Bajaj Energy set to join list of power NPAs

- DEV CHATTERJEE

After Tata Power, Adani Power offered to sell their power plants for free to the Gujarat state electricit­y board, Bajaj Energy’s project is set to join the list of non-performing asset for the lenders. Bankers said the company has stopped operations after the new Uttar Pradesh government cancelled the power purchase agreement citing high power cost thus effectivel­y shutting down the 450 mw plant.

“The cancellati­on of the power project in UP could lead to ~2,000 crore NPA (non-performing asset) for banks which had lent funds to the company. With the closure of the plant the project would lose close to ~600 crore of revenue head straight to bankruptcy,” said a banker. Bajaj Energy is an associate company of Bajaj Hindusthan Sugar

While cancelling the project, the new UP government led by Yogi Adityanath, the UP electricit­y board said as the board was buying electricit­y at the rate of ~7.22 a unit as compared to the average cost of ~4.11 a unit supplied by other units, it was unviable. Bajaj Energy has moved the court against the UP government’s move even as its 2,000 employees are now staring at the prospects of job loss. The project was supplying power to the state government for the last seven years at its full capacity.

The state has electricit­y deficit of 3500 mw during the peak hours even as spot price of electricit­y has shot up to ~9.92 a unit. If the state fails to buy electricit­y from the spot exchanges during peak time, it would lead to power shortfall.

The cancellati­on of PPAs comes at a time when the Indian Government launched the Sobhagya electrific­ation' scheme at a cost of ~16,000 crore to provide electricit­y connection­s to 40 million unconnecte­d households by December 2018 just prior to the General elections.

With another project facing bankruptcy the lenders are worried as Indian private power companies are facing a crisis of sorts with over 20,000 mw worth of projects up for sale. This includes L&T’s power projects apart from Tata, Adani and Essar’s power projects. Thanks to a change in coal export policy by Indonesia, all these projects based on imported coal have become sick. Take for example, Tata Power’s Mundra project constitute­s almost ~18,000 crore of its capital employed with negative returns till date. Similarly, Adani Power’s net worth is ~3,000 crore and has almost ~49,230 crore of debt on its books.

The Essar group had also invested ~2,600 crore in the equity of Salaiya plant and has ~5,000 crore of debt, bankers said.