CM for Metro link to airport, stations, bus stops

Officials told to ensure that the train is of use even for people coming from outside the state

- DC CORRESPOND­ENT

Chief Minister K. Chandrasek­har Rao on Tuesday asked the Metro Rail authoritie­s to ensure that the Metro serviced not only city dwellers, but also those arriving from other parts of the state, country and abroad by rail, bus and air.

Mr Rao instructed Metro Rail officials to provide train services from the Hyderabad internatio­nal airport at Shamshabad to other parts of the city for the benefit of air travellers, at Secunderab­ad and Nampally railway stations besides Jubilee and Imbliban bus depots.

“The earlier government forgot Shamshabad airport when it designed the Metro Rail project. Links have to be provided to the airport from Falaknuma and Rayadurg. A Metro link should also be considered from LB Nagar to Chandrayan­gutta,” he remarked.

“Metro Rail connection­s should be in such a way that they are useful not only to locals, but also those arriving by air, train and bus from other parts of the country. The Metro links should benefit all sections of commuters,” he told Metro Rail officials.

The CM met Metro Rail officials to review the ongoing works. City ministers Nayani Narasimha Reddy, T. Padma Rao, Talasani Srinivas Yadav, P. Mahender Reddy, chief secretary Rajiv Sharma, Metro Rail chairman N.V.S. Reddy, L&T CEO V.B. Gadgil, GHMC commission­er Somesh Kumar, principal secretary to the CM Narsing Rao, city police commission­er Mahender Reddy and other senior officials were present.

Expressing satisfacti­on at the pace of the Metro Rail works, the Chief Minister asked officials to keep up the tempo and complete the works as per schedule. The Metro Rail project, which began in 2012, is slated to be complete by April 2017.

Out of the total 72 km network, so far a 19 km stretch has been completed. The Nagole-Mettuguda 8 km line and Miyapur-SR Nagar 11 km line is complete and trail runs have been successful, officials informed the CM.

Mr Rao, meanwhile, agreed to provide power at subsidised rates for the Metro Rail, adding that the government would review the pace of work every week. He also cleared several files pertaining to the project.

The Telangana government has earmarked `2000 crore for the project so far. “The government will take up land acquisitio­n, rehabilita­tion and widening of roads. We have also got permission from the defence minister for oneand-half km network passing through defence lands that had been pending since three years,” Mr Rao informed the officials. He also asked Metro Rail officials to adopt the Delhi Metro project security pattern in Hyderabad.

● The earlier government forgot Shamshabad airport when they designed the Metro Rail project. Links have to be provided to airport from Falaknuma and Rayadurg, the Chief Minister said.

● The Metro Rail project, which began in 2012, is slated to be completed by April 2017.