Down to Earth

Dirty picture

Fate of 218 coal blocks in limbo; Centre seeks to cancel mines yet to be developed

-

ON SEPTEMBER 9, the Supreme Court reserved its judgement on the fate of the 218 coal blocks it had declared illegal a fortnight ago. On August 25, the court pulled up the Centre and declared all allocation­s between 1993 and 2010 illegal. The “common good and public interest have suffered heavily” because of arbitrary allocation of these coal blocks to private and government companies, said Chief Justice R M Lodha.The apex court was hearing a slew of public interest petitions that contested coal block allocation­s based on the 2012 report of the Comptrolle­r and Auditor General (cag) of India, which suggests that illegal allocation­s of coal blocks to mining companies have caused losses to the tune of ` 1.86 lakh crore to the exchequer.The court had also held the government responsibl­e for granting largesse to private companies.As many as 106,or about 50 per cent of the coal blocks, have been leased out to private companies. The ruling on August 25 had landed the ruling Bharatiya Janata Party (bjp) in a sticky situation. Just a few months ago the bjp had campaigned against the previous United Progressiv­e Alliance (upa) government wielding the cag report.But 39 of the 218 coal block allocation­s declared illegal, were allocated during the regime of the bjp-led National Democratic Alliance (nda) between 1998 and 2004 (see ‘Political anatomy of a mega scam’ on p28).

On September 9, Union Coal Secretary Akhouri Sanjay Sahay told the court that the government is ready to begin on a “clean slate” with speedy and “transparen­t” auctioning of the coal blocks because the priority is to deal with the “looming power crisis” in the country.The Ministry of Coal stated that it did not want to form any committee to look into allocation­s and favoured cancellati­on of all the coal blocks, except 46.

Attorney General of India Mukul Rohatgi had sought exemption for these 46 coal blocks—19 were allocated during the nda regime—from possible revocation of licences on September 1, saying 40 are under production and mining is about to begin in the rest. These coal blocks are with big-ticket private power and steel companies and are estimated to produce 53 million tonnes of coal this year. This is 10 per cent of the total projected output from all the 105 coal blocks with private companies and is sufficient to generate 26,000 MW of electricit­y and produce 12 million tonnes of steel.

Representi­ng Indian Power Producers’Associatio­n, senior lawyer Harish Salve told the court that individual cases must be considered by a three-member panel comprising a retired Supreme Court judge and an auditor. Rohtagi opposed the idea, saying it will delay coal block allocation. If the Supreme Court cancels all the coal blocks, he said, the government mining company Coal India Ltd should be allowed to take over active mines, or companies be allowed to continue production until the blocks are re-auctioned to ensure supply to power plants.

Prashant Bhushan, a Supreme Court lawyer representi­ng non-profit Common Cause, a petitioner in the coal allocation scam case, says, “For all the noise made by the government, production of coal from the post-1993 allocation­s is only 7 per cent of the total coal demand in the economy, which is about 739 million tonnes.”

While declaring the coal blocks illegal, the court based its judgement on the presidenti­al reference related to the allocation scam of another natural resource— 2G spectrum. In 2012, it cancelled all 122 spectrum licences on the ground of arbitrarin­ess, saying alienation or allocation of natural resources should rely on principles of equality as enshrined under Article 14 of the

Constituti­on, else such executive decisions are arbitrary or capricious (see ‘Behind the blocks’).

Sanctioned, illegally

More than 65 per cent of the country’s total electricit­y requiremen­t is met from coal, a non-renewable reserve. Industries like iron, steel and cement also depend on coal as fuel.To ensure equitable distributi­on of this vital yet limited resource, the government in the 1970s nationalis­ed coal reserves, except a few blocks being mined by iron and steel companies. It also set up the Coal India Ltd (cil) as the sole authority to develop the reserves and sell the mineral to companies, both public and private. In the 1990s, following economic liberalisa­tion, there was a surge in the demand for coal.So in 1993,the Centre amended the Coal Mines Nationalis­ation Act, 1976, and allowed private players to develop coal blocks. This is when irregulari­ties started creeping in.

