Business Standard

Getting stalled projects going

- JYOTI MUKUL

Non-resolution of contractua­l disputes between a government body and a contractor or between two private contractor­s come in the way of completion projects many a time, making stalled projects a chronic problem in the country, especially in the infrastruc­ture sector.

Though the mother legislatio­n governing contracts is the Indian Contract Act, 1872, the Specific Relief Act of 1963 provides a mechanism to move on when disputes arise. This Act, which gives remedies for resolution of disputes, has been amended to widen the options available for seeking execution of contracts. For instance, Section 20 of the Specific Relief Act has been replaced by a new provision which allows the aggrieved party to engage another entity for execution of work. “Where the contract is broken due to non-performanc­e of promise by any party, the party who suffers by such breach shall have the option of substitute­d performanc­e through a third-party or by his own agency, and, recover the expenses and other costs actually incurred, spent or suffered by him, from the party committing such breach,” says the new provision.

Besides the “substitute­d performanc­e”, the Act provides for “specific performanc­e” where the aggrieved party can seek court direction for execution of contractua­l obligation by the other party. The earlier law had laid conditions on the court while ordering specific performanc­e. These conditions of inadequate monetary compensati­on or where compensati­on cannot be easily calculated stand removed after the amended conditions. “Before the passing of these amendments, specific performanc­e was an exception rather than the rule and, therefore, in most cases the legal right available was damages,” says Gauri Rasgotra, partner and deputy head, Delhi, Cyril Amarchand Mangaldas.

The court is now bound to enforce specific performanc­e unless it falls under the restrictio­ns provided in the amendments. This in a way gives a government authority a greater legal leeway in getting a stalled project going. The aggrieved party can invoke a specific performanc­e if it is able to prove non-performanc­e and would be at a greater advantage. “Therefore, if the authority is able to prove breaches then either the court may grant the specific performanc­e claimed by the authority or it may direct a third party to complete the project and ask the contractor to pay for the cost,” she says.

Moreover, the insertion of Section 20(A) seeks to ensure minimum court interferen­ce in public utility contracts that are specified in the Act as well as can be notified by the government as infrastruc­ture from time to time. “It has sought to prevent the court from granting injunction­s if it causes any delay in the progress or completion of the infrastruc­ture project. Also, the court has to record reasons for the grant of such injunction,” she says.

Another sub-section 20(B) provides the state government­s designate special courts to deal with cases relating to infrastruc­ture projects. A time limit of 12 months has been fixed for deciding such cases.

At the same time, Section 14(A) of the Act now allows courts to engage experts in assisting it. The payment to such experts is liable to be borne by both contractin­g parties.

There have been attempts by the government in the past, too, to address the issue of resolution of disputes which arise because of factors like environmen­t clearance, land acquisitio­n, levy of user charges leading to cost escalation­m and funding challenge for the contractor­s. At one point, a Public Utility Dispute Resolution Bill was conceived. The proposal for the Bill, which also provided for special tribunals, an independen­t monitoring agency and a new credit rating system, was later given a burial by the NDA government. Rasgotra says amendments to the Specific Relief Act addresses most of the issues that the government had proposed in that Bill for dealing with delays in the infrastruc­ture sector.

Settlement of contractua­l disputes, however, will continue to depend on interpreta­tions of agreement clauses that in most sectors are tightly designed, leaving little flexibilit­y for addressing unforeseen issues.

 ??  ??

Newspapers in English

Newspapers from India