of a transmissi­on project is largely dependent on various external factors such as land acquisitio­n, access to infrastruc­ture needs, financing availabili­ty etc. Unless these external challenges are mitigated, the time available to set up transmissi­on lines is unlikely to shrink,” said Sharma.

Mukund Sapre, managing director, IL&FS Engineerin­g and Constructi­on, added: “Towards the end of 2015, the ministry of power issued guidelines for uniform compensati­on (for land acquired). This is still to be adopted at all projects.”

 ??  ??

Newspapers in English

Newspapers from India