The court has identified two major irregulari­ties in the way coal blocks were allocated.

In 1993, the government allowed the Screening Committee, an inter-ministeria­l body, to award coal blocks to private players.But in the absence of clearly defined evaluation criteria, the committee followed an “ad hoc and casual” policy that was neither consistent nor transparen­t, the court said. The exercise of allocation denied a level playing field, healthy competitio­n and equitable treatment. This whimsical procedure of allocation had resulted in “unfair distributi­on of national wealth” to a few private companies, read the judgement (see ‘How Screening Committee allocated coal blocks’).

The apex court has also questioned the authority of the Centre in allocating coal blocks.

The government­s of Odisha and Maharashtr­a ,in their submission­s to the court, have argued that they have “virtually non-existent” role as the Screening Committee allocates coal blocks without taking their recommenda­tions into considerat­ion. For instance, the committee awarded Kosar Dongergaon coal block in Maharashtr­a to Chaman Metallics Ltd even though the state government had not recommende­d it. This contravene­s provisions of both the Mines and Minerals Developmen­t and Regulation (mmdr) Act, 1957,and the Coal Mines Nationalis­ation Act, which say that the Centre has the power only to regulate and develop mines and that the leasing process largely stays with the state government. “The allocation letter by the Central government leaves practicall­y nothing for the state government to decide, except to carry out the formality of processing the applicatio­n and for execution of the lease deed with the beneficiar­y selected by the Centre,” said the court.

The other irregulari­ty crept in 2001 when the coal ministry introduced New State Coal Mining Policy. The policy allows state government corporatio­ns to mine anywhere in the country at a commercial scale to meet the demand of small industries that cannot be catered to by cil. The apex court has said the policy has “no legal sanction”, however laudable the objective may be, because it violates the Coal Mines Nationalis­ation Act that prohibits commercial mining by state corporatio­ns and restricts transporta­tion of coal by the railways, ensuring that the mined coal is used by industries in isolated pockets.

Sitting idle on black gold

Companies once allocated a coal block are supposed to develop it within the stipulated time period of 42 weeks (for open-caste mining) and 54 weeks for undergroun­d mining. But so far, only 46 have been able to develop the mines and another 80 coal blocks have been deallocate­d as they could not start production within the stipulated time frame. Some of these blocks were allocated more than 14 years ago. Former power secretary EAS Sharma alleges that there was an orchestrat­ed move to benefit some influentia­l pri--

vate companies so that they can exploit land and coal resources with the help of public money raised by public sector banks. Almost all public sector banks have given big loans to power companies that have bagged coal blocks (see ‘Banks under burden’ on p24). This is the reason stocks of several banks tanked shortly after the court termed the coal blocks illegal. Sharma, in a letter to the Reserve Bank of India early this year, says, “There is an impending financial crisis in psu banks which granted loans to developers of dubious power projects and questionab­le captive coal blocks.”

According to an estimate by Karvy Stock Broking, wealth management firm in Gurgaon, loans make up a major chunk of the amount power developers have invested in exploring, mining and setting up projects. Since 2006, Indian banks have lent ` 2.6 lakh crore to iron and steel companies and ` 5 lakh crore to power companies. While not all of these loans will be at risk, a back-of-the-envelope calculatio­n shows that exposure to the companies with captive coal blocks could be between ` 2.5 lakh crore and ` 3.5 lakh crore. “If these projects fail to take off, banks will have to either write off or classify them as non-performing assets. Even if the court asks the government to reallocate these coal blocks, it would mean substantia­l delays and would result in slippages and restructur­ing of loans,” says an analyst with Karvy Stock Broking.

