Business Standard

DFCS to be delayed again, deadline extended by 2 yrs

- DHRUVAKSH SAHA New Delhi, 30 May

The Eastern and Western Dedicated Freight Corridors (DFCS) would be delayed again for the fifth time in this decade. The completion deadline for the projects is now being extended by two years over pandemicin­duced challenges and land acquisitio­n delays.

The Dedicated Freight Corridor Corporatio­n of India (DFCC) has sent its revised completion estimates to the ministry of railways. It sought time till 2023 to complete the Eastern DFC and 2024 for the Western DFC, Business Standard has learnt.

DFCC did not respond to a Business Standard questionna­ire till print time.

The DFCS were earlier slated to be completed by next month. The latest extension will be the fifth revision in the completion timeline of the two DFCS. The project was initially expected to be completed in 2017. Since then, it has been extended to March 2018, March 2020, December 2021, and June 2022.

Marred by Covid-induced delays in land acquisitio­n, contractua­l fulfilment, and cash flow concerns, DFCC — in its project status report in December — stated, “Progress of works is badly affected in the second wave and targets are likely to be delayed.”

The revised timelines, however, have upset the ministry of railways, which, in its internal communicat­ions, expressed dissatisfa­ction. It sought advancing the targets, said officials in the know.

“There were internal concerns over the revised targets. We thought DFCC could have implemente­d certain things faster, but after consultati­ons over its issues as the executing agency, there is consensus to go forward with the proposed targets,” said a senior official.

The new target, although farther than anticipate­d, is a more realistic one, a railways official said.

There have also been lags in capital expenditur­e (capex) by DFCC. As of March, the government-owned firm has spent a little more than twothirds of its ~15,000-crore capex target for the financial year 2021-22, the company’s internal reports show.

DFCC has so far commission­ed 1,010 kilometres (km) of the proposed 2,843 km, pertaining to stretches undertaken by the government for both the corridors. A 538-km stretch between Sonnagar in Bihar and Dankuni in West Bengal is being developed under PPP mode.

Since its inception in 2007, the government’s marquee logistics project has undergone several delays due to concerns over land acquisitio­n and contract-awarding lags.

The agency had cited issues with procuremen­t of imported goods and rising prices of steel as challenges to timely execution.

There have been cost overruns due to repeated delays. The initial cost estimate of ~21,040 crore was revised to ~81,459 crore in 2015, and is now likely to be revised to over ~1.24 trillion.

Business Standard had previously reported that the ministry is expected to move the Union Cabinet to sanction the revised cost soon.

 ?? ??

Newspapers in English

Newspapers from India