Coronaviru­s delays indigenous aircraft carrier by 6 months

- AJAI SHUKLA

The long wait for India’s first indigenous aircraft carrier, INS Vikrant, is set to be even longer. Senior naval sources say the Covid-19 pandemic has set back the start of trials by at least six months — perhaps more if the lockdown and travel restrictio­ns continue.

The first phase of the warship’s trials — termed basin trials — was initially scheduled to begin on March 12 at Cochin Shipyard (CSL), where INS Vikrant has been constructe­d. However, constructi­on delays caused that to be moved back to April. Then, with the Covid-19 pandemic locking down facilities and travel, the Navy says trials are unlikely to begin before September/october.

An example of the delay is the difficulty faced by marine engine specialist­s from Hindustan Aeronautic­s (HAL) in travelling to Kochi for the trials. These HAL representa­tives are essential for the trials because the General Electric (GE) gas turbines that power INS Vikrant have been built and supplied by HAL’S collaborat­ive venture with GE in Bengaluru. However, the HAL representa­tives are reluctant to travel to Kochi, where they would face 14 days of quarantine on arrival in Kerala and another 14 days quarantine on return to Bengaluru.

Similarly, there are about 40-50 vendor representa­tives, including 10 from abroad, who cannot come to Kochi for basin trials without facing the deterring prospect of mandatory quarantine.

“The Navy has even offered to organise the vendors’ quarantine and to pay the expenses that are incurred. Given how much this delay in trials is escalating the cost of INS Vikrant, we would pay less for the quarantine and related expenditur­e. But the Kerala government is not agreeing to this,” says a Navy Admiral.

“We were optimistic about finding a solution because Kochi and Ernakulam are green zones. But when we request the Kerala government, they say: ‘Yes, we are in a green zone, but we don’t want to convert it back to a red zone’,” he said.

In his Navy Day press meeting last December, the Navy chief, Admiral Karambir Singh, had said the Navy would have a fully operationa­l INS Vikrant before the end of 2022. The Covid-19 pandemic has already pushed that back to 2023 and further delays are possible.

Karambir Singh stated it was operationa­lly essential for the Navy to operate three aircraft carriers. It now appears that, for about three more years, it will have to make do with its lone carrier — the Russia-built INS Vikramadit­ya.