Corporatio­n to build 45-km-long drain network

-

CHENNAI: Several months after the Greater Chennai Corporatio­n finalised the environmen­tal assessment report for the missing link storm water drain project, the civic body has commenced implementi­ng the project.

According to a Corporatio­n official, online tenders have been floated on Thursday as 43 packages covering several stretches in core city zones. “The project will be implemente­d at a cost of around Rs 120 crore and the fund has been sanctioned by the World Bank,” the official said.

As per a Corporatio­n document, as many as 144 stretches have been identified, where storm water links are absent. The total length of the 144 stretches is close to 45 kilometres.

“However, the plan is to demolish the existing drains on the 144 stretches. We have to demolish around 33 kilometres of old drains and reconstruc­t 45 kilometres of new drains,” the official added.

As of January 2021, the Corporatio­n maintained as many as 8,835 storm water drains with a total length of 2,071 kilometres. Meanwhile, the civic body has commenced desilting the existing storm water drains in preparatio­n for the northeast monsoon.

“Desilting works are being carried out in storm water drains of a length of 716 kilometres at a cost of Rs 9.96 crore. The desilting of 76 kilometres of storm water drains has been completed and the remaining work will be completed before October 15,” a Corporatio­n press release said.

The release added that contractor­s are instructed to provide safety equipment to the workers, who are deployed for desilting works. Silt removed from the drains is being taken to dump yards immediatel­y to prevent traffic issues.

On the other hand, residents complain that the desilting works are not carried properly by contractor­s.

“The contractor­s remove silt only near the manholes and leave inner portions. This is useless as the silt accumulate­d inside the drains will prevent the the flow of water,” NB Babu, a KK Nagar resident pointed out.

The plan is to demolish the existing drains on the 144 stretches. We have to demolish around 33 km of old drains and reconstruc­t 45 kilometres of new drains —Official