470 infra projects show Rs 4.38 L cr cost overruns

-

As many as 470 infrastruc­ture projects, each worth Rs 150 crore or more, have been hit by cost overruns totalling more than Rs 4.38 lakh crore, as per a report.

The Ministry of Statistics and Programme Implementa­tion monitors infrastruc­ture projects worth Rs 150 crore and above. Of the 1,737 such projects, 470 reported cost overruns and 525 were delayed.

“Total original cost of implementa­tion of the 1,737 projects was Rs 22,33,409.53 crore and their anticipate­d completion cost is likely to be 26,71,440.77 cr, which reflects overall cost overruns of 4,38,031.24 cr (19.61 per cent of original cost),” the ministry’s latest report for April 2021 said.

As per the report, the expenditur­e incurred on these projects till April 2021 is Rs 13,16,032.62 crore, which is 49.26 per cent of the anticipate­d cost of the projects.

However, the report said that the number of delayed projects decreases to 375 if the delay is calculated on the basis of the latest schedule of completion.

Further, for 988 projects neither the year of commission­ing nor the tentative gestation period has been reported.

Out of 525 delayed projects, 106 projects have an overall delay in the range of 1-12 months, 123 projects (13-24 months), 179 projects (25-60 months) and 117 projects (61 months and above).

The average time overrun in these 525 delayed projects is 45.63 months.

Reasons for time overruns as reported by various project implementi­ng agencies include delay in land acquisitio­n, delay in obtaining forest and environmen­t clearances, and lack of infrastruc­ture support and linkages.

Delay in tie-up for project financing, delay in finalisati­on of detailed engineerin­g, change in scope, delay in tendering, ordering and equipment supply, and law and order problems, among others, are the other reasons, the report said.

 ??  ??