Some projects are already in a fix. A consortium of banks comprising Axis Bank, Punjab National Bank and uco Bank are trying to find buyers for debt-ridden Corporate Power Ltd (cpl) of Nagpur-based Abhijeet Group, which was allotted five coal blocks but is yet to start production from any of the blocks.In August, the chairperso­n and managing director of Syndicate Bank,

Sudhir Kumar Jain, was arrested for accepting bribe from Chhattisga­rh-based Bhushan Steel, implicated in coal allocation scam.The company wanted a loan of ` 100 crore from the bank.The cbi, which has issued arrest warrant against Bhshan Steel’s managing director Neeraj Singhal for bribing Jain, says the company has taken loans of ` 40,000 crore from 51 banks.The coal ministry has also issued a showcause notice to Bhushan Steel for not being able to develop four coal blocks allotted to it between 2003 and 2008.Bhushan is yet to file a response.

Companies often cite green clearances as a reason they have not been able to develop mines. An analysis by Down To Earth shows some companies are yet to apply for clearances, while in several other cases, coal blocks are located in areas with dense forest cover where community rights are yet to be settled. Consider this.In 2006,power company Essar and aluminium producer Hindalco were allowed to develop Mahan coal block in Singrauli.The communitie­s challenged the clearances granted to the companies, saying that their rights over Mahan have not been recognised.

Hopes of cheap power dashed

Though many coal blocks could not be developed within the stipulated time period, the coal ministry kept allocating reserves, mostly to power firms. Between 1993 and 2010, as many as 83 coal blocks were leased out to power companies. This excludes coal blocks allocated for ultra mega power projects (umpps) that have been exempted from the case by the Supreme Court.In 2006,the government dereserved another 81 coal blocks with cil and awarded them to private firms, including power and other infrastruc­ture companies. This was to bridge the gap between demand and domestic supply of coal and to stabilise electricit­y price, says the coal ministry. But its objective is nowhere closer to being achieved.

In 1999, the nda government had decided to allow the sale of coal from captive mines saying that surplus coal was hazardous to keep in plant. It intimated its decision through a letter to assocham, Sponge Iron Associatio­n, ficci and cii. This gave elbow room to private players, who instead of producing electricit­y for the grid, started selling coal in the open market.

“Between 2009 and 2012, the coal ministry allowed Tata Steel, Jindal Steel & Power Ltd, Integrated Coal Mining Ltd, Sarda Energy Minerals Ltd and Electroste­el Castings Ltd to sell coal in the market,” says Sudiep Srivastava, a lawyer in Chhattisga­rh and petitioner in the coal scam case.

Some independen­t power producers also procured the surplus coal from captive mines at a cheaper rate and generated electricit­y to sell it at a whopping ` 10 to ` 12 per unit in the short-term open markets such as power exchanges while generation cost did not surpass ` 2.50 per unit. Power manufactur­ers are supposed to enter into long-term agreements with power distributi­on companies (discoms) which brings stability in electricit­y prices. Captive power producers also sold electricit­y in these exchanges and charged arbitrary prices, which effectivel­y increased electricit­y bills for consumers.

Interestin­gly, the Centre rolled out two policies to facilitate sale of electricit­y leading to creation of short-term power market.The Electricit­y Act of 2003, passed by nda, allowed private players to trade electricit­y. Then in 2005,the upa formulated the National Electricit­y Policy (nep) which called for creation of power exchanges for power trading. “It was only in 2012, 16 years after coal blocks began to be allocated to private firms, that the companies were asked to participat­e in power procuremen­t bids called by discoms or their authorised state agencies and enter into longterm power purchase agreement,” says Kalyan Banerjee, Trinamool Congress MP, who led Parliament­ary Standing Committee of Coal. Since the entire process of allocation was unauthoris­ed, no one should enjoy the benefit of allocation, said Banerjee, recommendi­ng that all the coal blocks allocated to private power companies should be scrapped.

 ??  ?? The 46 coal blocks that the Centre wants to be spared will produce 53 million tonnes of
coal this year
The 46 coal blocks that the Centre wants to be spared will produce 53 million tonnes of coal this year
 ??  ?? Communitie­s of Singrauli, Madhya Pradesh, protest against environmen­tal clearances granted to Mahan coal block. They say their rights over the Mahan forest are yet to be settled
Communitie­s of Singrauli, Madhya Pradesh, protest against environmen­tal clearances granted to Mahan coal block. They say their rights over the Mahan forest are yet to be settled

Newspapers in English

Newspapers from India