City bridges slow down Metro Rail

- DC CORRESPOND­ENT

L&T officials confirmed on Tuesday that work on three major rail overbridge­s in Secunderab­ad will not be complete before December 2016. This puts a question mark on the opening of the Nagole-Secunderab­ad Metro Rail sector from June 2016. The Metro Rail is ready on the NagoleMett­uguda stretch.

Senior L&T officials said that they had not received communicat­ion from the government regarding starting Metro services.

On February 19, minister K.T. Rama Rao had stated that the first phase of Metro Rail would start by June 2016. Before this, in December 2015, he had stated that it would start in the first quarter of 2016.

Besides, the process to get the safety certificat­e from the Union railway ministry has not started.

A senior officer said, “The state government has to take an active role to secure the safety certificat­e. But there is not much push from their end. These announceme­nts have been made to the public but there is no communicat­ion to the company from the government.”

Despite the three ROBs being given maximum attention due to the engineerin­g challenges and technical implicatio­ns, L&T officials said they would not be completed before December.

Works on the ROB at Oliphanta Bridge will five months, Bhoiguda eight months and Chikalguda four months. An officer said the work could be carried out only for three hours a day to avoid disruption of train traffic.