Business Standard

RESOLVING DISPUTES AT IL&FS GROUP

The success of public-private partnershi­ps rests on both prevention and resolution of dispute, say experts

- JYOTI MUKUL

The resolution of disputes between the Infrastruc­ture Leasing & Financial Services Limited (IL&FS) group and government entities is seen as a way forward for the liquidity-strapped infrastruc­ture financier and builder. Such a move is intended to bring in cash flow, thereby easing the task for the government-appointed board that took control of the group on October 1.

IL&FS and the National Highways Authority of India (NHAI) are likely to opt for an out-of-court settlement in a couple of cases entangled in the arbitratio­n process. IL&FS has arbitratio­n claims worth around ~70 billion with the NHAI. Though discussion­s are currently on in the two cases where IL&FS went to court over lower arbitratio­n compensati­on, clearly a dispute resolution is problemati­c despite the government putting in place a scheme in December 2016, under which the NHAI is required to release 75 per cent of the amount awarded by the arbitrator­s.

Contracts signed between two parties usually have a provision for arbitratio­n so that disputes can be settled outside of courts in a faster manner. An arbitratio­n agreement is a mutual resolution between the parties. However, Ramesh K Vaidyanath­an, managing partner, Advaya Legal, argues arbitrator­s being paid for the number of sittings creates a vested interest in prolonging proceeding­s, except for those who are in demand.

But, Ajay Bhargava, partner, Khaitan & Co, does not agree. He says arbitrator­s do not have any personal interest in the matter. “Delay is not occasioned because of them. However, in the case of threemembe­r tribunals, getting available dates from all the members remains a challenge," says Bhargava.

Since the award of the legal cost is nominal and not actual, there isn’t any disincenti­ve for the parties not to challenge. Vaidyanath­an says the slow pace of the judicial process encourages parties to delay matters and offers no incentive for settlement. He also points out to lack of oversight in the case of ad-hoc arbitratio­ns compared to institutio­nal arbitratio­ns. Disputes in infrastruc­ture projects can be complex and require high-level expertise and extensive documentat­ion. While there is also lack of specialist arbitrator­s, technology adaptation­s for some of the procedural aspects are low.

Naresh Thacker, partner, Economic Law Practice, says disputes in infrastruc­ture projects usually take longer to be resolved through any dispute resolution mechanism. Claims can range from delays in handing over land to concession­aires (contractor­s), time overrun in constructi­on, rejection of price escalation and change in scope of work claims, premature terminatio­n, and offloading of work to a third party, among others.

According to Thacker, the problem is systemic; the traditiona­l mindset is to approach arbitratio­n is akin to an elaborate judicial procedure adopted in the civil courts. “This behaviour is reflected not just in the dilatory approach of the contractor/concession­aire and the NHAI, but also that of lawyers and arbitrator­s,” says Thacker.

The most common approach is of taking time extensions without a just cause, protractio­n of proceeding­s due to the excessive workload on the lawyers or arbitrator­s and resorting to court interventi­on.

Bhargava says there is no bar for the parties to settle potential disputes; even after the arbitratio­n commences, the parties can discuss matters and resolve. “When it comes to private parties, we have seen a rise in settlement discussion­s pre and during the arbitratio­n,” he says. Even during arbitral proceeding­s, a settlement is legally permissibl­e under Section 30 of the Act.

Yet, almost all cases go in for appeals in courts, especially the cases related to government companies.

Disputes in an ongoing contract lead to financial problems. “Payments get withheld and bank guarantees are invoked. This leads to cash flow issues, impacting day-to-day operations and non-payment to thirdparty vendors,” says Bhargava. He, however, says there is a clause for the continuati­on of the project work in most projects, even if some dispute under the contract is referred to arbitratio­n unless the issue arises on account of terminatio­n or abandonmen­t of the contract.

The government amended the arbitratio­n law and introduced a time-bound resolution mechanism in 12 and 18 months. Thacker says prior to the 2015 amendments and the proposed 2018 amendments to the Arbitratio­n and Conciliati­on Act, 1996, the arbitratio­ns would run for several years at a stretch. He suggests management-level negotiatio­ns or conciliati­on through a committee of independen­t experts.

Thacker says courts need to take a proactive stance to support adjudicato­ry mechanism through arbitratio­n, especially where PSUs are concerned. “A sympatheti­c attitude towards PSUs make them commercial­ly non-responsive and a drain on the system.”

To a large extent, the success of public-private partnershi­ps rests on both the prevention and resolution of the dispute. If IL&FS cases indeed get resolved outside of courts, they could set a precedent and put the onus on both the government organisati­ons like the NHAI and private entities to carry the contract in its true spirit.

 ??  ??
 ?? ILLUSTRATI­ON BY AJAY MOHANTY ??
ILLUSTRATI­ON BY AJAY MOHANTY

Newspapers in English

Newspapers from India