Business Standard

Power play

With the Supreme Court asking the C ER C to look into power purchase agreements signed by various states with private firms, flood gates for tariff revisions may open up

- JYOTI MUKUL

With the Supreme Court asking the CERC to look into PPAs signed by various states with private firms, floodgates for tariff revisions may open up. JYOTI MUKUL writes

ASupreme Court order last month allowing the Gujarat government to approach the Central Electricit­y Regulatory Commission (CERC) for amendments to power purchase agreements (PPAs) perhaps for the first time will see a review of government contracts, primarily driven by concerns of the private sector. So far, government­s, on several instances, have not honoured contract conditions and even forced private parties like Reliance Industries and Vedanta Cairn to withdraw in “public interest” from arbitratio­n proceeding­s.

Though the issue in itself is not very complicate­d, there is a legal ping-pong which has been played out over the last six years and is likely to continue for some time. As it stands, Adani, Tata and Essar are looking for relief in the form of higher tariff due to the rise in the cost of imported coal, which makes power generation at the agreed price unfeasible. The contentiou­s issue here is that tariff for power plants were fixed after the projects were won through competitiv­e bidding and any change in tariff means a change in the winning bid as well as the PPA.

It is now expected that the CERC will allow amendments to the PPAs by December-end after hearing all stakeholde­rs, resulting in relief to the three companies. “An increase in tariff payable to generating company would directly result in an increase in retail supply tariff. Since, tariff orders are issued pursuant to public hearings, a challenge to tariff revision is almost certain,” says Sujit Ghosh, partner, Advaita Legal.

Also, the Supreme Court order raises an issue that whether contracts should be reopened and how much flexibilit­y can be built into them in order to prevent them from being abandoned. In cases, where these contracts form the basis for running of a public service or facility, then such abandonmen­t adversely impacts the public wellbeing. “Keeping in view the business dynamics and the regulated nature of these sectors, it probably makes a business case that the contracts are kept flexible. However, what needs to be laid down is the nature and character of the flexibilit­y — clearly demarcatin­g business risks and regulatory risks,” says Ghosh.

Though the PPAs provide for a revision of tariff in cases of change in law and have a force majeure clause, the Supreme Court in its 2017 order disallowed the power generators the benefit saying that the change in an Indonesian law could not be countedas an unforeseea­ble circumstan­ce that prevented them from fulfilling the contract. In 2010, the Indonesian energy regulation­s required the export price of coal to be benchmarke­d to domestic rate, leading to an increase in the price.

“This clause (12.4 of PPA) makes it clear that changes in the cost of fuel, or the agreement becoming onerous to perform, are not treated as force majeure events under the PPA itself,” the apex court held.

Ghosh says since most projects are financed on project finance basis, continued operation of the project is the only way to ensure that the invested public money is returned. “Therefore, it is imperative that the projects remain viable.”

Though allowing flexibilit­y runs contrary to making contracts watertight, Ghosh says a contract cannot be departed from merely because one party is facing hardship, which is precisely what the Supreme Court said in the original order in the matter. “However, where changes, which could not have been anticipate­d at the time of entering into the contract, occur and impact the fundamenta­l premise on which the contracts were based, the equities would have to be balanced again. Across the globe, there is a discussion over allowing mid-term review of long-term contract to cater for unforeseen events.”

In cases where the counterpar­ty happens to be a government entity, as defined under Article12 of the Constituti­on, there are additional constituti­onal tests that such an entity must meet for its actions to pass the judicial muster, says Ghosh.

Changes in a contract cannot be the norm since the process itself may be vitiated or be driven by narrow interests. In fact, Ghosh says sanctity of the contract is a basic feature of the rule of law and courts have insisted on it in several cases. “Any deviation from a contract would alter the bargain between the parties, especially if the contract was awarded pursuant to competitiv­e bidding. Hence the legal implicatio­ns of reopening any contract, including PPAs, go to the very root of the contract, especially in cases where such reopening has commercial implicatio­ns.”

On a macro regulatory perspectiv­e, the rules of the game have to be uniform in order to create a level playing field, says Ghosh. He cites Section 62 of the Electricit­y Act under which tariff determinat­ion is practicall­y available to only PSUs, which can claim at least technicall­y a tariff revision based on statutory right. Private sector players, which are largely governed by Section 63, are left with only a contractua­l right. “It, therefore, bears to reason that a slightly fungible contractua­l framework that insulates the business from unforeseen events may be considered-subject to limitation­s.”

How the CERC picks up from here on and interprets the clauses in the PPAs signed by five states with the three firms will set a template, as floodgates for tariff revisions in other cases are bound to open up.

 ??  ??
 ?? PHOTO IMAGING: AJAY MOHANTY ??
PHOTO IMAGING: AJAY MOHANTY

Newspapers in English

Newspapers from India