Hindustan Times (Amritsar)

Deadline to complete project by June-end looks implausibl­e

- Hitender Rao hrao@hindustant­imes.com ■

CHANDIGARH: The fresh rhetoric of the BJP government in Haryana that the much-delayed 136-km Kundli-Manesar-Palwal (KMP) expressway will become operationa­l by June 30 seems to be a ruse to avoid embarrassm­ent in view of the scheduled May 27 inaugurati­on of Kundli-Ghaziabad-Palwal (KGP) expressway by Prime Minister Narendra Modi.

The KGP has been completed in a record two-year period but its other half, the KMP e-way is only partially operationa­l. Though the 53-km Manesar-Palwal section got completed in March 2016 with the toll collection starting in July 2016, the 83-km Kundli-Manesar section is yet to be completed. The concession­aire has till May 20 achieved a physical progress of 83% for the Kundli-Manesar stretch.

On Tuesday, Haryana chief secretary DS Dhesi issued “strict directions” to officers to ensure that constructi­on work of the KMP expressway gets completed by June 30. Project status documents, however, show that the June 30 deadline seems farfetched.

UNFINISHED WORK

As per the official records, eight major structures on the e-way are yet to be completed. These include all the four railway overbridge­s (RoBs), three out of six major bridges and one grade separator.

The four ROBs are on DelhiAmbal­a, Delhi-R oh tak,G ur ga on Farrukhn agar and Delhi-Re wariJaip ur railway tracks .“All these structures would take time for completion.

The June 30 deadline looks implausibl­e, The concession­aire though has assured us that he will try to get it completed,’’ said an official in know of the project details.

Besides, works like setting up embankment­s, laying of granular sub-base, wet mix macadam, dense bituminous macadam, bituminous concrete for road work also is unfinished, official said.

ESSEL INFRA TO COMPLETE PROJECT

The HSIIDC had awarded the work of developmen­t of access controlled Kundli-Manesar section to M/s Essel Infraproje­cts on July 31,2015 on build, operate and transfer basis.

The agreement was executed on September 3, 2015. The initial completion deadline for the stretch was August 2018. However, due to delays in achieving financial closure, the project deadline was extended to February

2019. The concession­aire achieved financial closure on August 24, 2016, which is the commenceme­nt date of the project.

JINXED PROJECT

The e-way project, which was first allotted to KMP Expressway Ltd during the previous Congress regime, had got derailed, being mired in sticky legal and financial complicati­ons.

The previous Congress regime decided to go beyond the provisions of the concession agreement thereby terminatin­g the concession agreement with mutual consent and giving the contract for constructi­on of the project to a new company.

As a part of the bail-out plan, the Congress government decided terminatio­n payment of about Rs 1,300 crore to be paid to KMP Expressway­s and the project lenders by the new company which will get the contract to complete the project. However, the present BJP government rejected the move.

FOUR RAILWAY OVERBRIDGE­S, THREE MAJOR BRIDGES STILL UNFINISHED