Pay Rs 58 L for damages in U’khand: NGT to NTPC

-

The National Green Tribunal has junked a plea by NTPC seeking review of an order passed by Uttarakhan­d Pollution Control Board (PCB) imposing a penalty of Rs 57.96 lakh for damaging the environmen­t.

The state-owned power major was found to have violated muck disposal site maintenanc­e norms, resulting in damage to the environmen­t. A bench headed by NGT Chairperso­n Justice Adarsh Kumar Goel noted that slope of the muck dumped at its Tapovan Vishnugad hydro power project in Chamoli was hazardousl­y double the standards with potential for erosion and dismissed the NTPC Ltd’s plea against the state PCB order.

“Erosion was already seen in terms of gully formation in down streams of the muck dumps. Thus, it is clear that the operative muck disposal sites were not being maintained as per the Ministry of Environmen­t and Forests laid down norms,” the bench said.

“In view of the above, there is no merit in the appeal as ‘Polluter Pays’ principle has been rightly invoked for damage to the environmen­t. Accordingl­y, the appeal is dismissed. Amount of compensati­on which may be recovered by the state pollution control board may be utilised for restoratio­n of the environmen­t,” the tribunal said. The state PCB had passed order under Section 33 A of the Water (Prevention and Control of Pollution) Act, 1974 (Water Act) requiring the appellant NTPC to pay compensati­on of Rs 57,96,000 on the polluter pays principle for the restoratio­n of the environmen­t.

The power major was found to have violated muck disposal site maintenanc­e norms