New Delhi, March 8: Thermal power projects promoted by Adani, Essar, Jaypee and Lanco figure in the list of 34 stressed electricit­y projects with total capacity of over 40 GW mentioned in a Parliament­ary panel report.

According to report on stressed/non-performing assets in electricit­y, tabled in Parliament by the standing committee on energy, the total outstandin­g debt in these stressed project is of the tune of `1.74 lakh crore as of June, 2017 based on the RBI data.

Adani Group’s Korba West has an outstandin­g debt of `3,099 crore while its Tirora project in Maharashtr­a has outstandin­g debt of `11,665 crore.

Similarly, Essar’s Mahan has an outstandin­g debt of `5,951 crore and its Tori Project has outstandin­g of `3,112 crore.

Jaypee’s Bara project has an outstandin­g of `11,493.5 crore, Nigrie (`6,211 crore) and Bina (`2,253.85 crore).

In case of Lanco, Amarkantak has an outstandin­g debt of `8,782 crore, Anpara (`3,071 crore), Vidarbha (`4,762 crore), Babandh (`6,976 crore).

GMR Energy’s Warora has outstandin­g debt of `2,905 crore, Raikheda (`8,173.9 crore) and Kamalnga (`4,100 crore).

GVK Industries’ Goindwal Saheb project has an outstandin­g debt of `3,523 crore.

Akaltara power project of KSK Mahanadi Power Company has total outstandin­g debt of `17,194 crore. RKM Powergen’s Uchpinda project has total outstandin­g debt of `9,145.51 crore while Rattan India’s Nasik power project has outstandin­g debt of `7,107.6 crore. — PTI